CHAPTER NO.

19

PLUMBING SANITARY INSTALLATION


& GAS FITTINGS

DESCRIPTION OF ITEM:

Item No. 1 Providing and fitting glazed earthen ware water closet European Type,
excluding seat and cover.

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. European Type 1.00 No. 840.00 each 840.00


2 Rubber Sheet 0.222 Kg. 36.00 P. Kg. 7.99
3 Bolts & Nuts 4.00 Nos. 16.00 each 64.00
4 Cement 0.161 Bag 230.00 Bag 37.03
5 Sand 0.40 Cft. 350.00 % Cft. 1.41
6 Bajri 0.80 Cft. 1850.00 % Cft. 14.80

Total 965.23
Contractor's Profit & Overheads 20.00 Percent 193.05
Total 1,158.28

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Skilled Cooly 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10.00 Percent 33.00
Total 363.00
Contractor's Profit & Overheads 20.00 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 1267.18 Say 1267.20

Page 1
DESCRIPTION OF ITEM:

Item No. 1 Providing and fitting glazed earthen ware water closet European Type,
excluding seat and cover.

(ii) Coloured

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. European Type 1.00 No. 900.00 each 900.00


2 Rubber Sheet 0.222 Kg. 36.00 P. Kg. 7.99
3 Bolts & Nuts 4.00 Nos. 16.00 each 64.00
4 Cement 0.161 Bag 230.00 Bag 37.03
5 Sand 0.40 Cft. 350.00 % Cft. 1.41
6 Bajri 0.80 Cft. 1850.00 % Cft. 14.80

Total 1025.23
Contractor's Profit & Overheads 20.00 Percent 205.05
Total 1,230.28

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Skilled Cooly 1.00 No. 160.00 per day 160.00

Total 330.00
Sundries 10.00 Percent 33.00
Total 363.00
Contractor's Profit & Overheads 20.00 Percent 72.60
Total 435.60

ITEM RATES

Labour rate for Each Rs. 108.90 Say 108.90


Composite rate for Each Rs. 1339.18 Say 1339.20

Page 2
DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing double seat and cover only.

(i) Bakelite.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Seat and cover double (Bakelite) 1.00 No. 275.00 each 275.00

Total 275.00
Contractor's Profit & Overheads 20.00 Percent 55.00
Total 330.00

LABOURFor 48 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate for Each Rs. 1.17 Say 1.15


Composite rate for Each Rs. 331.17 Say 331.15

Page 3
DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing double seat and cover only.

(ii) Plastic.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Seat and cover double (Plastic) 1.00 No. 150.00 each 150.00

Total 150.00
Contractor's Profit & Overheads 20.00 Percent 30.00
Total 180.00

LABOURFor 48 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate for Each Rs. 1.17 Say 1.15


Composite rate for Each Rs. 181.17 Say 181.15

Page 4
DESCRIPTION OF ITEM:

Item No. 3 Providing and fitting glazed earthen ware water closet, squatter type
(orisa pattern) combined with foot rest.

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C Orisa pattern with foot rest 1.00 No. 675.00 each 675.00
2 Cement 0.021 Bag 230.00 Bag 4.83
3 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 680.03
Contractor's Profit & Overheads 20.00 Percent 136.01
Total 816.03

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10.00 Percent 24.00
Total 264.00
Contractor's Profit & Overheads 20.00 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 79.20 Say 79.20


Composite rate for Each Rs. 895.23 Say 895.25

Page 5
Item No. 3 Providing and fitting glazed earthen ware water closet, squatter type
(orisa pattern) combined with foot rest.

(ii) Coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C Orisa pattern with foot rest 1.00 No. 815.00 each 815.00
coloured
2 Cement 0.021 Bag 230.00 Bag 4.83
3 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 820.03
Contractor's Profit & Overheads 20.00 Percent 164.01
Total 984.03

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10.00 Percent 24.00
Total 264.00
Contractor's Profit & Overheads 20.00 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 79.20 Say 79.20


Composite rate for Each Rs. 1063.23 Say 1063.25

Page 6
DESCRIPTION OF ITEM:

Item No. 4 Providing and fitting white glazed earthen ware water closet, squatter type
with separate foot rest.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. squatter type 1.00 No. 450.00 each 450.00


2 Foot rest 2.00 Nos. 20.00 each 40.00

Total 490.00
Contractor's Profit & Overheads 20.00 Percent 98.00
Total 588.00

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10.00 Percent 24.00
Total 264.00
Contractor's Profit & Overheads 20.00 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 79.20 Say 79.20


Composite rate for Each Rs. 667.20 Say 667.20

Page 7
DESCRIPTION OF ITEM:

Item No. 5 Providing and fitting water closet squatter type of terrazzo concrete.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.C. squatter type of terrazzo concrete 1.00 No. 175.00 each 175.00
2 Cement 0.021 Bag 230.00 Bag 4.83
3 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 180.03
Contractor's Profit & Overheads 20.00 Percent 36.01
Total 216.03

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.50 No. 140.00 per day 70.00

Total 240.00
Sundries 10.00 Percent 24.00
Total 264.00
Contractor's Profit & Overheads 20.00 Percent 52.80
Total 316.80

ITEM RATES

Labour rate for Each Rs. 79.20 Say 79.20


Composite rate for Each Rs. 295.23 Say 295.25

Page 8
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 cm
(22" x 16"), including bracket set, waste pipe and waste coupling, etc.

(i) White with padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware wash hand basin 1.00 No. 885.00 each 885.00
2 Padestal 1.00 No. 250.00 each 250.00
3 Waste coupling, Bracket, Waste Pipe 1.00 No. 105.00 each 105.00

Total 1240.00
Contractor's Profit & Overheads 20.00 Percent 248.00
Total 1,488.00

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overheads 20.00 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 102.30 Say 102.30


Composite rate for Each Rs. 1590.30 Say 1590.30

Page 9
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 cm
(22" x 16"), including bracket set, waste pipe and waste coupling, etc.

(ii) Coloured with padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Earthen ware wash hand basin (coloured) 1.00 No. 1085.00 each 1085.00
2 Pedestal 1.00 No. 250.00 each 250.00
3 Waste coupling, Bracket Waste
Pipe 1.00 No. 105.00 each 105.00

Total 1440.00
Contractor's Profit & Overheads 20.00 Percent 288.00
Total 1,728.00

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overheads 20.00 Percent 68.20
Total 409.20

ITEM RATES

Labour rate for Each Rs. 102.30 Say 102.30


Composite rate for Each Rs. 1830.30 Say 1830.30

Page 10
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 cm
(22" x 16"), including bracket set, waste pipe and waste coupling, etc.

(iii) White without padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 W.H. Basin 1.00 No. 635.00 each 635.00


2 Waste coupling, Bracket, Waste Pipe 1.00 No. 105.00 each 105.00

Total 740.00
Contractor's Profit & Overheads 20.00 Percent 148.00
Total 888.00

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 978.75 Say 978.75

Page 11
DESCRIPTION OF ITEM:

Item No. 6 Providing and fitting glazed earthen ware wash hand basin 56 x 40 cm
(22" x 16"), including bracket set, waste pipe and waste coupling, etc.

(iv) Coloured without padestal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Coloured W.H. Basin 1.00 No. 735.00 each 735.00


2 Coupling, C.I. Bracket, Waste Pipe 1.00 No. 105.00 each 105.00

Total 840.00
Contractor's Profit & Overheads 20.00 Percent 168.00
Total 1,008.00

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 1098.75 Say 1098.75

Page 12
DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing stainless steel sink with drain board, size 120 x 60 cm
(48" x 24") including bracket set, waste pipe and waste coupling.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Stainless steel sink with drain


board 120 x 60 cm (48" x 24") 1.00 No. 1600.00 each 1600.00
2 Waste coupling 1.00 No. 75.00 each 75.00
3 Waste pipe 1.00 No. 15.00 each 15.00
4 Bracket 2.00 Nos. 25.00 each 50.00
5 Cement 0.042 Bag 230.00 Bag 9.66
6 Sand 0.130 Cft. 350.00 % Cft. 0.46

Total 1750.12
Contractor's Profit & Overheads 20.00 Percent 350.02
Total 2,100.14

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 2190.89 Say 2190.90

Page 13
DESCRIPTION OF ITEM:

Item No. 8 Providing and fitting terrazzo concrete sink 60 x 45 cm (24" x 18") with
drain board of mosaic including bracket set waste pipe and waste coupling.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Terrazzo concrete sink


60 x 45 cm (24" x 18") 1.00 No. 300.00 each 300.00
2 C.I. Bracket 2.00 Nos. 25.00 each 50.00
3 Waste coupling 1.00 No. 75.00 each 75.00
4 Waste pipe 1.00 No. 15.00 each 15.00
5 Cement 0.067 Bag 230.00 Bag 15.41
6 Sand 0.280 Cft. 350.00 % Cft. 0.98

Total 456.39
Contractor's Profit & Overheads 20.00 Percent 91.28
Total 547.67

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 638.42 Say 638.40

Page 14
DESCRIPTION OF ITEM:

Item No. 9 Providing and fixing glazed earthen ware sink, including bracket set, waste
pipe and waste coupling.

(i) 60 x 45 cm (24" x 18")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware sink 1.00 No. 520.00 each 520.00


2 C.I. Bracket 2.00 Nos. 25.00 each 50.00
3 Waste pipe 1.00 No. 15.00 each 15.00
4 Waste coupling 1.00 No. 75.00 each 75.00
5 Cement 0.053 Bag 230.00 Bag 12.19
6 Sand 0.144 Cft. 350.00 % Cft. 0.50

Total 672.69
Contractor's Profit & Overheads 20.00 Percent 134.54
Total 807.23

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 897.98 Say 898.00

Page 15
DESCRIPTION OF ITEM:

Item No. 9 Providing and fixing glazed earthen ware sink, including bracket set, waste
pipe and waste coupling.

(ii) 37.5 x 45 cm (15" x 18")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. Sink Size 37.5 x 45 cm


(15" x 18") 1.00 No. 350.00 each 350.00
2 Waste pipe 1.00 No. 15.00 each 15.00
3 Waste coupling 1.00 No. 75.00 each 75.00
4 C.I. Bracket 2.00 Nos. 25.00 each 50.00
6 Cement 0.053 Bag 230.00 Bag 12.19
7 Sand 0.144 Cft. 350.00 % Cft. 0.50

Total 502.69
Contractor's Profit & Overheads 20.00 Percent 100.54
Total 603.23

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 693.98 Say 694.00

Page 16
DESCRIPTION OF ITEM:

Item No. 10 Providing and fixing glazed earthen ware Flat Back Urinal.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. flat Back Urinal Complete set 1.00 No. 400.00 each 400.00
2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw (75 mm) 3" long 2.00 Nos. 0.44 each 0.88

Total 401.88
Contractor's Profit & Overheads 20.00 Percent 80.38
Total 482.26

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 56.10 Say 56.10


Composite rate for Each Rs. 538.36 Say 538.35

Page 17
DESCRIPTION OF ITEM:

Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern 13.63
litres (3 gallons) capacity, including bracket set, copper connection, etc.

(i) White

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 3 gallon


or 13.63 litters 1.00 No. 700.00 each 700.00
2 C.I. Bracket one pair 20.00 per pair 20.00
3 Copper connection with check nut 1.00 No. 30.00 each 30.00
4 Cement 0.04 Bag 230.00 Bag 9.20
5 Sand 0.23 Cft. 350.00 % Cft. 0.81

Total 760.01
Contractor's Profit & Overheads 20.00 Percent 152.00
Total 912.01

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 1002.76 Say 1002.75

Page 18
DESCRIPTION OF ITEM:

Item No. 11 Providing and fitting glazed earthen ware low down flushing cistern 13.63
litres (3 gallons) capacity, including bracket set, copper connection, etc.

(ii) Coloured

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 1.00 No. 800.00 each 800.00


2 C.I. Bracket one pair 20.00 per pair 20.00
3 Copper connection with check nut 1.00 No. 30.00 each 30.00
4 Cement 0.04 Bag 230.00 Bag 9.20
5 Sand 0.23 Cft. 350.00 % Cft. 0.81

Total 860.01
Contractor's Profit & Overheads 20.00 Percent 172.00
Total 1,032.01

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 1122.76 Say 1122.75

Page 19
DESCRIPTION OF ITEM:

Item No. 12 Providing and fitting plastic made low down flushing cistern 13.63 litres
(3 gallons) capacity, including bracket set, copper connection, etc.,
complete.

Coloured & White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Low down flushing cistern 1.00 No. 450.00 each 450.00


2 C.I. Bracket one pair 20.00 per pair 20.00
3 Copper connection with check nut 1.00 No. 30.00 each 30.00
4 Cement 0.04 Bag 230.00 Bag 9.20
5 Sand 0.23 Cft. 350.00 % Cft. 0.81

Total 510.01
Contractor's Profit & Overheads 20.00 Percent 102.00
Total 612.01

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each (White) Rs. 702.76 Say 702.75
Composite rate for Each (Coloured) Rs. 687.45 Say 687.45

Page 20
DESCRIPTION OF ITEM:

Item No. 13 Providing and fixing white enamelled cast iron low down flushing cistern
13.63 litters (3 gallons) capacity, including bracket set, copper connection
etc.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 White enamelled C.I low down


flushing cistern 3 gallons or
13.63 litters capacity including
all assessaries. 1.00 No. 760.00 each 760.00
2 C.I. Bracket one pair 20.00 per pair 20.00
3 Cement 0.021 Bag 230.00 Bag 4.83
4 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 785.03
Contractor's Profit & Overheads 20.00 Percent 157.01
Total 942.03

LABOURFor 4 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 275.00
Sundries 10.00 Percent 27.50
Total 302.50
Contractor's Profit & Overheads 20.00 Percent 60.50
Total 363.00

ITEM RATES

Labour rate for Each Rs. 90.75 Say 90.75


Composite rate for Each Rs. 1032.78 Say 1032.80

Page 21
DESCRIPTION OF ITEM:

Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost of
bracket set copper connection etc.

(i) 13.63 litters (3 gallons) capacity.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. High level flushing cistern 1.00 No. 580.00 each 580.00
13.63 letters or 3 gallon
capacity including
accessories.
2 C.I. Bracket one pair 20.00 per pair 20.00
3 Cement 0.021 Bag 230.00 Bag 4.83
4 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 605.03
Contractor's Profit & Overheads 20.00 Percent 121.01
Total 726.03

LABOURFor 4 Nos.

1 Plumber 1.10 Nos. 170.00 per day 187.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 292.00
Sundries 10.00 Percent 29.20
Total 321.20
Contractor's Profit & Overheads 20.00 Percent 64.24
Total 385.44

ITEM RATES

Labour rate for Each Rs. 96.36 Say 96.35


Composite rate for Each Rs. 822.39 Say 822.40

Page 22
DESCRIPTION OF ITEM:

Item No. 14 Providing and fixing C.I. highlevel flushing cistern including cost of
bracket set copper connection etc.

(ii) 4.55 liters (1 gallon) capacity.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. High level flushing cistern 1.00 No. 432.00 each 432.00
I/C all accessaries
2 C.I. Bracket one pair 20.00 per pair 20.00
3 Cement 0.021 Bag 230.00 Bag 4.83
4 Sand 0.056 Cft. 350.00 % Cft. 0.20

Total 457.03
Contractor's Profit & Overheads 20.00 Percent 91.41
Total 548.43

LABOURFor 4 Nos.

1 Plumber 1.10 Nos. 170.00 per day 187.00


2 Cooly un-skilled 0.75 No. 140.00 per day 105.00

Total 292.00
Sundries 10.00 Percent 29.20
Total 321.20
Contractor's Profit & Overheads 20.00 Percent 64.24
Total 385.44

ITEM RATES

Labour rate for Each Rs. 96.36 Say 96.35


Composite rate for Each Rs. 644.79 Say 644.80

Page 23
DESCRIPTION OF ITEM:

Item No. 15 Providing and fixing, chromium plated soap dish.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromuim plated soap dish 1.00 No. 90.00 each 90.00


2 Gutties Plastic 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 3/4" 2.00 Nos. 1.68 P. Doz 0.28

Total 91.28
Contractor's Profit & Overheads 20.00 Percent 18.26
Total 109.54

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 5.61 Say 5.60


Composite rate for Each Rs. 115.15 Say 115.15

Page 24
DESCRIPTION OF ITEM:

Item No. 16 Providing and fitting, glazed earthen ware soap dish.

(i) White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed earthen ware soap dish 1.00 No. 110.00 each 110.00
2 Gutties Plastic 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 3/4" 2.00 Nos. 1.68 P. Doz 0.28

Total 111.28
Contractor's Profit & Overheads 20.00 Percent 22.26
Total 133.54

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 5.61 Say 5.60


Composite rate for Each Rs. 139.15 Say 139.15

Page 25
DESCRIPTION OF ITEM:

Item No. 16 Providing and fitting, glazed earthen ware soap dish.

(ii) Soap dish coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Soap dish coloured 1.00 No. 120.00 each 120.00


2 Gutties Plastic 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 3/4" 2.00 Nos. 1.68 P. Doz 0.28

Total 121.28
Contractor's Profit & Overheads 20.00 Percent 24.26
Total 145.54

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 5.61 Say 5.60


Composite rate for Each Rs. 151.15 Say 151.15

Page 26
DESCRIPTION OF ITEM:

Item No. 17 Providing and fixing chromium plated toilet paper holder.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Toilet holder 1.00 No. 90.00 each 90.00


2 Gutties Plastic 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 3/4" 4.00 Nos. 1.68 P. Doz 0.56
4 Cement 0.010 Bag 230.00 Bag 2.30
5 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 94.07
Contractor's Profit & Overheads 20.00 Percent 18.81
Total 112.88

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 120.36 Say 120.35

Page 27
DESCRIPTION OF ITEM:

Item No. 18 Providing and fixing chromium plated towel rail.

(i) 60 cm (24") long and 2 cm (3/4") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Towel rail 1.00 No. 150.00 each 150.00


2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 4.00 Nos. 1.68 P. Doz 0.56

Total 151.56
Contractor's Profit & Overheads 20.00 Percent 30.31
Total 181.87

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 189.35 Say 189.35

Page 28
DESCRIPTION OF ITEM:

Item No. 18 Providing and fixing chromium plated towel rail.

(ii) 50 cm (20") long and 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. Towel rail 50 cm (20") long


1.5 cm (½" dia) 1.00 No. 100.00 each 100.00
2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screws 4.00 Nos. 1.68 P. Doz 0.56

Total 101.56
Contractor's Profit & Overheads 20.00 Percent 20.31
Total 121.87

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 129.35 Say 129.35

Page 29
DESCRIPTION OF ITEM:

Item No. 19 Providing and fixing looking glass 55 x 40 cm (22" x 16") size and 5 mm
thick first quality.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Looking glass 5 mm thick


55 x 40 cm (22" x 16") 1.00 No. 328.00 each 328.00
2 Gutties 4.00 Nos. 6.00 P. Doz 2.00
3 Screw
4.00 Nos. 1.68 P. Doz 0.56

Total 330.56
Contractor's Profit & Overheads 20.00 Percent 66.11
Total 396.67

LABOURFor 16 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 14.03 Say 14.05


Composite rate for Each Rs. 410.70 Say 410.70

Page 30
DESCRIPTION OF ITEM:

Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm thick
glass.

(i) With chromium plated brackets and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glass 60 x 13 cm (24" X 5")


with 5 mm thick glass 1.00 No. 60.00 each 60.00
2 Chromium plated brackets and railing 1.00 No. 50.00 each 50.00
3 Screws 4.00 Nos. 1.68 P. Doz 0.56
4 Gutties 2.00 Nos. 6.00 P. Doz 1.00
5 Cement 0.010 Bag 230.00 Bag 2.30
6 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 114.07
Contractor's Profit & Overheads 20.00 Percent 22.81
Total 136.88

LABOURFor 16 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly skilled 0.25 No. 160.00 per day 40.00

Total 210.00
Sundries 10.00 Percent 21.00
Total 231.00
Contractor's Profit & Overheads 20.00 Percent 46.20
Total 277.20

ITEM RATES

Labour rate for Each Rs. 17.33 Say 17.35


Composite rate for Each Rs. 154.21 Say 154.20

Page 31
DESCRIPTION OF ITEM:

Item No. 20 Providing and fixing glass shelf 60 x 13 cm (24" x 5") with 5 mm thick
glass.

(ii) Glass Shelf only without chromium plated brackets and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glass Shelf 1.00 No. 60.00 each 60.00

Total 60.00
Contractor's Profit & Overheads 20.00 Percent 12.00
Total 72.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 83.22 Say 83.20

Page 32
DESCRIPTION OF ITEM:

Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5") with
chromium plated bracket and railing.

(i) White.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. shelf 60 x 13 cm (24" x 5")


with C.P bracket and railing. 1.00 No. 150.00 each 150.00
2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw 4.00 Nos. 1.68 P. Doz 0.56
4 Cement 0.010 Bag 230.00 Bag 2.30
5 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 154.07
Contractor's Profit & Overheads 20.00 Percent 30.81
Total 184.88

LABOURFor 16 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly skilled 0.25 No. 160.00 per day 40.00

Total 210.00
Sundries 10.00 Percent 21.00
Total 231.00
Contractor's Profit & Overheads 20.00 Percent 46.20
Total 277.20

ITEM RATES

Labour rate for Each Rs. 17.33 Say 17.35


Composite rate for Each Rs. 202.21 Say 202.20

Page 33
DESCRIPTION OF ITEM:

Item No. 21 Providing and fitting glazed earthen ware shelf 60 x 13 cm (24" x 5") with
chromium plated bracket and railing.

(ii) Coloured.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.E. shelf 60 x 13 cm (24" x 5")


with C.P bracket and railing. 1.00 No. 160.00 each 160.00
2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw 4.00 Nos. 1.68 P. Doz 0.56
4 Cement 0.010 Bag 230.00 Bag 2.30
5 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 164.07
Contractor's Profit & Overheads 20.00 Percent 32.81
Total 196.88

LABOURFor 16 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly skilled 0.25 No. 160.00 per day 40.00

Total 210.00
Sundries 10.00 Percent 21.00
Total 231.00
Contractor's Profit & Overheads 20.00 Percent 46.20
Total 277.20

ITEM RATES

Labour rate for Each Rs. 17.33 Say 17.35


Composite rate for Each Rs. 214.21 Say 214.20

Page 34
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(i) Plastic soap dish.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic soap dish 1.00 No. 40.00 each 40.00


2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw 2.00 Nos. 1.68 P. Doz 0.28
4 Cement 0.005 Bag 230.00 Bag 1.15
5 Sand 0.030 Cft. 350.00 % Cft. 0.11

Total 42.53
Contractor's Profit & Overheads 20.00 Percent 8.51
Total 51.04

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 5.61 Say 5.60


Composite rate for Each Rs. 56.65 Say 56.65

Page 35
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(ii) Plastic toilet paper holder.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic toilet paper holder 1.00 No. 85.00 each 85.00


2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw 4.00 Nos. 3.25 P. Doz 1.08
4 Cement 0.010 Bag 230.00 Bag 2.30
5 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 89.59
Contractor's Profit & Overheads 20.00 Percent 17.92
Total 107.51

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 114.99 Say 115.00

Page 36
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(iii) Plastic towel rail.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic towel rail 1.00 No. 60.00 each 60.00


2 Gutties 2.00 Nos. 6.00 P. Doz 1.00
3 Screw 4.00 Nos. 3.25 P. Doz 1.08
4 Cement 0.010 Bag 230.00 Bag 2.30
5 Sand 0.06 Cft. 350.00 % Cft. 0.21

Total 64.59
Contractor's Profit & Overheads 20.00 Percent 12.92
Total 77.51

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 84.99 Say 85.00

Page 37
DESCRIPTION OF ITEM:

Item No. 22 Providing and fitting.

(iv) Plastic Shelf with bracket and railing.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Plastic shelf with railing 1.00 No. 50.00 each 50.00


2 Bracket 2.00 Nos. 2.00 each 4.00
3 Gutties 2.00 Nos. 6.00 P. Doz 1.00
4 Screw 4.00 Nos. 3.25 P. Doz 1.08
5 Cement 0.004 Bag 230.00 Bag 0.92
6 Sand 0.020 Cft. 350.00 % Cft. 0.07

Total 57.07
Contractor's Profit & Overheads 20.00 Percent 11.41
Total 68.49

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 75.97 Say 75.95

Page 38
DESCRIPTION OF ITEM:

Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.

(i) 2 cm (¾").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (¾") Pillar Cock 1.00 No. 180.00 each 180.00

Total 180.00
Contractor's Profit & Overheads 20.00 Percent 36.00
Total 216.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 223.48 Say 223.50

Page 39
DESCRIPTION OF ITEM:

Item No. 23 Providing and fixing chromium plated pillar - cock, heavy.

(ii) 1.5 cm (½").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 15 cm (½") Pillar Cock heavy 1.00 No. 150.00 each 150.00

Total 150.00
Contractor's Profit & Overheads 20.00 Percent 30.00
Total 180.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 187.48 Say 187.50

Page 40
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing chromium plated stop Cock Heavy.

(i) 2 cm (¾").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (¾") stop cock 1.00 No. 200.00 each 200.00

Total 200.00
Contractor's Profit & Overheads 20.00 Percent 40.00
Total 240.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 247.48 Say 247.50

Page 41
DESCRIPTION OF ITEM:

Item No. 24 Providing and fixing chromium plated stop Cock Heavy.

(ii) 1.5 cm (½").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (½") stop cock 1.00 No. 165.00 each 165.00

Total 165.00
Contractor's Profit & Overheads 20.00 Percent 33.00
Total 198.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 205.48 Say 205.50

Page 42
DESCRIPTION OF ITEM:

Item No. 25 Providing and fixing underground stop cock 13 mm (½") with chromium
plated cover.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Underground stop cock with chromium


plated cover 1.00 No. 200.00 each 200.00
2 Gutties 4.00 Nos. 6.00 P. Doz 2.00
3 Screw 4.00 Nos. 1.68 P. Doz 0.56
4 Cement 0.022 Bag 230.00 Bag 5.06
5 Sand 0.060 Cft. 350.00 % Cft. 0.21

Total 207.62
Contractor's Profit & Overheads 20.00 Percent 41.52
Total 249.14

LABOURFor 30 Nos.

1 Plumber 1.25 No. 170.00 per day 212.50


2 Cooly un-killed 0.25 No. 140.00 per day 35.00

Total 247.50
Sundries 10.00 Percent 24.75
Total 272.25
Contractor's Profit & Overheads 20.00 Percent 54.45
Total 326.70

ITEM RATES

Labour rate for Each Rs. 10.89 Say 10.90


Composite rate for Each Rs. 260.03 Say 260.05

Page 43
DESCRIPTION OF ITEM:

Item No. 26 Providing and fixing chromium plated bib cock.

(i) 2 cm (¾").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 2 cm (¾") bib cock 1.00 No. 150.00 each 150.00

Total 150.00
Contractor's Profit & Overheads 20.00 Percent 30.00
Total 180.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 187.48 Say 187.50

Page 44
DESCRIPTION OF ITEM:

Item No. 26 Providing and fixing chromium plated bib cock.

(ii) 1.5 cm (½").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (½") bib cock 1.00 No. 120.00 each 120.00

Total 120.00
Contractor's Profit & Overheads 20.00 Percent 24.00
Total 144.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 151.48 Say 151.50

Page 45
DESCRIPTION OF ITEM:

Item No. 27 Providing and fixing chromium plated tee stop cock 1.5 cm (½").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (½") Chromium plated


tee stop cock 1.00 No. 85.00 each 85.00

Total 85.00
Contractor's Profit & Overheads 20.00 Percent 17.00
Total 102.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 109.48 Say 109.50

Page 46
DESCRIPTION OF ITEM:

Item No. 28 Providing and fixing, chromium plated shower rose.

(i) 1.5 cm x 10 cm (½" x 4")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated shower rose


1.5 cm x 10 cm (½" x 4") 1.00 No. 150.00 each 150.00

Total 150.00
Contractor's Profit & Overheads 20.00 Percent 30.00
Total 180.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 187.48 Say 187.50

Page 47
DESCRIPTION OF ITEM:

Item No. 28 Providing and fixing, chromium plated shower rose.

(ii) 2 cm x 15 cm (¾" x 6")

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated shower rose


2 cm x 15 cm (¾" x 6") 1.00 No. 200.00 each 200.00

Total 200.00
Contractor's Profit & Overheads 20.00 Percent 40.00
Total 240.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 247.48 Say 247.50

Page 48
DESCRIPTION OF ITEM:

Item No. 29 Providing & Fixing, chromium plated mixing valve, for wash hand basin,
sinks or shower.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Chromium plated mixing valve 1.00 No. 525.00 each 525.00

Total 525.00
Contractor's Profit & Overheads 20.00 Percent 105.00
Total 630.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 9.35 Say 9.35


Composite rate for Each Rs. 639.35 Say 639.35

Page 49
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(i) Peet valve 3 cm (1¼") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gun Metal Peet Valve 1.00 No. 265.00 each 265.00

Total 265.00
Contractor's Profit & Overheads 20.00 Percent 53.00
Total 318.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 329.22 Say 329.20

Page 50
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(ii) Peet valve 4 cm (1½") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 4 cm (1½") dia 1.00 No. 310.00 each 310.00

Total 310.00
Contractor's Profit & Overheads 20.00 Percent 62.00
Total 372.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 383.22 Say 383.20

Page 51
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(iii) G.M. Peet Valve 5 cm (2" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 5 cm (2" dia) 1.00 No. 380.00 each 380.00

Total 380.00
Contractor's Profit & Overheads 20.00 Percent 76.00
Total 456.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 467.22 Say 467.20

Page 52
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(iv) G.M. Peet Valve 6.5 cm (2½") dia.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 6.5 cm (2½" dia) 1.00 No. 430.00 each 430.00

Total 430.00
Contractor's Profit & Overheads 20.00 Percent 86.00
Total 516.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 527.22 Say 527.20

Page 53
DESCRIPTION OF ITEM:

Item No. 30 Providing and fixing gun metal peet/gate valve (screwed).

(v) G.M. Peet Valve 7.5 cm (3" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 G.M. Peet Valve 7.5 cm (3" dia) 1.00 No. 490.00 each 490.00

Total 490.00
Contractor's Profit & Overheads 20.00 Percent 98.00
Total 588.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 599.22 Say 599.20

Page 54
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck cock
1.5 cm (½" dia).

(i) Single way 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 225.00 each 225.00

Total 225.00
Contractor's Profit & Overheads 20.00 Percent 45.00
Total 270.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 277.48 Say 277.50

Page 55
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck cock
1.5 cm (½" dia).

(ii) Two way 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 325.00 each 325.00

Total 325.00
Contractor's Profit & Overheads 20.00 Percent 65.00
Total 390.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 11.22 Say 11.20


Composite rate for Each Rs. 401.22 Say 401.20

Page 56
DESCRIPTION OF ITEM:

Item No. 31 Providing and fitting, Chromium plated or brass oxidised, swan neck cock
1.5 cm (½" dia).

(iii) Three way 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 425.00 each 425.00

Total 425.00
Contractor's Profit & Overheads 20.00 Percent 85.00
Total 510.00

LABOURFor 15 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 14.96 Say 14.95


Composite rate for Each Rs. 524.96 Say 524.95

Page 57
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing, union brass cock.

(i) 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 52.00 each 52.00

Total 52.00
Contractor's Profit & Overheads 20.00 Percent 10.40
Total 62.40

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 69.88 Say 69.90

Page 58
DESCRIPTION OF ITEM:

Item No. 32 Providing and fixing, union brass cock.

(ii) 2 cm (¾" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Cost of cock 1.00 No. 80.00 each 80.00

Total 80.00
Contractor's Profit & Overheads 20.00 Percent 16.00
Total 96.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 7.48 Say 7.50


Composite rate for Each Rs. 103.48 Say 103.50

Page 59
DESCRIPTION OF ITEM:

Item No. 33 Providing and fixing floor trap of Cast Iron including concrete chamber
all-round and C.I grating.
(i) 10 x 5 cm (4" x 2").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I floor trap including grating


size 10 x 5 cm (4" x 2") 1.00 No. 90.00 each 90.00
2 Cement 0.065 Bag 230.00 Bag 14.95
3 Sand 0.160 Cft. 350.00 % Cft. 0.56
4 Crushed Stone 0.310 Cft. 1850.00 % Cft. 5.74

Total 111.25
Contractor's Profit & Overheads 20.00 Percent 22.25
Total 133.49

LABOURFor 10 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 22.44 Say 22.45


Composite rate for Each Rs. 155.93 Say 155.95

Page 60
DESCRIPTION OF ITEM:

Item No. 33 Providing and fixing floor trap of Cast Iron including concrete chamber
all-round and C.I grating.

(ii) Floor trap size 10 x 7.5 cm (4" x 3").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I floor trap including grating


size 10 x 7.5 cm (4" x 3") 1.00 No. 105.00 each 105.00
2 Cement 0.065 Bag 230.00 Bag 14.95
3 Sand 0.160 Cft. 350.00 % Cft. 0.56
4 Crushed Stone 0.310 Cft. 1850.00 % Cft. 5.74

Total 126.25
Contractor's Profit & Overheads 20.00 Percent 25.25
Total 151.49

LABOURFor 10 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 22.44 Say 22.45


Composite rate for Each Rs. 173.93 Say 173.95

Page 61
DESCRIPTION OF ITEM:

Item No. 34 Providing and fitting P-trap including concrete chamber with cast iron
gully grating.

(i) Cast Iron 10 cm (4" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. P-trap 10 cm (4" dia) 1.00 No. 135.00 each 135.00


2 Cement 0.016 Bag 230.00 Bag 3.68
3 Sand 0.040 Cft. 350.00 % Cft. 0.14
4 Crushed Stone 0.081 Cft. 1850.00 % Cft. 1.50

Total 140.32
Contractor's Profit & Overheads 20.00 Percent 28.06
Total 168.38

LABOURFor 12 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES
Labour rate for Each Rs. 18.70 Say 18.70
Composite rate for Each Rs. 187.08 Say 187.10

Page 62
DESCRIPTION OF ITEM:

Item No. 34 Providing and fitting P-trap.

(ii) Glazed 10 cm (4" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Glazed Pee trap 10 cm (4" dia) 1.00 No. 40.00 each 40.00
2 Cement 0.016 Bag 230.00 Bag 3.68
3 Sand 0.040 Cft. 350.00 % Cft. 0.14
4 Crushed Stone 0.081 Cft. 1850.00 % Cft. 1.50

Total 45.32
Contractor's Profit & Overheads 20.00 Percent 9.06
Total 54.38

LABOURFor 12 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate for Each Rs. 18.70 Say 18.70


Composite rate for Each Rs. 73.08 Say 73.10

Page 63
DESCRIPTION OF ITEM:

Item No. 35 Providing and fitting 10 cm (4") gully trap, including cement cncrete,
costof PVC grating 15 x 15 cm (6" x 6") and Masonry chamber 30 x 30
cm(12" x 12").

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Concrete Gully trap 1.00 No. 100.00 each 100.00


2 P.V.C grating 15 x 15 cm (6" x 6") 1.00 No. 25.00 each 25.00
3 Cement 0.119 Bag 230.00 Bag 27.37
4 Sand 0.190 Cft. 350.00 % Cft. 0.67
5 Crushed Stone 0.323 Cft. 1850.00 % Cft. 5.98
6 Brick 20.00 No. 1200.00 %0 No. 24.00

Total 183.01
Contractor's Profit & Overheads 20.00 Percent 36.60
Total 219.61

LABOURFor 8 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES
Labour rate for Each Rs. 28.05 Say 28.05
Composite rate for Each Rs. 247.66 Say 247.65

Page 64
DESCRIPTION OF ITEM:

Item No. 36 (i) Providing & fitting cast iron soil pipe with:

(a) Lead caulked, yarn joint 10 cm (4") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil 10 cm (4") dia 2.00 Metre 350.00 per metre 700.00
Cost of lead joint
a) Lead 2.36 Kg. 20.00 Per Kg. 47.20
b) Yarn 0.25 Lbs 16.00 Lbs 4.00
c) Fuel wood 1.45 Kg. 2.75 Per Kg. 3.99

Total 755.19
Contractor's Profit & Overheads 20.00 Percent 151.04
Total 906.23
Material cost/metre
906.23 = 453.11 453.11
2

LABOURFor 20 Metre

1 Plumber/Mason 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10.00 Percent 45.00
Total 495.00
Contractor's Profit & Overheads 20.00 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 29.70 Say 29.70


Labour rate per Ft. Rs. 9.05 Say 9.05

Composite rate per Metre Rs. 482.81 Say 482.80


Composite rate per Ft. Rs. 147.20 Say 147.20

Page 65
DESCRIPTION OF ITEM:

Item No. 36 (i) Providing & fitting cast iron soil pipe with:

(b) Lead caulked, yarn joint 5 cm (2") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil 5 cm (2") dia 2.00 Metre 200.00 per metre 400.00
Cost of lead joint
a) Lead 0.23 Kg. 20.00 Per Kg. 4.60
b) Yarn 0.13 Lbs 16.00 Lbs 2.00
c) Fuel wood 0.73 Kg. 2.75 Per Kg. 2.01

Total 408.61
Contractor's Profit & Overheads 20.00 Percent 81.72
Total 490.33
Material cost/metre
449.46 = 224.73 245.1645
2

LABOURFor 50 Metre

1 Plumber/Mason 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 2.00 No. 140.00 per day 280.00

Total 450.00
Sundries 10.00 Percent 45.00
Total 495.00
Contractor's Profit & Overheads 20.00 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 11.88 Say 11.90


Labour rate per Ft. Rs. 3.62 Say 3.60

Composite rate per Metre Rs. 257.04 Say 257.05


Composite rate per Ft. Rs. 78.37 Say 78.35

Page 66
DESCRIPTION OF ITEM:

Item No. 36 (ii) Cement caulked joint.

(a) 10 cm (4") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil pipe 10 cm (4") dia 2.00 Meter 350.00 per metre 700.00
2 Yarn 0.25 Lbs 16.00 Lbs 4.00
3 Cement 0.022 Bag 230.00 Bag 5.06

Total 709.06
Contractor's Profit & Overheads 20.00 Percent 141.81
Total 850.87
Material cost per metre 425.44

LABOURFor 40 Metres

1 Mason/Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 6.77 Say 6.75


Labour rate per Ft. Rs. 2.06 Say 2.05

Composite rate per metre Rs. 432.20 Say 432.20


Composite rate per Ft. Rs. 131.77 Say 131.75

Page 67
DESCRIPTION OF ITEM:

Item No. 36 (ii) Cement caulked joint.

(b) 5 cm (2") dia.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE)

1 C.I Soil pipe 5 cm (2") dia 2.00 Metre 200.00 per metre 400.00
2 Yarn 0.13 Lbs 16.00 Lbs 2.00
3 Cement 0.011 Bag 230.00 Bag 2.53

Total 404.53
Contractor's Profit & Overheads 20.00 Percent 80.91
Total 485.44
Material cost per metre 242.72

LABOURFor 100 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 2.71 Say 2.70


Labour rate per Ft. Rs. 0.83 Say 0.85

Composite rate per metre Rs. 245.42 Say 245.40


Composite rate per Ft. Rs. 74.82 Say 74.80

Page 68
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint, including all
specials.

(i) 6 cm i/d.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 3 Metre


MATERIAL

1 A.C Soil Pipe 3.00 Metre 57.80 per metre 173.40


2 Specials @ 10% 17.34
3 Yarn 0.25 Lbs 16.00 Lbs 4.00
4 Cement 0.022 Bag 230.00 Bag 5.06

Total 199.80
Contractor's Profit & Overheads 20.00 Percent 39.96
Total 239.76
Material cost per metre 79.92

LABOURFor 50 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 5.41 Say 5.40


Labour rate per Ft. Rs. 1.65 Say 1.65

Composite rate per Metre Rs. 85.33 Say 85.35


Composite rate per Ft. Rs. 26.02 Say 26.00

Page 69
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(ii) 7.5 cm (3" dia).

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 3 METRE

1 A.C Soil Pipe 3.00 Metre 147.36 per metre 442.08


2 Specials @ 10% 44.21
3 Yarn 0.25 Lbs 16.00 Lbs 4.00
4 Cement 0.022 Bag 230.00 Bag 5.06

495.35
Contractor's Profit & Overheads 20.00 Percent 99.07
Total 594.42
Material cost per metre 198.14

LABOURFor 45 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 6.01 Say 6.00


Labour rate per Ft. Rs. 1.83 Say 1.85

Composite rate per Metre Rs. 204.15 Say 204.15


Composite rate per Ft. Rs. 62.24 Say 62.25

Page 70
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(iii) 10 cm (4" dia).

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 3 METRE

1 A.C Soil Pipe 4.00 Metre 215.89 per metre 863.56


2 Specials @ 10% 86.36
3 Yarn 0.31 Lbs 16.00 Lbs 4.96
4 Cement 0.028 Bag 230.00 Bag 6.44

961.32
Contractor's Profit & Overheads 20.00 Percent 192.26
Total 1,153.58
Material cost per metre 288.39

LABOURFor 40 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 6.77 Say 6.75


Labour rate per Ft. Rs. 2.06 Say 2.05

Composite rate per Metre Rs. 295.16 Say 295.15


Composite rate per Ft. Rs. 89.99 Say 90.00

Page 71
DESCRIPTION OF ITEM:

Item No. 37 Providing and fitting, A.C Soil pipe with cement caulked joint,
including all specials.

(iv) 15 cm (6" dia) A/C Soil Pipe.

Detail Unit Rate (Metric) per R.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 4 METRE

1 A.C Soil pipe 50 cm (6" dia) 4.00 Metre 300.58 per metre 1202.32
2 Special at 10% 120.23
3 Yarn 0.500 Lbs 16.00 Lbs 8.00
4 Cement 0.044 Bag 230.00 Bag 10.12

1340.67
Contractor's Profit & Overheads 20.00 Percent 268.13
Total 1,608.81
Material cost per metre 402.20

LABOURFor 30 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Metre Rs. 9.02 Say 9.00


Labour rate per Ft. Rs. 2.75 Say 2.75

Composite rate per Metre Rs. 411.22 Say 411.20


Composite rate per Ft. Rs. 125.37 Say 125.35

Page 72
DESCRIPTION OF ITEM:

Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar, cross, etc.
plain type.

(i) Lead Caulked Joint.

Detail Unit Rate (British System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 5 KG.

1 C.I. bend 100 mm (4" dia) 5.00 kg 30.00 per kg 150.00


2 Lead 0.91 kg 20.00 per kg 18.20
3 Fuel 2.91 kg 2.75 per kg 8.00
4 Yarn 0.50 lbs 16.00 per lbs 8.00

Total 184.20
Contractor's Profit & Overheads 20.00 Percent 36.84
Total cost for 5 kg 221.04
Material cost per Kg 44.21

LABOURFOR 60 NOS.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 1.20 Nos. 140.00 per day 168.00

Total 338.00
Sundries 10.00 Percent 33.80
Total 371.80
Contractor's Profit & Overheads 20.00 Percent 74.36
Total 446.16

ITEM RATES

Labour rate per Kg Rs. 7.44 Say 7.45


Composite rate per Kg Rs. 51.64 Say 51.65

Page 73
DESCRIPTION OF ITEM:

Item No. 38 Providing and fitting cast iron specials, such as tee bend, collar,
cross, etc. plain type.

(ii) Cement caulked joint.

Detail Unit Rate (British System) per Kg

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 5 KG.

1 C.I. bend 10 cm (4" dia) 5.00 kg 30.00 per kg 150.00


2 Yarn 0.50 lbs 16.00 per lbs 8.00
3 Cement 0.040 Bag 230.00 Bag 9.20
4 Sand 0.230 Cft. 350.00 % Cft. 0.81

Total 168.01
Contractor's Profit & Overheads 20.00 Percent 33.60
Total 201.61
Material cost per Kg 40.32

LABOURFor 90 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00


2 Cooly un-skilled 1.00 No. 140.00 per day 140.00

Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overheads 20.00 Percent 68.20
Total 409.20

ITEM RATES

Labour rate per Kg Rs. 4.55 Say 4.55


Composite rate per Kg Rs. 44.87 Say 44.85

Page 74
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. complete.

(i) 30 cm (12" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Manhole cover 30 cm (12" dia) 1.00 No. 120.00 each 120.00

Total 120.00
Contractor's Profit & Overheads 20.00 Percent 24.00
Total 144.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 155.22 Say 155.20

Page 75
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. complete.

(ii) 45 cm (18" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I. manhole cover with frame 45 cm 1.00 No. 220.00 each 220.00
(18" dia)

Total 220.00
Contractor's Profit & Overheads 20.00 Percent 44.00
Total 264.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 275.22 Say 275.20

Page 76
DESCRIPTION OF ITEM:

Item No. 39 Supply and fitting of cast iron Manhole cover with frame, etc. complete.

(iii) C.I. Manhole cover 60 cm (24" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.I manhole cover with frame 60 cm (24" dia) 1.00 No. 400.00 each 400.00

Total 400.00
Contractor's Profit & Overheads 20.00 Percent 80.00
Total 480.00

LABOURFor 15 Nos.

1 2 1.00 No. 170.00 per day 170.00


2 Helper (Cooly) 0.25 No. 140.00 per day 35.00

Total 205.00
Sundries 10.00 Percent 20.50
Total 225.50
Contractor's Profit & Overheads 20.00 Percent 45.10
Total 270.60

ITEM RATES

Labour rate per Each Rs. 18.04 Say 18.05


Composite rate per each Rs. 498.04 Say 498.05

Page 77
DESCRIPTION OF ITEM:

Item No. 40 Providing and fitting R.C.C Pipe 10 cm (4" dia) including
laying and jointing in trenches.

Detail Unit Rate (British System) per L.M

Qty Rate Per Unit Amount (Rs.)

MATERIAL FOR 2 METRE


2.00 metre
1 R.C.C pipe 10 cm (4" dia) 6.56 Rft 20.00 per Rft 131.20

Total 131.20
Contractor's Profit & Overheads 20.00 Percent 26.24
Total 157.44
Material cost per metre 78.72

LABOURFor 40 Metre

1 Plumber 1.00 No. 170.00 per day 170.00


2 Helper (Cooly) 2.00 Nos. 140.00 per day 280.00

Total 450.00
Sundries 10.00 Percent 45.00
Total 495.00
Contractor's Profit & Overheads 20.00 Percent 99.00
Total 594.00

ITEM RATES

Labour rate per Metre Rs. 14.85 Say 14.85


Labour rate per Ft. Rs. 4.53 Say 4.55

Composite rate per Metre Rs. 93.57 Say 93.55


Composite rate per Ft. Rs. 28.53 Say 28.55

Page 78
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (¼" dia)

(i) Single way.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of 6 mm (¼" dia) 1.00 No. 60.00 each 60.00

Total 60.00
Contractor's Profit & Overheads 20.00 Percent 12.00
Total 72.00

LABOURFor 30 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 7.48 Say 7.50


Composite rate per each Rs. 79.48 Say 79.50

Page 79
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (¼" dia)

(ii) Two way cock.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of 6 mm (¼" dia) 1.00 No. 65.00 each 65.00

Total 65.00
Contractor's Profit & Overheads 20.00 Percent 13.00
Total 78.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 89.22 Say 89.20

Page 80
DESCRIPTION OF ITEM:

Item No. 41 Providing and fitting chromium plated or oxidised gas Cock
6 mm (¼" dia)

(iii) Three way cock.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Gas Cock of three way 1.00 No. 70.00 each 70.00

Total 70.00
Contractor's Profit & Overheads 20.00 Percent 14.00
Total 84.00

LABOURFor 15 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 14.96 Say 14.95


Composite rate per each Rs. 98.96 Say 98.95

Page 81
DESCRIPTION OF ITEM:

Item No. 42 Providing and fitting nipple or bush 6 mm to 10 mm (¼" - 3/8") i/d.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Nipple or bush 6 mm to 10 mm
(1/4" - 3/8") i/d. 1.00 No. 6.00 each 6.00

Total 6.00
Contractor's Profit & Overheads 20.00 Percent 1.20
Total 7.20

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 5.61 Say 5.60


Composite rate per each Rs. 12.81 Say 12.80

Page 82
DESCRIPTION OF ITEM:

Item No. 43 Providing and fixing, brass gas cock.

(i) 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass gas cock 1.5 cm (½" dia) 1.00 No. 60.00 each 60.00

Total 60.00
Contractor's Profit & Overheads 20.00 Percent 12.00
Total 72.00

LABOURFor 48 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate per Each Rs. 1.17 Say 1.15


Composite rate per each Rs. 73.17 Say 73.15

Page 83
DESCRIPTION OF ITEM:

Item No. 43 Providing and fixing, brass gas cock.

(ii) 2 cm (¾" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass gas cock 2 cm (¾" dia) 1.00 No. 75.00 each 75.00

75.00
Contractor's Profit & Overheads 20.00 Percent 15.00
Total 90.00

LABOURFor 48 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate per Each Rs. 1.17 Say 1.15


Composite rate per each Rs. 91.17 Say 91.15

Page 84
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing brass stop cock/bib cock.

(i) 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass stop cock/bib cock. 1.00 No. 38.00 each 38.00

Total 38.00
Contractor's Profit & Overheads 20.00 Percent 7.60
Total 45.60

LABOURFor 30 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate per Each Rs. 1.87 Say 1.85


Composite rate per each Rs. 47.47 Say 47.45

Page 85
DESCRIPTION OF ITEM:

Item No. 44 Providing and fixing brass stop cock/bib cock.

(ii) 2 cm (¾" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass stop cock/brass bib cock 1.00 No. 65.00 each 65.00

Total 65.00
Contractor's Profit & Overheads 20.00 Percent 13.00
Total 78.00

LABOURFor 30 Nos.

1 Plumber 0.25 No. 170.00 per day 42.50

Total 42.50
Sundries 10.00 Percent 4.25
Total 46.75
Contractor's Profit & Overheads 20.00 Percent 9.35
Total 56.10

ITEM RATES

Labour rate per Each Rs. 1.87 Say 1.85


Composite rate per each Rs. 79.87 Say 79.85

Page 86
DESCRIPTION OF ITEM:

Item No. 45 Hoisting and placing in position precast R.C latrine seats.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

LABOURFor 8 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00


2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

Total 650.00
Sundries 10.00 Percent 65.00
Total 715.00
Contractor's Profit & Overheads 20.00 Percent 143.00
Total 858.00

ITEM RATES

Labour rate per Each Rs. 107.25 Say 107.25

Page 87
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 1 Providing and fixing, chromium plated waste coupling.

(i) 3 cm (1¼" dia)

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. coupling 3 cm (1¼" dia) 1.00 No. 70.00 each 70.00

Total 70.00
Contractor's Profit & Overheads 20.00 Percent 14.00
Total 84.00

LABOURFor 20 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 95.22 Say 95.20

Page 88
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 1 Providing and fixing, chromium plated waste coupling.

(ii) 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P. coupling 4 cm (1½" dia) 1.00 No. 75.00 each 75.00

Total 75.00
Contractor's Profit & Overheads 20.00 Percent 15.00
Total 90.00

LABOURFor 20 Nos.

1 Plumber/Mason 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 101.22 Say 101.20

Page 89
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing rubber plug with chain.

(i) 3 cm (1¼" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber plug with chain 3 cm


(1¼" dia) 1.00 No. 25.00 each 25.00

Total 25.00
Contractor's Profit & Overheads 20.00 Percent 5.00
Total 30.00

LABOURFor 50 Nos.

1 Plumber 0.10 No. 170.00 per day 17.00

Total 17.00
Sundries 10.00 Percent 1.70
Total 18.70
Contractor's Profit & Overheads 20.00 Percent 3.74
Total 22.44

ITEM RATES

Labour rate per Each Rs. 0.45 Say 0.45


Composite rate per each Rs. 30.45 Say 30.45

Page 90
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 2 Providing and fixing rubber plug with chain.

(ii) Rubber plug with chain 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber plug with chain 4 cm


(1½" dia) 1.00 No. 25.00 each 25.00

Total 25.00
Contractor's Profit & Overheads 20.00 Percent 5.00
Total 30.00

LABOURFor 50 Nos.

1 Plumber 0.10 No. 170.00 per day 17.00

Total 17.00
Sundries 10.00 Percent 1.70
Total 18.70
Contractor's Profit & Overheads 20.00 Percent 3.74
Total 22.44

ITEM RATES

Labour rate per Each Rs. 0.45 Say 0.45


Composite rate per each Rs. 30.45 Say 30.45

Page 91
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 3 Providing and fixing waste pipe of PVC.

(i) 3 cm (1¼" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. waste pipe 3 cm (1¼" dia) 1.00 No. 12.00 each 12.00

Total 12.00
Contractor's Profit & Overheads 20.00 Percent 2.40
Total 14.40

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 5.61 Say 5.60


Composite rate per each Rs. 20.01 Say 20.00

Page 92
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 3 Providing and fixing waste pipe of PVC.

(ii) P.V.C Waste Pipe 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. waste pipe 4 cm (1½" dia) 1.00 No. 15.00 each 15.00

Total 15.00
Contractor's Profit & Overheads 20.00 Percent 3.00
Total 18.00

LABOURFor 40 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 5.61 Say 5.60


Composite rate per each Rs. 23.61 Say 23.60

Page 93
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 4 Providing and fixing flushing bend of P.V.C.

(i) 3 cm (1¼" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. flushing bend 3 cm (1¼" dia) 1.00 No. 18.00 each 18.00

Total 18.00
Contractor's Profit & Overheads 20.00 Percent 3.60
Total 21.60

LABOURFor 45 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 4.99 Say 5.00


Composite rate per each Rs. 26.59 Say 26.60

Page 94
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 4 Providing and fixing flushing bend of P.V.C.

(ii) P.V.C Flusing bend 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 P.V.C. Flusing bend 4 cm (1½" dia) 1.00 No. 20.00 each 20.00

Total 20.00
Contractor's Profit & Overheads 20.00 Percent 4.00
Total 24.00

LABOURFor 45 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 4.99 Say 5.00


Composite rate per each Rs. 28.99 Say 29.00

Page 95
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.

(i) 3 cm (1¼" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P Bottle trap with waste pipe 1.00 No. 362.00 each 362.00

362.00
Contractor's Profit & Overheads 20.00 Percent 72.40
Total 434.40

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 445.62 Say 445.60

Page 96
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 5 Providing and fixing chromium plated bottle trap with waste
pipe etc. complete.

(ii) C.P. Bottle Trap with waste pipe 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 C.P Bottle trap 4 cm with waste pipe 1.00 No. 365.00 each 365.00

365.00
Contractor's Profit & Overheads 20.00 Percent 73.00
Total 438.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 449.22 Say 449.20

Page 97
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 6 Providing and fixing angle iron brackets for

(i) Wash hand basin and cistern.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle Iron Bracket 2.00 Nos. 15.00 each 30.00


2 Nail with Cutter 4.00 Nos. 1.00 each 4.00

Total 34.00
Contractor's Profit & Overheads 20.00 Percent 6.80
Total 40.80

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 52.02 Say 52.00

Page 98
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 6 Providing and fixing angle iron brackets.

(ii) Sink.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Angle Iron Bracket for Sink 2.00 Nos. 18.00 each 36.00
2 Nail with cutter 4.00 Nos. 1.00 each 4.00

Total 40.00
Contractor's Profit & Overheads 20.00 Percent 8.00
Total 48.00

LABOURFor 20 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 11.22 Say 11.20


Composite rate per each Rs. 59.22 Say 59.20

Page 99
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing 1.5 cm (½" dia) connection, including check
nuts etc.

(i) Plastic rubber connection.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Rubber connection with


assessories 1.00 Nos. 20.00 each 20.00

Total 20.00
Contractor's Profit & Overheads 20.00 Percent 4.00
Total 24.00

LABOURFor 50 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 4.49 Say 4.50


Composite rate per each Rs. 28.49 Say 28.50

Page 100
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 7 Providing and fixing 1.5 cm (½" dia) connection, including check
nuts etc.

(ii) Copper connection.

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Copper Connection
assessories 1.00 Nos. 30.00 each 30.00

Total 30.00
Contractor's Profit & Overheads 20.00 Percent 6.00
Total 36.00

LABOURFor 50 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 4.49 Say 4.50


Composite rate per each Rs. 40.49 Say 40.50

Page 101
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(i) 1.5 cm (½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 1.5 cm (½" dia) brass ball valve with


assessaries 1.00 No. 50.00 each 50.00

50.00
Contractor's Profit & Overheads 20.00 Percent 10.00
Total 60.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 69.35 Say 69.35

Page 102
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(ii) 2 cm (¾" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball valve 2 cm (¾" dia) 1.00 No. 65.00 each 65.00

Total 65.00
Contractor's Profit & Overheads 20.00 Percent 13.00
Total 78.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 87.35 Say 87.35

Page 103
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(iii) 2.5 cm (1" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball valve 2.5 cm (1" dia) 1.00 No. 85.00 each 85.00

Total 85.00
Contractor's Profit & Overheads 20.00 Percent 17.00
Total 102.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 111.35 Say 111.35

Page 104
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(iv) 3 cm (1¼" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 3 cm (¼" dia) 1.00 No. 125.00 each 125.00

Total 125.00
Contractor's Profit & Overheads 20.00 Percent 25.00
Total 150.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 159.35 Say 159.35

Page 105
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(v) 4 cm (1½" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 4 cm (1½" dia) 1.00 No. 170.00 each 170.00

Total 170.00
Contractor's Profit & Overheads 20.00 Percent 34.00
Total 204.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 213.35 Say 213.35

Page 106
REPLACEMENT

DESCRIPTION OF ITEM:

Item No. 8 Providing and fixing brass ball float valve.

(vi) 5 cm (2" dia).

Detail Unit Rate (British System) for Each

Qty Rate Per Unit Amount (Rs.)

MATERIAL

1 Brass ball float valve 5 cm (2" dia) 1.00 No. 250.00 each 250.00

Total 250.00
Contractor's Profit & Overheads 20.00 Percent 50.00
Total 300.00

LABOURFor 24 Nos.

1 Plumber 1.00 No. 170.00 per day 170.00

Total 170.00
Sundries 10.00 Percent 17.00
Total 187.00
Contractor's Profit & Overheads 20.00 Percent 37.40
Total 224.40

ITEM RATES

Labour rate per Each Rs. 9.35 Say 9.35


Composite rate per each Rs. 309.35 Say 309.35

Page 107