You are on page 1of 1

CALCUL

RETETA ARTICOL: IZF12IV10 UM: MP

SISTEM IZOLARE TERM.EXT.BAUMIT LA PERETI: POLIST.EPS-FATADA 10 CM.PE SUPORT MINERAL+TENC.DECORATIVA

Sporuri deviz: 0.000000% / 0.000000% / 0.000000%


Sporuri subcapitol: 0.000000% / 0.000000% / 0.000000%
Sporuri articol: 0.000000% / 0.000000% / 0.000000%

material: 1000227 KG GRUND GRANOPOR BAUMIT GRANOPORGRUND FISA 1616


ELEMENTE DE CALCUL \ PRETURI: TOTAL MATERIAL MANOPERA UTILAJ TRANSPORT
 0.20000 X
Materiale total:   =  46.92
livrare:
din care:
material:livrare:
1000409 KG  46.92
ADEZIV SPACLU BAUMIT KLEBESPACHTEL  46.92
FISA 1511
aprovizionare:
 8.00000 X =  0.00  0.00
transport cf:  0.00  0.00
material: 1000552 BUC DIBLU 95 MM.BAUMIT DUBEL 95 MM
transport auto:  0.00  0.00
 6.00000 X   =
manipulare manuala:  0.00  0.00
material:manipulare
1001506mecanica:
MP  0.00
PLASA FIBRA STICLA BAUMIT TEXTILGLASSGITTER FISA 1513  0.00
 1.10000 X   =
Manopera total din articole de deviz:  15.45  15.45
livrare:
Manopera total:  15.45
material: 1113074 KG TENCUIALA GRANOPOR BAUMIT GRANOPORPUTZ 2 MM.FISA 1617
din care:
 3.10000 X   =
manopera bruta articole + manipulari:  12.06  12.06
livrare:
C.A.S.  20.800%  2.51  2.51
Somaj
manopera: 013400 H ZIDAR 0.500%  0.06  0.06
Sanatate
 2.01000 X  5.200%
  =  0.63  0.63
Accidente  0.279%  0.03  0.03
Alte cote 1  0.850%  0.10  0.10
Alte cote 2  0.250%  0.03  0.03
Alte cote 3  0.250%  0.03  0.03

Utilaje din lucrari:  0.00  0.00

Transport din lucrari: 0.00

Total I:  62.37  46.92  15.45  0.00  0.00

Cheltuieli indirecte:  7.000%  4.37

Profit:  7.000%  4.67

TOTAL LUCRARI DE BAZA:  71.41

pag. 21