COST COMPONENT FOR IT PARK BUILDINGS

PROJECT- E
(This building includes common area finishes
PROJECT- B PROJECT- C PROJECT- D PROJECT- F
PROJECT- A and Concrete dimolishion due to change in
Comp 2004-5 Comp 2005 Comp 2004-5 (Comp 2007)
Drgs)
SL Comp 2006
ITEM
NO
GRID - 10.2X10.2 GRID - 10.5X10.5 GRID - 10.2X10.2 GRID - 10.2X10.2 GRID - 10.2X10.2 GRID - 10.2X10.2

AMOUNT (RS) AREA (SQM) RATE/SFT AMOUNT AREA RATE/SFT AMOUNT AREA RATE/SFT AMOUNT AREA RATE/SFT AMOUNT AREA RATE/SFT AMOUNT AREA RATE/SFT Av cost /Sft

1 EXCAVATION 5978430 41849 13.28 2937719 35949 7.59 11633971.77 29393 36.79 4,846,229.58 36000 12.51 20052381.65 46596 39.99 12863941 34740 34.41 24.10

2 CONCRETE 65152028 41849 144.69 50992819 35949 131.83 40290067.36 29393 127.39 57,096,772.00 36000 147.40 79727313.95 46596 159.02 53093124 34740 142.04 142.06

3 FORMWORK 25535645 41849 56.71 12889354 35949 33.32 10825209.32 29393 34.23 21548034 36000 55.63 19296975.10 46596 38.49 12346482.38 34740 33.03 41.90

4 STEEL 85125006 41849 189.04 74867059 35949 193.55 49,011,906.50 29393 154.97 80,379,521.00 36000 207.51 101363701.00 46596 202.17 59598610.72 34740 159.44 184.45

5 BLOCK WORK 5227032 41849 11.61 3479210 35949 8.99 2,374,201.50 29393 7.51 4351210 36000 11.23 5589367.43 46596 11.15 18699 34740 0.05 8.42

6 PLASTERING 3659322 41849 8.13 1460788 35949 3.78 687,487.21 29393 2.17 1625568 36000 4.20 2701396.00 46596 5.39 1169552 34740 3.13 4.47

7 FLOORING 1131336 41849 2.51 1180665 35949 3.05 1,368,497.70 29393 4.33 9,677,171.06 36000 24.98 1893136 46596 3.78 1781878.90 34740 4.77 7.24

8 WATERPROOFING 11729903 41849 26.05 11875212 35949 30.70 9357181 29393 29.59 7534265 36000 19.45 20733483 46596 41.35 8430592.20 34740 22.55 28.28

9 MISCELLANIOUS 14335687 41849 31.84 8650063.00 35949 22.36 12926206.98 29393 40.87 2,707,546.05 36000 6.99 27961845.85 46596 55.77 2319649.984 34740 6.21 27.34

TOTAL 217874389 41849 483.85 168332889 35949 435.18 138474729.34 29393 437.84 189766316.7 36000 489.90 279319599.98 46596 557.11 151622530.2 34740 405.62 468.25
Note:--The Per SFT Cost is only for RCC strecture including blockwork plaster