The weekly progress report from the Traffic Safety Unit of the Northern Region of Projek Penyelenggaraan Lebuhraya Berhad covers the period of 10 March 2010 to 14 March 2010. It includes 18 projects involving pavement repair, signage installation, bridge work, and slope rehabilitation along highways in the northern region. The status, start and completion dates, staffing details of drivers and workers are provided for each project. The report was prepared by ARH of the Traffic Safety Unit - Northern Region.
The weekly progress report from the Traffic Safety Unit of the Northern Region of Projek Penyelenggaraan Lebuhraya Berhad covers the period of 10 March 2010 to 14 March 2010. It includes 18 projects involving pavement repair, signage installation, bridge work, and slope rehabilitation along highways in the northern region. The status, start and completion dates, staffing details of drivers and workers are provided for each project. The report was prepared by ARH of the Traffic Safety Unit - Northern Region.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online from Scribd
The weekly progress report from the Traffic Safety Unit of the Northern Region of Projek Penyelenggaraan Lebuhraya Berhad covers the period of 10 March 2010 to 14 March 2010. It includes 18 projects involving pavement repair, signage installation, bridge work, and slope rehabilitation along highways in the northern region. The status, start and completion dates, staffing details of drivers and workers are provided for each project. The report was prepared by ARH of the Traffic Safety Unit - Northern Region.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online from Scribd
2 P.S.O Km 127.10 Sb UEMC 3 Pavement Repair Km 129.60 Nb Propel - Ed 4 Pavement Repair Km 133.00 Nb Propel - Ed 5 Pavement Repair Km 136.00 Nb Propel - Ed 6 Pavement Repair Km 140.00 Nb Propel - Ed 7 Pavement Repair Km 145.00 Nb Propel - Ed 8 Pavement Repair Km 150.00 Sb Propel - Ed 9 P.S.O - Survey Km 153.00 Nb UEMC 10 Railling Inspection Sec N4 & Sec N5 Propel - Nbd 11 Installation For Wire Rope Sec N3 MRSB 12 Penang Bride Widenning Penang Bridge UEMC 13 P.S.O Km 259.00 Nb UEMC 14 P.S.O Km 229.00 Sb UEMC 15 Pedestrian Bridge Km 191.90 BB Bumi Aman 16 Package 5 Jelapang UEMC 17 Slope Rehab@ Rock Fence Km 263.90 Sb Impian Khidmat Sb 18 Slope Rehab@ Rock Fence Km 258,10 Sb Nce Conctructions
Prepared By ARH - TSU - NR /3/2010 - 14/3/2010 )
Start Date Completion Date Status Manpower Remarks
Driver Workers 1/9/2009 In progress 1 3 Section N3 1/9/2010 In progress 2 6 Section N3 2/1/2010 In progress Section N3 3/1/2010 10/2/2010 In progress Section N3 1/11/2009 In progress 1 5 Section N3 1/11/2009 10/2/2010 In progress 4 Section N3 1/11/2009 In progress 1 8 Section N3 1/11/2009 10/2/2010 In progress 1 3 Section N3 1/1/2010 10/2/2010 In progress 1 3 Section N3 3/1/2010 25/2/2010 In progress Section N3 3/2/2010 23/2/2010 In progress 1 3 Section N3 2006 In progress 3 6 Penang Bridge 1/7/2009 In progress 2 12 Section N5 1/9/2009 In progress 2 6 Section N5 10/11/2009 In progress 1 6 Section N4 2006 In progress 2 5 Section C1 & N5 3/3/2010 In progress 1 2 Section N5 11/3/2010 In progress 1 2 Section N5