Professional Documents
Culture Documents
Time-Cost Optimisation
Objective
Cost
Crash Point
Crash cost
Normal Point
Normal cost
Time
Crash time Normal time
Indirect costs
Includes
Overheads
Administrative expenses
Depreciation
Loss of profit
Loss of revenue
Penalty
The loss in profit, penalty comes under a
category called outage loss
Indirect costs
Cost
Outage loss
Supervisory and
overheads
Time
Crash time Normal time
Total cost
Total cost
Optimum
cost Direct cost
Indirect cost
Time
Crash time Normal time
Optimum time
Some terms
Normal time (tn)
Standard time that an estimator normally allow for an activity
Crash time (tc)
Minimum possible time in which an activity can be completed, by
employing extra resources
Normal cost(Cn)
Direct cost required to complete the activity in the normal time duration
Crash cost(Cc)
Direct cost corresponding to the completion of the activity within crash
time
Cost slope (Cs)
Slope of the line(s) used to approximate the direct cost curve
Cost slope
Increase in cost
Cc Cn c
Cs
t n tc t
Decrease in time
Note:
If the cost curve is approximated by one single line it will have only one cost slope
whereas if it is approximated by more than one line it would adopt more cost slopes and
more calculations, respectively.
Using network analysis
The project time is controlled by the
activities lying on the critical path
To minimize the cost we crash the critical
activities.
Particularly, critical activity with minimum
cost slope must be crashed first
At each and every time check whether the
critical path is unique
If not, crash the activity one by one
Example 1
Solution 1
Critical path is 1-2-3-5-6
Length of critical path =6+14+12+8=40
Calculate the cost slop for each activity and
rank them in descending order
Activity Cost slope Ranking
1-2 20 3
2-3 14 2
3-5 12 1
1-4 20 4
4-5 120 6
5-6 100 5
Solution 1
Activity Cost slope Ranking
1-2 20 3
2-3 14 2
3-5 12 1
1-4 20 4
4-5 120 6
5-6 100 5
Now we have two parallel critical paths with duration 29 days. (i.e. 1-2-3-5-6 & 1-4-5-6)
The following are the activities yet to be crashed. They are 1 - 4, 4 - 5 and 5 - 6. Of the 3
activities 1 - 4 is with minimum cost slope.
Solution 1
Therefore,
a 28-day project schedule costs
1200 pounds
Example 2
The following data shows the duration and
costs of each activity of a project. The indirect
cost of the project is £3000 per week.
Determine the optimum duration of project
and the corresponding minimum cost.
Activity Normal Normal Crash Crash
Duration Cost (£) Duration Cost (£)
(week) (week)
1-2 6 7000 3 14500
1-3 8 4000 5 8500
2-3 4 6000 1 9000
2-4 5 8000 3 15000
3-4 5 5000 3 11000
Solution 2
N6 N5
C3 C3
1 N4 4
C1
N8
N5
C5
C3
3
Solution 2
Notes:
1. The critical path must remain critical whilst crashing
2. When you have more than one critical path, crash the
common activities to the same amount to maintain the
first condition
Solution 2
Solution 2 1-3
2-3
1500
1000
2
1
2-4 3500 5
3-4 3000 4