DAILY PROGRESS REPORT

I A ENERGY CHANJU-1 HYDRO ELECTRIC POWER PROJECT (36MW) DATED :- 05 June 2011 DAY SHIFT
SR.NO. NAME OF SITE/MACHINERY Katwar Stock Yard 10:00 am to 1:00 PM JCB 210 shifting 1:00 PM to 5:00 PM fencing work DESCRIPTION OF WORK MAN POWER SKILLED UNSKILLED NATUR OF DUTY REMARKS

Fencing work 1

DG Set 45KW

Fixing of barbed wire and mesh

Welding work

P.W.D.Road widening from Nakrod To Bagaigarh JCB 210 2 Escort Backhoe Excavation work at PWD road widening 1 Breaking of hard rock 1 Helper deputed with Machiene Helper deputed with Machiene Machiene reached at approximately 4.5 KM from Nakrod

Chamba Stock Yard 3 Fencing Work 30 pole erected 1 5

Loading and Unloading Helper deputed with machine

Escort Hydra 14 Tonnes 4

Channels shifting

Escort Hydra 23 Tonnes

Nil

Machiene is at Chamba Stockyard

Transmission 11 KV for construction power

Line route survey

Helper for assist to senior staff

Extra Activities 6 Celebration of World Envoirnment Day at Tikrigarh school and Bagaigarh School. Approximately 60 candidate participate. Photographs attached. TOTAL MAN POWER 3 17

NIGHT SHIFT
SR.NO. 1 2 3 4 5 6 NAME OF SITE/MACHINERY Dam Site Chamba Stock Yard Kandla Stock Yard Nakrod Stock Yard Katwar Stock Yard On the way Nakrod to Tikrigarh (3KM From Nakrod) TOTAL MAN POWER Checked By :Er.Raj Kumar Dhiman Senior Manager (Civil) IA Energy Chanju-1 Hydro ElectricProject Chanju (H.P.)

DESCRIPTION OF WORK SKILLED Night Watchman Night Watchman Night Watchman Night Watchman Night Watchman Night Watchman 0 0 0 0 0 0 0

MAN POWER UNSKILLED 2 1 1 2 2 2 10 Verified By :NATUR OF DUTY

REMARKS

One watchman is on regular basis For security of JCB 210 and Escort backhoe

Prepaired By :Sameer Mehra Accountant IA Energy Chanju-1 Hydro ElectricProject Chanju (H.P.)