Professional Documents
Culture Documents
Project Report on
Submitted By
P. RamyaSri (16JJ1A0246)
P. Niharika (16JJ1A0244)
M. Lavanya (16JJ1A0241)
CH. Lavanya (17JJ5A0201)
K. Mounika (16JJ1A0231)
G. Mounika (16JJ1A0216)
Under the guidance of
1
Switchyard protection
CERTIFICATE
P. RamyaSri (16JJ1A0246)
P. Niharika (16JJ1A0244)
M. Lavanya (16JJ1A0241)
CH. Lavanya (17JJ5A0201)
K. Mounika (16JJ1A0231)
G. Mounika (16JJ1A0216)
Project guide
Sri.Suresh. Bhukya
Manager (Operation)
Ntpc., Ramagundam
Project coordinator
Shri. G.Rajashekar
AGM (Operation)
Ntpc., Ramagundam
2
Switchyard protection
ACKNOWLEDGEMENT
With profound respect and gratitude, we take the opportunity to convey our
thanks to complete the mini project here.
We also extremely grateful to all the technical staff of NTPC, Ramagundam for
their co- operation and guidance that has helped us a lot during the course.
We are thankful to each and every one who helped us in completion of this
project report.
DECLARATION
3
Switchyard protection
Signature of candidates
P. RamyaSri
P. Niharika
M. Lavanya
CH. Lavanya
K. Mounika
G. Mounika
ABSTRACT
This project report gives brief idea about Thermal power plant, Switchyard and
its major equipment and its operational activities. It explains basic principle of
Rankine cycle on which a power plant works. Main aim of this project is to
study the operation of switchyard which facilitates switching operations in
transmitting electrical energy from generating station to substation
andprotection methods facilitated by the switchyard and switchyard equipment
and their operation in detail and isolation of switchyard equipment and
measures to be taken in case of a blackout.
The details and the data provided in this are of 400KV Switchyard of NTPC-
Ramagundam in TG.
4
Switchyard protection
INDEX
5
Switchyard protection
1.Introduction of NTPC
NTPC, India’s largest power company with an installed capacity of 41,184MW
is presently operating 16 coal based, 7 gas based power stations and 4joint
ventures. NTPC contributed nearly one-third of the countries entire power
generation during the year 2011-12 and plans to be become a 75,000MW power
company by 2017. NTPC has moved ahead by diversifying its portfolio to
emerge has an integrated power major with presence across entire energy value
chain. NTPC has been allocated 6 mine blocks which are expected to produce
48 million tons per annum. NTPC has also ventured into oil and gas
exploration. It was founded on November 7, 1975.
Leader in power sector:
NTPC with an installed capacity of 41,184 MW is generating 28.60% of the
countries entire power requirement. So, it is recognized as the India’s largest
power utility. Power is an important infrastructure in developing countries.
Power development in INDIA received a big boost with the dawn of NTPC.
6
Switchyard protection
Coal-fired stations:
7
Switchyard protection
Gas-based stations:
8
Switchyard protection
9
Switchyard protection
Water Requirements:
The water requirement for thermal stations come under two main groups, the
first requirement is the water required for steam generation and the second
requirement is for cooling purposes. The Pochampad Dam was built on river
Godavari. Measures were taken to ensure that station is not required to be
closed under closure of irrigation canal or during draughts. Water requirement
of the plant during such conditions can be met for 9-10 weeks without any
replacement from the distributory canal.
Ash Disposal:
Large area of land is required for the disposal of the waste like coal ash. Ash
being generated from the plant is pumped in slurry from through pipelines to the
ash pond at Kundanpalli, which are 5km away from the power station. The
ash disposed is utilized in various forms.
Environmental Control:
Station is equipped with highly efficient ESP system and with tall chimney of
about 275m height. Effluent treatment plant was also installed for reuse of
decants ash water from ash pond.
10
Switchyard protection
Distribution of Electricity:
GOA 75MW 3%
PONDICHERRY 108MW 4%
-: UNITS COMMISSIONED:-
11
Switchyard protection
Hyderabad ------------------ 4
NagarjunaSagar ------------------- 2
Chandrapur ------------------ 2
Khammam ----------------- 1
Dichpelly ------------------ 1
AP Transco ------------------ 5
Turbine
Generator
Boiler Condensor
Pump
Principles of Combustion
12
Switchyard protection
The primary function of oil and coal burning systems in the process of steam
generation is to provide controlled efficient conversation of the chemical energy
of the fuel into heat energy which is then transferred to the heat absorbing
surfaces of the steam generator. The combustion element of a fuel consists of
carbon, hydrogen and usually a small amount of Sulphur. When combustion is
properly completed the exhaust gases will contain, carbon dioxide, water
vapour, Sulphur dioxide and a large volume of Nitrogen, Combustion is brought
about by combining carbon and hydrogen or hydrocarbons with the oxygen in
air. When carbon burns completely, it results in the formation of a gas known as
carbon dioxide. When carbon burns incompletely it forms Carbon monoxide.
13
Switchyard protection
3.1. Boiler:
The function of boiler is steam production. It is also called steam generator. It
converts given chemical energy into heat energy. Chemical energy given to
boiler is fossil fuel or coal. This coal is burning with air and produce heat. This
heat is absorbed by water and thus water converts into steam.
Boiler is specified with its features like dry bottom, corner fired, coal fired,
forced circulation, balanced draft, single drum. Generally boiler consist of
boiler drum, economizer, super heater zone, re-heater zone, water walls etc.,
Initially the firing in boiler started by burning of HFO (heavy fuel oil) till the
temperature raise ignition temperature of coal.
3.2. Turbine:
The function of turbine is to convert given heat energy into mechanical energy.
The superheated steam produced in boiler is impinged on turbine to produce
mechanical energy. It consists of 3 cylinders called high-pressure turbine (HPT),
intermediate pressure turbine (IPT), low-pressure turbine (LPT). Each turbine is
a set of stages. Each stage is set of moving and fixed blades.
HPT is single flow turbine and consist of 18 stages. Main steam with high-
pressure impinged on to it. This steam flows through each stage. The steam
losses pressure and temperature in each stage. The exhaust of this (steam outlet
of last stage) sent to boiler.
IPT is double flow turbine and consist of 14 stages in each flow path thus totally
consists of 14X2 stages. The steam enters into it with medium pressure. This
flows through each stage in both directions. The exhaust of last stages sent on
LPT.
LPT is double flow turbine and consist of 6 stages in each flow path,
totally it consist of 6 X 2 stages. The steam pressure entering into this is at low
pressure. The exhaust of this sent to condenser.
14
Switchyard protection
3.3. Generator:
This converts given mechanical energy into electrical energy. Mechanical
energy fed to it by turbine and produced electrical energy transmitted to load
centers through GT s and transmission lines. This is hydrogen-cooled generator.
This hydrogen is cooled by water.
Overall efficiency of unit depends on boiler efficiency, turbine efficiency,
generator efficiency and cycle efficiency.
Overall efficiency
ŋ = Boiler efficiency X Turbine efficiency X Generator efficiency X Cycle
efficiency
3.4. Condenser:
There are two condensers entered to the two exhausters of the L.P. turbine.
These are surface type condensers with two pass arrangement. Cooling water
pumped into each condenser by a vertical C.W. pump thru' the inlet pipe. Water
enters the inlet chamber of the front water box, passes horizontally through the
brass tubes to the water box at the other end, takes a turn, passes thru' the upper
cluster of tubes and reaches the outlet chamber in the front water box. From
these, cooling water leaves the condenser through the outlet pipe and discharge
into the discharge duct.
Steam exhausted from the L.P. turbine washing the outside of the condenser
tubes losses its latent heat to the cooling water and is connected with water in
the steam side of the condenser. This condensate collects in the hot well, welded
to the bottom of the condensers.
3.5. CONDENSATE EXTRACTION PUMP:
15
Switchyard protection
High pressure heaters are designed for recovering the heat from the turbine
extraction steam for preheating the boiler feed water to improve efficiency. Feed
water flows inside the tubes and heating steam flows in the shell of the heaters
to maintain back pressure in the heaters, drip level to be maintained. A
pneumatic operated normal drip level control value (between 6&5 heater Zero
meter level) maintains level in HPH-6 and allows drip to flow to HPH - 5.
Emergency drip from HPH-6 flow to deaerator (control valve at deaerator floor)
Normal drip from HPH-5 (valve at 5.5 mts near B-row wall) flows to
deaerator and emergency drip (control valve near HP flash tank) flows to
condenser.
16
Switchyard protection
Low pressure heaters (LPHs) are indirect type and are designed for recovering
heat from steam extracted from IP turbine and LP turbine to increase condensate
temperature going to deaerator and thus improving efficiency of the cycle.
There are three LP heaters for this system
Each normal drip and alternate drip has pneumatic control valve with two
manual isolating valves and a bypass motor operated valve. Normally control
valve maintains the drip level, whenever it fails to operate, motor operated by
pass valve can be operated. Each LP heater has provision for bypassing heater
on condensate side, whenever any tube leakage inside the heater.
LP heaters are provided with level controllers, level transmitters and level
switches connected on a stand pipe for measuring and maintaining drip levels.
LP heaters are provided with safety valves to vent out in case of pressurization.
3.7.Deaerator
The presence of certain gases, principally oxygen, carbon-di-oxide and
ammonia, dissolved in water is generally considered harmful because of their
17
Switchyard protection
cor
rosive attack on metals, particularly at elevated temperatures. The prevention of
internal corrosion in modern boilers is achieved by embodying into the boiler
feed system a deaerating unit, whose function is to remove dissolved gases from
the feed water by mechanical means. Particularly the unit must reduce the
oxygen content of the feedwater to as low a valve as is possible or desirable,
depending upon the individual circumstances, residual oxygen content in
condensate at the outlet of deaerating plant usually specified is 0.005/litre or
less.
3.8) MAIN PUMP :
Main pump is a multi (8 stage) centrifugal pump. Mechanical seals are provided
on the shaft and cooling of each shaft seal is cooled by (1) circulating water by a
cooler with magnetic filters connected in parallel (2) jacket cooling of seal
casing
18
Switchyard protection
The three-element feed-flow regulating system has been develop to meet the
requirements of the modern boiler. The essential factors in obtaining the fine
degree of regulation required are the steam flow from the boiler, the feed water
flow to the boiler and the water level in the boiler drum.
To maintain the rate of feed-water input in correct ratio to the steam output
under all conditions of loading, the system measures feed flow and steam -flow
and the meter readings are balanced against each other by means of a
differential linkage.
19
Switchyard protection
4.Rankine Cycle:-
The Power Plant works on the basic principle of “ Rankine Cycle”.
20
Switchyard protection
6 – 7, Reheating (Reheater)
The main advantage of this modified Rankine cycle is that it prevents the
vapour ending up in the superheat region after the expansion in the turbine
which reduces the energy removed by the condensers.
The efficiency of Rankine cycle is usually limited by the working fluid. This
fluid follows a closed loop and is reused constantly.
21
Switchyard protection
SWITCHYARD
22
Switchyard protection
23
Switchyard protection
24
Switchyard protection
In addition to the above, three nos. of Tie Transformers, five nos. of Auto
Transformers and two nos. of Shunt Reactors are provided as shown in the
switchyard line diagram.
25
Switchyard protection
5.4AUTO TRANSFORMERS
Five Auto Transformers with on Load Tap Changers are provided to
interconnect the 400 Kv system of NTPC and 220/132 Kv system of AP
Transco, Malyalapally substation situated 1.8 Km away from the RSTPS
switchyard.
Four nos. of Tie Transformers are provided for feeding power to station
auxiliaries like Cooling water & Raw water pumps, Coal Handling & water
treatment Plants, Ash & Fuel Handling pumps, Cooling towers and lighting
requirements of station & colony.
5.6SHUNT REACTORS
Long lines when lightly loaded, the receiving end voltage raises, due to Ferranti
effect. Shunt Reactors produce lagging MVAR there by control the receiving
end voltages during lightly loaded conditions. Shunt reactors also limit the
short circuit fault levels. Therefore, Shunt reactors are provided on both the
ends of Nagarjunasagar lines 1 & 2, the length of these lines being about 267
km
26
Switchyard protection
27
Switchyard protection
28
Switchyard protection
7. SWITCHYARD EQUIPMENT
Transformers
Switch Gears
Circuit Breaker
Isolators
Earth Switches
Surge Arrestors
Wave Traps
Reactive Power compensating device
BUS Bars
Conductors / Auxiliary Items
Post Insulators and supporting structures
29
Switchyard protection
7.2 ISOLATORS
Earth switch is mounted on the isolator base on the line side or breaker side
depending upon the position of the isolator. The earth switch usually comprises
of a vertical break switch arm with the contact, which engages with the isolator
contact on the line side. Earth switch is required to discharge the trapped
charges on the line or equipment (under shut own) to earth for maintaining
safety. Earth switch can be operated only from local either by electrical
operation or manually.
7.4 BUSBAR
Busbar is an Aluminum tube of 4” IPS having wall thickness of 0.4”, where all
incoming and outgoing feeders are connected in a schematic way to enable
smooth operation and Maintenance of equipment without any interruption to
the system. At RSTPS one and half breaker scheme is provided for 200 MW
generator feeders and 400 KV outgoing lines, Two-breaker scheme is provided
for 500 MW generator feeders.
Surge Arresters are provided to ground the over voltage surges caused by
switching and lighting surges. Surge Arresters provide leakage path to the
ground whenever the system voltage rises above the specified value. They are
equipped with surge monitors, which measures the leakage currents and a
counter to record the number of surges taken place.
30
Switchyard protection
Current Transformers are provided to step down the current to low values
suitable for measuring protection and control instruments. Current
Transformers also isolate measuring and protective devices from high system
voltage. CTs in the switchyard consist of five secondary cores. Core 1&2 are
used for busbar protection, 4 & 5 are for main 1&2 protection and core 3 is for
measuring instruments.
CVTs step-down the system voltage to sufficiently low value (110 V) for
measuring, protection and synchronizing circuits. CVT has a H.F. terminal
point for receiving & transmitting the high frequency signals for carrier
protection and communication.
31
Switchyard protection
Corridor type flat control panels are provided in U shape with doors at both the
end panels. Between the front and rear panels, there is adequate space for
inspection of interior wiring. The controlling knobs are provided on front panel
for opening & closing of breakers and isolators. The close/open position of the
breakers / isolators / earth switches is indicated through lamps or semaphore
indicators. The relative position of each equipment is shown in the mimic
single line diagram that is painted on front side of the control panels. The
indicating instruments (MW, MVAR, voltage, current etc.) and annunciation
windows are provided on the top of front panel for monitoring of the
equipment. Breaker monitoring and protective relays such as LBB, Auto
reclosure, check synchronization, Trip circuit monitoring, Annunciation relays
and energy meters are mounted on the rear side of the panel.
Relay panels are of cubicle type, flat independent boxes with a door at
backside. All the protective relay units related to one bay are divided into two
groups viz. Main 1 protection, stub protection, O/V protection and their
auxiliary & trip relays as group 1 and Main 2 protection, U/v protection and
their auxiliary & trip relays as group 2 relays. Group 1 & group 2 relays are
mounted on front side of two separate panels side by side. Fault locator and
disturbance recorder of the corresponding bay mounted on front side of the
third panel. A separate glass door is provided front side of all the panels to
cover the relays from dust.
Event Logger recognizes the changes in signal-input states, plus time data
allocation for sequential recording of events. It displays the events in a time
sequential of 1/ sec, such as opening/closing of breaker poles, Isolator poles,
E/S etc. pressure high/low of air, SF6, N2 Oil etc. Alarm Appeared/reset of all
32
Switchyard protection
protection / trip relays, it also displays the status of equipment, in service/ out
of service in a regular period say 8 hrs. This is one of the important diagnostic
equipment available to operation staff to understand the type of emergency in a
flick of a second.
33
Switchyard protection
TYPES OF DISPLAYS
All 400 KV lines connected to this switchyard are provide by the Disturbance
Recorders (D/R), D/R is a PC based or Microprocessor based on line
monitoring equipment D/R is the most vital diagnostic equipment in analysis of
post fault trappings.
34
Switchyard protection
In order to achieve fast clearance and correct discrimination for faults in 400
KV transmission network, it is necessary to signal between the points at which
protection relays are connected. PLCC is high frequency signal transmission
along with actual overhead power line. It is robust and therefore reliable,
constituting a low loss transmission path that is fully controlled by the power
authority. PLCC is required for the following cases.
a) Inter tripping
b) Permissive tripping
35
Switchyard protection
c) Blocking
d) Telemetry
e) Telephone
36
Switchyard protection
2. Arcing faults invariably are a fire hazard and damage the equipment.
A relay detects the faulty element in the integrated power system and removes
it, with the help of the circuit breaker, from the remaining healthy system as
quickly as possible to avoid damage and maintain security or reliability of
supply in the healthy system. The quality of relaying depends on its sensitivity,
selectivity, speed and reliability. Varieties of protection relays are provided to
protect EHV lines and Transformers. A brief Description is given below about
the relays used for protection of Transformers and lines connected to
switchyard.
37
Switchyard protection
1. Instantaneous OC relay
The DTOC Relay has two settings; the first one is the pick value in amperes
(plug setting.). Another setting is the constant or definite operating time of the
relay. The relay delivers trip output only when the current exceeds the pickup
value and that after a specified time delay.
The operating time of IDMT relay is inversely proportional to the square of the
relay input current (plug setting) and the travel time of the disk to close the NO
contacts. The travel time of the disk to close the NO contact can be changed by
moving the backstop of the relay (Time multiplier setting).
Conventional over current relays are non-directional, which means the relay
operates on current magnitude and not on its direction or phase shift. The
Directional over current relay comprises two elements, a directional element
and OC relay element. The OC element is inhibited for operating until the
directional element has operated. The directional element is a watt metric
device, which measures the direction of power flow.
Earth fault relay is a sensitive protection against earth faults, which responds
only to residual current of the system, since a residual component that exists
only when fault current flow to earth. The residual component is extracted by
connecting the line CTs in parallel.
38
Switchyard protection
The differential relay checks the difference between the input and output
currents for any power system element, either in amplitude or in phase or both,
to determine whether the state of the power system is healthy or faulty. In the
event of a substantial difference, the element is assumed to be faulty and trip
the concerned breakers.
Pilot wire protection scheme can be used for protection of transmission lines of
220 KV and below voltages. Similar current Transformers at each end of the
protected zone are interconnected through pilot wires. Current transmitted
through the zone causes secondary current to circulate round the pilot circuit
without producing any current flow in relay. A fault within the protected zone
will cause secondary current flow in to protection relay.
The basic principle of the phase comparison relay is to check the phase
difference of current at both ends of the protected line. The carrier channel is
used to convey the phase angle of the current at one relaying point to another
for comparison with the phase angle of the current at that point.
Distance relay is of the high speed class can provide both primary and back up
facilities in a single scheme. Distance relay operate only for faults occurring
between the relay location and the selected reach point, thus giving
discrimination for faults that may occur between different line sections. The
basic principle is comparing of the fault current ‘seen’ by the relay with voltage
at the relaying point; by comparing these two quantities sit is possible to
determine whether the impedance of the line up to the point of the fault is
greater than or less than the predetermined reach point independence.
For EHV, line where fast fault clearance and high reliability vital ‘full scheme
of distance relays are provided. Full distance scheme uses six measuring units
per zone, three for phase faults and three for earth faults. All 18 measuring
39
Switchyard protection
units in three zones operate independently to protect the line and provide
backup to the adjacent lines.
Power swings are variations in power flow which occur when the voltage of
generators at different points of the power system slip relative to each other to
cater changes of load magnitude and direction or as a result of faults and their
subsequent clearance. In the case of a transient power swing, it is important that
the Distance relay should not trip and should allow the power system to return
to a stable condition. For this reason Distance, protection scheme has an
optional power swing-blocking feature.
40
Switchyard protection
The details break down analysis can be done after checking the relays,
protections operated at relay panels. Disturbance recorder provides the voltage
and current graph with respect to time of pre and post incident of fault
conditions. D/R also provide the sequence of protections operated.
41
Switchyard protection
A brief description about the annunciations provided, and the plan of action to
be taken by the operation staff is as follows.
PLAN OF ACTION
3. Check for the event logger and D/R printouts for various relay operations
and events taken place.
5. Reset the CB auto trip indication by giving the trip impulse with the
breaker close/open handle at control panel.
42
Switchyard protection
All the three poles of a circuit breaker must open or close at a time when a trip
or close command initiated. If one of the pole fails or delayed to open or close
within a specified (0.02 secs) time, circuit breaker trips immediately followed
by C.B. pole discrepancy alarm.
PLAN OF ACTION
This annunciation appears when the master trip relay (86) operates in
response to a fault but the concerned circuit breaker fails to trip. Local Breaker
Breakup relay (50Z) acts and initiates the busbar protection of the respective
bus, which trips all other circuit breakers connected to the bus.
PLAN OF ACTION
1 Check for the protection relay, which caused operation of Group A/B
trip relays.
2 Check for the busbar protection trip relay (96) for Main/tie breaker
whichever LBB has operated.
3 Check for physical opening of breakers for which LBB relay
operated.
4 Inform Maintenance group for attending the problem.
5 Restore the normalcy through the other breaker (Tie breaker) in case
of Main breaker failed to trip and vice versa.
43
Switchyard protection
All the circuit breakers are provided with two trip coils to facilitate breaking
operation reliability. This annunciation appears whenever either of the trip
circuit gets open circuited. As the failure of one of the trip circuit reduces the
reliability of the tripping operation of the breaker in the vent of fault.
PLAN OF ACTION
This annunciation appears whenever SF6 gas pressure/ Air pressure falls below
the specified value.
PLAN OF ACTION
1 Check the SF6 pressure / Air pressure locally, and asses the rate of
leakage.
2 If the rate of leakage is high, after obtaining necessary clearance trip
and isolate the breaker as early as possible. Otherwise the breaker
may go into lockout state, which is to be avoided as much as
possible.
3 If leakage rate is low inform Maintenance group for attending the
problem.
This annunciation appears whenever either air pressure (oil pressure in case of
hydraulic operated breakers) or SF6 gas pressure falls below specified values.
44
Switchyard protection
In operation lockout state circuit breaker will not operate. This feature is very
much required to prevent the breaker operation in adverse conditions of
operating system and/or arc quenching media (SF6 gas)
The settings for this annunciation are given below for reference.
PLAN OF ACTION
1 Check for the loss of oil/N2 gas pressure /SF6 gas pressure locally and
also AC supply to the pump.
2 Conform the running of the pump if oil pressure is low.
3 Identify the problem. If leakage is observed in SF6 gas line, sought
permission from IOCC to isolate the breaker.
4 If leakage is minute, inform the Maintenance staff to attend the problem.
After normalizing SF6/Oil parameters rest the alarm.
45
Switchyard protection
Two main protection relays are providing for the protection of each EHV
transmission line against phase to phase and phase to earth faults. Two distance
relays or combination of one distance relay and one phase comparison relay are
provided as main protection relays in each line. Main 1/2 operated alarm
appears when one of the main protection relays operates.
PLAN OF ACTION
Over voltage relay operate when the line voltage rises above a specified value.
Instantaneous and definite time over voltage relay is provided for each line. If
the voltage exceeds 40% of the rated voltage (400kv) instantaneous relay picks
up and trip the line. If voltage exceeds 10% of rated value for duration of more
than 5 sec. the time delay relay picks up and trip the line.
46
Switchyard protection
This alarm appears when one of the main protections becomes unhealthy due to
D.C. supply failure for relay unit or some in built problem in the relay.
PLAN OF ACTION
All protection relays work on 220 volts DC supply; Protection panels are
provided with two separate sources of 220 volts DC supply. This alarm appears
whenever one or both D.C. supply sources fails.
PLAN OF ACTION
6 No’s of fuses are provided for the three secondary cores of a CVT. VT fuse
fail annunciation appears in case of one of the fuse fails.
PLAN OF ACTION
1 Check for the flag indication for the operation of the relay indication.
2 Inform Maintenance group for replacing the CVT fuse/rectifying the
problem.
47
Switchyard protection
3 In case the rectification of problem takes more time. The voltage inputs
to the over fluxing relay, directional over current relay and VT fuse
failure relay shall be shifted to other 400 KV bus.
PLAN OF ACTION
The protection scheme provided for the bay equipment are divided into two
groups and connected separately to two trip relays. Operation of any protection
relay will operate the trip relay connected to that group. The operation of any
one of the two trip relays initiates the above annunciation.
PLAN OF ACTION
Carrier L/O relay operates through remote end carrier signal and give direct trip
command to the local breaker during the following conditions.
PLAN OF ACTION
PLAN OF ACTION
1 Collect the other end relay and breaker operation and correlate with the
operations of this end.
2 Do not charge the line until Maintenance clearance obtained.
49
Switchyard protection
The carrier aided distance schemes (Micromho, LZ 96, RAZFE) and phase
comparison scheme (P 40 contra phase relay) use signaling to convey a single
Command, usually in the form of a contact closure, from a remote relaying
point to a local relaying point, where the additional information is used to aid
or speed up clearance of faults within a protected zone or to prevent tripping
for faults outside a protected zone. For more reliability in EHV protection
schemes the carrier signals send/receive in two channels. If one of the channels
fails this alarm appears.
PLAN OF ACTION
This alarm appears whenever power supply unit of fault locator fails (power
switch off position etc.) or some in built problem in the unit arises.
PLAN OF ACTION
50
Switchyard protection
This alarm appears whenever power supply unit of fault locator fails (power
switch off position etc.) or some in built problem in the unit arises.
PLAN OF ACTION
51
Switchyard protection
This alarm appears whenever power supply unit of D/R fails (power switch off
position etc.) Or some in built problem in the unit arises.
PLAN OF ACTION
PLAN OF ACTION
1 Check for the protection relay operations of the reactor and identify the
fault.
2 Check physically reactor and its NGR (Neutral grounding reactor)
observe any oil spillage in the surroundings, oil leakages, gas
accumulation in buchholz relay.
52
Switchyard protection
3 If any abnormality observed take permission from IOCC and trip the
line.
4 Inform to Maintenance group to attend the problem.
Cooler trouble alarm appears when one or more of the following conditions.
PLAN OF ACTION
PLAN OF ACTION
After getting clearance from SCE, DGM (EM), IOCC and AP TRANSCO
53
Switchyard protection
PLAN OF ACTION
1 The Transformer can be charged only after carrying out tests including
DGA and obtaining clearance in writing from EM dept.
2 In case the gas is not found in buchholz relay, the reason shall be
established for operation of buchholz relay and then the Transformer
should charged.
3 In case of air accumulated in Buchholz relay, the Transformer can be
charged after releasing the air.
This alarm appears when the winding. Temp/oil temp of the Transformer goes
beyond the set value.
PLAN OF ACTION
The magnetic oil level gauge fitted on the main conservator initiates
annunciation / trip in the event of the oil level falling below the preset levels
due to any reason.
54
Switchyard protection
PLAN OF ACTION
The load (current) on Transformer exceeds its rated (or set) value for more than
a specified time, then Transformer over loaded annunciation appears.
PLAN OF ACTION
Pressure release device allows for the rapid release of excessive pressure that
may be generated in the event of a serious fault in the Transformer. A bright
color coded Mechanical indicator pin in the cover moves with the valve disc
during operation of PRD and is held in position by an in the pin bushing. This
pin is clearly visible from the ground level indicating that the device is
operated.
55
Switchyard protection
PLAN OF ACTION
1 Check for any other protection relays operated to identify the problem.
2 Check for both LT and HT side breaker tripping. If any one of the
breaker in service hand trip the same.
3 Check for any gas accumulation in Buchholz relay
4 Transformer may be charged only after thorough investigation for the
reason of PRD operation and obtaining clearance from Maintenance
group.
Isolation and charging of high voltage equipment have great potential for
hazardous occurrences and need to consider safety at each juncture. Safety in
electrical system concerns three different areas; protection of life, protection of
equipment, protection of uninterrupted productive output. The protection of
human life is paramount. Equipment can be replaced lost production can be
made up. However, human life can never be recovered nor human sufferings
compensated. Therefore, only qualified and authorized persons shall be
allowed to operate switchyard equipment.
b) There must be checks and cross checks to confirm that you are at
right apparatus for the particular operation.
c) NO part of the body should touch any part of the equipment under
charging during isolation or normalization.
56
Switchyard protection
f) Operation staff for their own safety should use the personal protective
equipment like safety shoe, hand gloves etc. at work.
57
Switchyard protection
If the required shutdown is going to affect the power flow in the tie lines
connected to PGCIL substations, then shutdown concurrence must be
obtained from IOCC. For the line belongs to AP Transco, shutdown
concurrence must be obtained from LDC.
58
Switchyard protection
d) Check the line loads and ensure that the shutdown of the equipment,
should not make over loading the other lines or Transformers.
e) Identify the correct bay and concerned main and tie breakers to be
tripped for de energization of the line/ Transformer.
f) Keep the Auto Recloser switches of the main and tie breakers in N.A.
position.
i) Inform orally to the other end substation shift in charge regarding the de
energization of line/Transformer and hold him on line.
2. Confirm from the other end operator on telephone that the breaker at
their end tripped on intertrip signal.
59
Switchyard protection
1. Hand trip the main breaker of the line to be de energized if the line is
connected to main bus or the transfer bay breaker if the line is
connected to transfer bus.
2. Confirm from the other end operator on telephone that the breaker at their
end tripped on intertrip signal.
2. Hand trip line breaker (220 KV side) and inform the other end shift in
charge on phone that the Transformer is de energized and ensure that the
other end breaker tripped on intertrip signal.
60
Switchyard protection
4. Check the breaker on/off indication lamp and ensure the breaker is in
off position.
5. Check for the fall of flags in three phase of the trip relay.
2. Open the 400 KV side (HT) isolator from remote or local mode.
3. Open the 220kv/132kv side (LT) isolator either from remote or from
local position.
5. Close the 400kv side isolator earth switch and 220kv/132kv side
earth switches and lock them.
6. Keep the danger tags at breakers on/off handle giving the details of
the permit being issued.
7. Note down on the permit card the isolations done along with the
precautions to be taken further by the recipient at time of work carrying
the work and issue the permit card to the applicant.
61
Switchyard protection
b) Generally, voltage at charging end bus shall be kept below 400 kv before
charging of the line.
62
Switchyard protection
a) Ensure that all permits issued on Line equipment / the authorised area
Maintenance engineer canceled Transformer. Also, ensure that any
NBFC issued to the other end substation was returned back in writing.
b) Check physically the work area for removal of men and Material.
e) Check for SF6 gas and air/ oil pressure of main/ tiebreakers.
f) Ensure that the Local / Remote switches of the Main/ Tie breakers are
kept on remote position.
g) Check physically for the removal of all the temporary earthlings done
at the work site.
k) Ensure that disturbance recorder, fault recorder, and event logger are
in service.
m) Return back the NBFC obtained from the other end substation
through written message and take clearance in writing for charging
the line.
63
Switchyard protection
a) Open the earth switch of the line isolator. Also open the earth
switches of main and tie bay isolators if any closed position.
d) Close the tie bay isolators I the permits are not pending on Tie bay
equipment.
e) Close the shunt reactor isolator if shunt reactor available for the line
and it is in isolated condition.
In case of IOCC instructed to charge the line from this end and to synchronize
from the remote substation.
a) Inform IOCC that the line is ready for charging and take the final
clearance for charging the line.
b) Inform orally to the other end substation operator that the line is ready
for charging and hold him on line.
64
Switchyard protection
f) Close main/ tiebreaker which ever bay is made ready for charging the
line (dead line charging). Subsequently close the other breaker also If
the bay equipment not under permit.
g) Inform the remote end operator on telephone that the line is charged
and give clearance for synchronizing to the grid.
In case, IOCC instructed to charge the line at remote end and synchronize the
line this end.
a) Inform IOCC that the line is ready for synchronizing and take the final
clearance for synchronizing and take the final clearance for
synchronizing the line.
c) Once again, ascertain that the voltage and the frequency are within
synchronizing limits.
d) Inform orally to the other end substation operator that the line is going to
be synchronized and let him hold on line.
65
Switchyard protection
g) Close Main/ tiebreaker whichever bay is made ready for charging the
line. Subsequently close the other breaker also if the bay equipment not
under permits.
3. Check for heavy oil leaks if any from tank, radiator, pipes and
bushings.
5. Note down the WTI and OTI readings, confirm they are
working.
b) Open the earth switches of the 400 KV Bus side Isolator (HT) and
200Kv line side isolator (LT) . Also open the earth switches of main and
tie-bay isolators if any found in close position.
c) Check for any portable earthlings on bay equipment. If found any, request
Maintenance staff to remove the same.
d) Close 220 kv side isolators and 400 kv side main and tie bay isolators
provided the permits are not pending.
e) If isolators are closed in remote mode, check physically to confirm
all the three poles closed properly.
66
Switchyard protection
In case, AP Transco requested to change the 220 KV line from this end and to
synchronize at their substation.
a) Inform LDC that the 220 KV line is ready for charging and take the
final clearance for charging the line.
e) Close Main/ Tie breaker which ever bay is made ready for charging
the Transformer. Subsequently close the other breaker also if the bay
equipment not under permits.
g) Keep Auto recolor switch in NLA mode. Close the line breaker of the
feeder to be charged.
67
Switchyard protection
d) Close Main/ Tie breaker which ever bay is made ready for charging
the Auto Transformer. Subsequently close the other breaker also if
the bay equipment is not under permit.
i) Ascertain that the voltage and the frequency are within synchronizing
limits.
68
Switchyard protection
In case of total Blackout of station / region due to grid failure or partial grid
failure, operation staff are responsible.
2. Have a broad lock on the panel, see whether any unit has survived
on house load and / or any line feeding on house load has
survived.
3. Inform shift charge engineer and all units about the status on
emergency PA system through group call.
5. Check and not down the relays operated, ascertain the reasons of
cause leading to grid failure also whether it is from station side or
switchyard side or substation side.
6. See that all outgoing feeder breakers have opened out, if not, open
them manually.
69
Switchyard protection
In case of startup power not available form CHANDRAPUR S/S due to outage
of equipment or any other, reason the following alternate arrangements to be
made.
70
Switchyard protection
71
Switchyard protection
a) Close 400 KV breakers pertaining to above set feeder and thus charge
400 kV buses 1 or 2
b) Charge 400/33 kV Tie Transformer 1 or 2 or 3.
c) Charge 33 kV bus 1 and / r 2 and / or 3.
g) Due to lack of power, battery chargers had tripped and the ENTIRE
Batteries supplied load.
k) Now situation is normal. Once units are ready for synchronization seek
instructions from IOCC and LDC, accordingly take lines in service and
synchronize the units.
72
Switchyard protection
CONCLUSION
With advancement of power systems, line and other equipment
operates at high voltage and carry large current when a short circuit
occurs on the system heavy current flowing through the equipment
may cause damage. Switchyard is a place where the entire primary
protecting equipment of the power system is arranged in a systematic
manner to protect the generating station from the faults. It suppress
the faults by making them not to reach the generating unit. Thus, a
switchyard plays a vital role in the protection.
As non-renewable sources like coal will get extinguished in future it
is important to make use of every form of energy available naturally.
There is no advanced technology to utilize the over voltages occurred
due to lightning, let’s hope for that improved technology in near
future to save nonrenewable resources.
73
Switchyard protection
REFERENCES:
5) SWITCHYARD -WIKIPEDIA
74