Professional Documents
Culture Documents
ANBARASAN
RESTRUCTURED POWER SYSTEMS OPTIMAL POWER FLOW FOR ECONOMIC DISPATCH SOMETIMES THIS LEADS TO CONGESTION IN TRANSMISSION LINES THIS CREATES A LOT OF PROBLEMS LIKE HIGH POWER LOSSES , DIFFICULTY IN TRNSMITTING POWER
TO REDUCE CONGESTION WE HAVE TO RESCHEDULE THE GENERATION SCHEDULE WE LOOK AT SYSTEMS POOL DISPATCH BILATERAL DISPATCH NON-COST FREE METHODS RESCHEDULING CURTAILMENT OF LOAD COST FREE METHODS FACTS DEVICES, PHASE SHIFTERS
TO REDUCE CONGESTION IN RESTRUCTURED POWER SYSTEMS BY RESCHEDULING THE GENERATION SCHEDULE WITH NECESSARY MODIFICATIONS IN OPF PROBLEM FORMULATION
HUGE GROWTH IN LOAD DEMANDRESTRUCTURED POWER SYSTEMS CONGESTION-OPERATING CONDITION IN WHICH, NO ENOUGH TRANSMISSION CAPABILITY TO IMPLEMENT ALL THE TRADED TRANSACTIONS CONGESTION MANAGEMENT IDENTIFYING AND THEN RESCHEDULING THE GENERATION SCHEDULE
OPF PROBLEM IS FORMED AND SOLVED USING PARTICLE SWARM OPTIMISATION PSO IS MOTIVATED FROM BEHAVIOUR OF SOCIAL SYSTEMS INITIALLY A POPULATION IS FORMED RANDOMLY
MOVEMENT OF EACH PARTICLE DEPENDS ON BOTH ITS BEST AND GLOBAL BEST POSITION THIS ITERATIVE PROCESS CONTINUES TILL SPECIFIED NO OF ITERATIONS 3 AND 5 GENERATOR SYSTEMS WERE SOLVED FOR ECONOMIC DISPATCH WITH AND WITHOUT LOSSES USING PSO IN MATLAB 7.8
C1=500+5.3P1+0.004P1^2 200<P1<450
C2=400+5.5P2+0.006P2^2 150<P2<350 C3=200+5.8P3+0.009P3^2 100<P3<225 PD=975MW
6950
6900
6850
cost function
6800
6750
6700
6650
20
40
60
140
160
180
200
8360
8340
8320
cost function
8300
8280
8260
8240
8220
20
40
60
140
160
180
200
PROBLEM C1=200+7P1+0.008P1^2 10<P1<85 C2=180+6.3P2+0.009P2^2 10<P2<80 C3=140+6.8P3+0.007P3^2 10<P3<70 PL=0.0218P1^2+0.0228P2^ 2+0.0179P3^2 (BASE=150MW) PD=150MW
cost function
20
40
60
140
160
180
200
PROBLEM
C1=40+3.6P1+0.005P1^2 20<P<120
C2=60+3.4P2+0.004P2^2
C3=60+3.4P3+0.004P3^2
C4=50+3.5P4+0.0045P4^2 C5=40+3.5P5+0.0045P5^2 PD=260
1235
1230
1225
cost function
1220
1215
1210
1205
50
100
150 no of iterations
200
250
300
AFTER HAVING GENERATION SCHEDULE , WE HAVE TO CHECK WHETHER CONGESTION ARISES OR NOT FOR THIS WE WILL DO LOAD FLOW ANALYSIS USING NEWTON RAPHSON METHOD OBTAINED RESULTS WILL BE USED TO FIND POWER TO BE TRANSMITTED
INITIALLY NET POWER AVAILABLE AT EACH BUS IS CALCULATED FOR EACH BRANCH, CURRENT ENTERING FROM BOTH ENDS IS CALCULATED FOR EACH BRANCH, POWER FLOW IS FOUND ( S=VI*) THIS VALUE IS COMPARED WITH THE LINE MVA RATING
B.NO. 1 2
VM 1.06 1.0474
DELTA 0 -2.8063
3
4 5
0
0 0
0
0 0
0.45
0.4 0.6
0.15
0.05 0.1
1.0242
1.0236 1.0179
-4.997
-5.3291 -6.1503
STANDARD IEEE 3 GENERATOR 5 BUS SYSTEM WITH SPECIFIED GENERATION SCHEDULE IS CHECKED FOR CONGESTION IN MATLAB 7.8
LINE 1-2 1-3 MVA RATING 150 100 POWER TO BE TRANSMITTED 163.6 53.9
2-3
2-4 2-5 3-4 4-5
50
100 120 100 100
17.6
23.1 91.2 34.1 29.6
RESCHEDULE- BY INTRODUCING PENALTY FUNCTION IN PSO PENALTY FUNCTION CONVERTS CONSTRAINED PROBLEM INTO UNCONSTRAINED PROBLEM PENALTY FUNCTION IS VALUE PROPORTIONAL TO THE DEVIATION FROM CONSTRAINTS IT IS ADDED TO THE COST FUNCTION
OUR CASE-PROBLEM IS NOT COMPLETELY CONVERTED INTO UNCONSTRAINED ONLY CONGESTION IS CONSIDERED IN PENALTY FUNCTION AND ADDED TO COST FUNCTION EVERY TIME NEW POSITION IS CREATED, INTENSITY OF CONGESTION IS CALCULATED BY LOADFLOW AND LINEFLOW STUDIES AND ADDED TO COST FUNCTION
BUS NUMBER 1 2 3 4 5
ED SOLUTION TOTAL GEN COST CONGESTION LINE LOSSES TOTAL LOSSES NET POWER DELIVERED EFFECTIVE COST (RS/MWhr) P1=270,P2=100,P3=50 RS.3,01,500/13.64MW(IN 1-2 LINE) 11.4MW 25MW 420-25=395MW 848
2.46
x 10
2.44
2.42
cost function
2.4
2.38
2.36
2.34
20
40
60
140
160
180
200
x 10
cost function
20
40
60
140
160
180
200
STANDARD IEEE 14 BUS SYSTEM 30<P1<100; 0.3P1^2+3.4P2+30 20<P2<100; 0.5P2^2+3.51P2+44.4 20<P3<100; 0.5P3^2+3.89P3+40.6 50<P4<200; 0.5P4^2+2.45P4+105 50<P5<200; 0.3P5^2+2.2P5+110 TOTAL LOAD=260MW
RS.3,05,014.5/3.2 (5-6) MW
MW
LINE LOSSES TOTAL LOSSES NET POWER DELIVERED EFFECTIVE COST (RS/MWhr)
x 10
cost function
20
40
60
140
160
180
200
4.5
x 10
3.5
cost function
2.5
1.5
50
100
300
350
400
JANUARY: ECONOMIC DISPATCH FEBRUARY: LINEFLOW- IDENTIFYING CONGESTION MARCH: RESCHEDULING AND COMPARING THE OBTAINED RESULTS APRIL: MAKE CONCLUSIONS AND THESIS WORK
M A Pai and A S Nayak University of Illinois atUrbana-Champaign Masters thesis report and Project report Congestion management in restructured power systems using an Optimal power flow Frame work. D.N. Jeyakumar , T. Jayabarathi , T. Raghunathan ,Particle swarm optimization for various types of economic dispatch problems Electrical Power and Energy Systems 28 (2006) 3642 Congestion management in hybrid power markets, Yu Xiao , Peng Wang, L.Goel Vestas Technology R&D Singapore pte Ltd , Connexis, 1 Fusionopolis Way, #06-10, Singapore 138632, Singapore bschool of EEE, Nanyang Technological University, Singapore 639798, singapore Congestion Management Using Multiobjective Particle Swarm Optimization, Jagabondhu Hazra and Avinash K. Sinha IEEE
D. Shirmohammadi et al., Transmission dispatch and congestion management in the emerging energy market structures, IEEE Transactions on Power Systems, vol. 13, no. 4, pp. 1466-1474, November 1998. Congestion management using adaptive bacterial foraging algorithm B.K.panigrahi, V.Ravikumar Pandi Department of Electrical Engineering, Indian Institute of Technology, Delhi Congestion management in competetive power market: a bibilographical survey, Electrical power system research 2005;76:153-64 Kumara A Srivastava SC, Singh S.N.