You are on page 1of 1

JADUAL KERJA UNTUK PERMOHONAN GANGGUAN AIR BERJADUAL DI JALAN 3/155 DAN 4/155, TAMAN BUKIT OUG ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Task

Name H-2 Gangguan Bekalan Air Berjadual 330mm MS Taman Bukit OUG Shutdown water supply and discharge the water Dewatering and dicharge the balance water to nearest drain Connection 1 (OUG Condo) Cut existing main pipe with the required legths Welding Work (300mm MS Flange) Install Valve and Flange Adaptor Connection 2 (OUG Condo) Cut existing main pipe with the required legths Prefabricated 300mm Short Piece and 45 Bend to be installed Welding Work for 300mm Collar at both side Connection 3 (OUG Condo) Cut existing main pipe with the required legths Prefabricated 300mm Short Piece and 45 Bend to be installed Welding Work for 300mm Collar at both side Connection 4 (Jalan 4/155) Cut existing main pipe with the required legths Prefabricated 300mm Short Piece and 45 Bend to be installed Welding Work for 300mm Collar at both side Connection 5 (PPR Muhibbah) Cut existing main pipe with the required legths Prefabricated 45 Bend and 250mm reducer to be installed Welding Work for 300mm Collar at new pipe and 250mm Collar at existing pipe Connection 6 (PPR Muhibbah) Cut existing main pipe with the required legths Prefabricated 90 Bend and 250mm reducer to be installed Welding Work for 300mm Collar at new pipe and 250mm Collar at existing pipe Flushing and reopen water supply Recovering water H-1 H1 H2 H3 H4 H5 H6 H7 H8 H9

Task Project: Permohonan Gangguan Air Be Date: 18/5/2012 Split Progress

Milestone Summary Project Summary Page 1

External Tasks External Milestone Deadline

You might also like