You are on page 1of 5

Crystalline Chemical Industry PVT Ltd

Mechanical jobs: 25-10-2023

Workshop:

 Machining and face the 12” MS flange for ETP area work is completed.
 Dismantled the P412 change its mechanical seal and both bearing work is
completed.
 Machining and welding the rotor AG3000B motor work is completed.
 Machining and facing to make the teflon washer for diesel peter engine
work is completed.
 Two flexible shafts of boiler are repaired and maintenance, work is
completed.
 Welding and resizing of the shaft of P412 work is completed.
 One adopter is prepared for the cleaning shaft work is completed.
 Dismantled the P308B change its mechanical seal and both bearing work
is completed.
 Spare centrifugal pump change its bearing and whole maintenance work
is in progress.
 Cleaning the lathe, drill and shaper machine work is completed.

General work:

 Checked the all welding plants & covered them work is completed.

Distillation Area/ Fermentation Area:

 Welding cutting and grinding the R428 to ready the fiber glass coating
work is in progress.
 Welding cutting and grinding the R427 to ready the fiber glass coating
work is in progress.
 Welding cutting and grinding to install the new MS plates bottom of
R428 tank work is in progress.
 Dismantled the 8” setup valve of R411 tank for cleaning purpose work is
completed.
 Dismantled the 8” setup valve of R412 tank for cleaning purpose work is
completed.
 Dismantled the 8” setup valve of R413 tank for cleaning purpose work is
completed.
 After cleaning air sparger of R411 boxed up work is completed.
 Dismantled the bottom main hole of R305 decanter for cleaning purpose
work is completed.
 Welded the MS patch of 5’*8” at R422 tank work is completed.
 Welded the MS patch of 5’*8” at R423 tank work is completed.
 After tube cleaning boxed up the side two main hole of E401 work is
completed.
 Dismantled the suction and discharge pipe line of P308 pump for
cleaning purpose after cleaning boxed up work is in progress.
 Dismantled the inlet and outlet pipelines of H.E302 pump for cleaning
purpose after cleaning again boxed up work is in progress.
 The line of R304 is dismantled towards pump P308 for cleaning and
inspection purpose work is in progress.
 The all butterfly valves at the line of R430 are dismantled for cleaning
purpose after cleaning again boxed up.
 After washing one side main hole of E526 is boxed up work is in
progress.
 Dismantled the main ways of C540 column, work is completed.
 Overhauling work of all pumps in distillation, work is in progress.
 Dismantled the P308B pump for maintenance and bring to mechanical
work shop work is in progress.
 Dismantled the P412 pump for maintenance and bring to mechanical
work shop work is in progress.
 Dismantled the P550A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P535A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P545A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P530A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P561A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P563A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P543A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P560A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P565A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P500A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P546A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P540A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P510A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P515A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P501A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P525A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P562A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P541A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P555A motor for overhauling and hand over to electrical
department work is completed.
 Dismantled the P520A, B motor for overhauling and hand over to
electrical department work is completed.
 Dismantled the P521A, B motor for overhauling and hand over to
electrical department work is completed.
ETP Area:

 The 12” biogas line coming from ETP to boiler is dismantled and bring
down with the assistance of crane for cleaning purpose, work is in
progress.
 The 12” biogas line coming from ETP to Flair tip is dismantled and
brings down with the assistance of crane for cleaning purpose, work is in
progress.
 The work of replacing the damaged 12” MS Biogas line of Flair tip is in
progress.
 Dismantled the over flow lines digesters with the help of crane work is in
progress.
 All clarifier’s outlet lines were dismantled for cleaning purpose after
cleaning boxed up the line work is in progress.
 Dismantled the 8” bottle lines of all digester for cleaning purpose work is
in progress.
 The work of replacing the damaged 12” MS Biogas line is in progress.
 Dismantled the 12” main biogas line for cleaning purpose after cleaning
again boxed up the lines work is in progress.
 The work of replacing the damaged 12” MS Biogas elbow is in progress.
 After cleaning boxed up the suction and discharge side 6” biogas line of
all blowers work is in progress.
 Install and operate the 5” submersible pump near STP area work is
completed.

Boiler House:

 Cutting of damaged plates in chain carrier of boiler house work is in


progress.
 Cutting the new MS plates for main chain carrier work is in progress.
 Cutting the damaged flat bar of main chain Baggass carrier work is in
progress.
 A new SS line of biogas is prepared of size 4” and the welding work is in
progress.
 Cutting the new 48 MS tubes for air pre heater work is completed.
Drain nala:

 Operate the 30HP diesel peter engine near Based wala point for effluent
transfer work is completed.
 Operate the 25HP diesel peter engine at kamena wala dera point for
effluent transfer work is completed.
 Operate the 5”F submersible pump at pit no 3 for effluent transfer work
is completed.

Sultan concrete:

 Checked the all machineries solved their problems work is completed.


 Cleaning the all gear in tuff tile plant 1 and tuff tile plant 2 work is
completed.

Pre-cast plant:

 Checked the all machineries solved their problems work is completed.

Manager Mechanical

You might also like