You are on page 1of 23

S.

No
A)Estimated Amount Rs.20.00 lakhs:-
1 Doors to Ground floor of Block No.3---4 Nos
2 Windows to ground floor of Block No.3---12 Nos
3 Platerings,Paintings&Flooring to G.F
4 Construction of 1 st floor of plinth area 320 Sqm
5 Construction of Block No.4 of plinth area 104 Sqm
Asst.Exe. Engineer, Dy.Exe. Engineer,
Panchayat Raj, Panchayat Raj,
Ichapuram Ichapuram
All items completed
Details of Items taken up by the Panchayat Raj Department
For the Govt.Degree College at Ichapuram
Description of Item taken up Remarks
DISTRICT : SRIKAKULAM
CIRCLE : SRIKAKULAM
DIVISION : TEKKALI
SUB-DIVISION : ICHAPURAM
MANDAL : ICHAPURAM
GRANT:-COLLEGE EDUCATION
ESTIMATED COST:-Rs.20.00 lakhs
GOVERNMENT OF ANDHRA PRADESH
PANCHAYATRAJ ENGINEERING DEPARTMENT
Buildings and amenities to the Degree College at Ichapuram
Name of the work:-Buildings and amenities to the Degree college at Ichapuram
Est.Cost.Rs.20.00 lakhs
The work"Buildings and amenities to the Degree College at Ichapuram",Est.Cost.Rs.20.00 lakhs
was administratively sanctioned under COLLEGE EDUCATION grant for the year 2004-2005 vide
Progs.Rc.No.126/AII-1/2004-05 Dt.18.3.2005 of the Director of Collegiate Education,AP
One building sanctioned under the work"Additional accomodation to Govt.Degree college at Ichapuram is
under progress and it will be left incomplete even for the G.F, due to insufficient funds.
The following items will be left incomplete pertaining to that building:-
1.Plastering with CM(1:5) 12mm thick for the entire building
2.Snowcem painting for the entire building
3.Construction of steps to the building&Dias in the class rooms
4.Four Nos.of 1.20X2.55m size doors including ventilators of height 0.45m
5.Twelve Nos.of 1.80X1.80m size windows including ventilators of height 0.45m
Further,it is proposed to construct 1st floor over the above building after its completion.The connected designs
are already approved by the SE,PR,SKLM for two stories block earlier under the work"Construction of Govt.Degree college
at Ichapuram",Est.Cost.Rs.20.00 lakhs.The same designs adopted in the present estimate.(Copy enclosed along with
drawings)
Further,it is proposed to construct one additional administrative block of size 9.00mX7.50m from the balance
amount.The designs of 7.50mX12.00m size room,which are approved earlier, are adopted because the effective span of
beams and slab is 7.50m for both the buildings.
Hence the estimate is prepared with the following provisions:-
A.Completion of incomplete Ground floor:-
1.Plastering with CM(1:5) 12mm thick for the entire building
2.Snowcem painting for the entire building
3.Construction of steps to the building&Dias in the class rooms
4.Four Nos.of 1.20X2.55m size doors including ventilators of height 0.45m
5.Twelve Nos.of 1.80X1.80m size windows including ventilators of height 0.45m
B.Construction of Additional floor over the ground floor
C.Construction of Additional ADMINISTRATIVE BLOCK of size 9.00mX7.50m
D.Provision for engaging technical person
E.Provision for insurance
F.Provision for Q.C.Inspection charges
G.Provision for investigation charges
The estimate is prepared as per the current SSR,i.e.2004-2005 rates and the work will be carried
out as per APDSS.
Asst.Executive Engineer Dy.Executive Engineer Executive Engineer
PR(spl),Ichapuram PR,Ichapuram PR,Tekkali
SPECIFICATION REPORT
Est.Cost.Rs.20.00 lakhs
One building sanctioned under the work"Additional accomodation to Govt.Degree college at Ichapuram is
Further,it is proposed to construct 1st floor over the above building after its completion.The connected designs
are already approved by the SE,PR,SKLM for two stories block earlier under the work"Construction of Govt.Degree college
at Ichapuram",Est.Cost.Rs.20.00 lakhs.The same designs adopted in the present estimate.(Copy enclosed along with
Further,it is proposed to construct one additional administrative block of size 9.00mX7.50m from the balance
amount.The designs of 7.50mX12.00m size room,which are approved earlier, are adopted because the effective span of
The estimate is prepared as per the current SSR,i.e.2004-2005 rates and the work will be carried
SPECIFICATION REPORT
Name of the work:-Construction of Additional Accomodation(1st Floor) to the existing District Consumer Forum
Building at Eluru
Est.Cost.Rs.9.20 lakhs
S.No Description of item Nos Quantity Rate Per Amount
Length Bredth Depth
1
Wall in Judge Room 1X1 4.8 0.23 4.25 4.69Cum
Deduct door 1X1 1.05 0.23 1.95 -0.47Cum
4.22Cum
2
In Judge room 1X1 ---- ---- ---- 1Nos
3
1X1 4.8 0.23 0.55 0.61Cum
4
For Columns 1X12 3.1 0.23 0.3 2.57Cum
1X6 3.25 0.23 0.3 1.35Cum
3.92Cum
5
T-Beams in R/S portion 1X6 5.13 0.23 0.45 3.19m
Rear end T-Beam in
R/S portion 1X1 1.63 0.23 0.23 0.09m
Longitudinal beams in
R/S portion 1X2 14.7 0.23 0.23 1.56m
Deduct Junction
locations 2x6 0.23 0.23 0.23 -0.15m
T-Beams in L/S portion 1X3 3.9 0.23 0.3 0.81m
Front end T-Beam in
L/S portion 1X1 1.63 0.23 0.23 0.09m
Longitudinal beams in
L/S portion 1X2 7.8 0.23 0.23 0.83m
Deduct Junction
locations 2x3 0.23 0.23 0.23 -0.07m
6.35Cum
6
Main hall portion 1X1 13.8 11.1 ---- 153.18Sqm
Deduct existing slab 1X1 5.7 4.2 ---- -23.94Sqm
Front R/S extra portion 1X1 5.45 1.2 ---- 6.54Sqm
135.78Sqm
7
Main hall portion 1X1 13.8 11.1 ---- 153.18Sqm
Deduct existing slab 1X1 5.7 4.2 ---- -23.94Sqm
Front R/S extra portion 1X1 5.45 1.2 ---- 6.54Sqm
Detailed-Cum-Abstract Working Estimate
Measurements
Dismantling,clearing away and carefully stacking materials useful for re-use for Brick masonry including all labour
VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing and vibrating charges,sienorage charges but excluding cost and fabrication charges of
steel for Roof slab of 100mm thick in 1st floor
Providing 300mm dia DUR piles to a depth of 2.50m fill with RCC(1:2:4) mix using 20mm HBG chips with required
quantity of steel per cum of concrete including cost and conveyance of all materials and all labour charges such as
cutting bores with augers and underreams with reamer set etc.complete.
VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing and vibrating charges,sienorage charges but excluding cost and fabrication charges of
steel for Plinth beam in Ground floor
VRCC(1:11/2:3) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing and vibrating charges,sienorage charges but excluding cost and fabrication charges of
steel for Columns in 1st floor
VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing and vibrating charges,sienorage charges but excluding cost and fabrication charges of
steel for T-Beams in 1st floor
Acco-Proof plastering in CM(1:3) mix to 12mm thick using 1.5 Kg of Acco-Proof powder per 1 bag of cement
including cost and conveyance of all materials and all labour charges etc.complete
S.No Description of item Nos Quantity Rate Per Amount
Length Bredth Depth
Measurements
135.78Sqm
8
Lintels over main doors 1X4 1.65 0.23 0.15 0.23Cum
Lintels over toilet door 1X1 1.3 0.23 0.15 0.04Cum
Lintels over windows 1X8 1.35 0.23 0.15 0.37Cum
0.64Cum
9
Over windows 1X8 1.35 ---- ---- 10.80m
In Judge room 1X1 4.8 0.23 3.7 4.08Cum
Deduct door 1X1 1.05 0.23 1.95 -0.47Cum
3.61Cum
10
Room-I on left side 1X1 19.38 0.23 3.05 13.60Cum
Deduct Door 1X1 1.05 0.23 2.15 -0.52Cum
Deduct windows 1X3 1.5 0.23 1.35 -1.40Cum
Deduct ventilators 1X5 0.6 0.23 0.23 -0.16Cum
Room-II on right side 1X1 27.12 0.23 3.05 19.02Cum
Deduct Door 1X2 1.05 0.23 2.15 -1.04Cum
Deduct windows 1X3 1.5 0.23 1.35 -1.40Cum
Deduct ventilators 1X7 0.6 0.23 0.23 -0.22Cum
Room-III on right side 1X1 16.24 0.23 3.05 11.39Cum
Deduct Door 1X1 1.05 0.23 2.15 -0.52Cum
Deduct windows 1X2 1.5 0.23 1.35 -0.93Cum
Deduct ventilators 1X5 0.6 0.23 0.23 -0.16Cum
Back side wall in corridor 1X1 1.35 0.23 3.05 0.95Cum
Cross walls for toilet 1X1 2.05 0.23 3.05 1.44Cum
Deduct Door 1X1 0.7 0.23 2.2 -0.35Cum
Deduct ventilators 1X1 0.6 0.23 0.23 -0.03Cum
Deduct Lintels over main doors 1X4 1.65 0.23 0.15 -0.23Cum
Deduct Lintel over toilet door 1X1 1.3 0.23 0.15 -0.04Cum
Deduct Lintels over windows1X8 1.35 0.23 0.15 -0.37Cum
39.03Cum
11
Parapet wall on roof A/R 1X1 55.50 0.1 0.75 4.16Cum
Add for brick pillars 1X28 0.23 0.13 0.75 0.63Cum
4.79Cum
12
In Judge Room both sides 1X2 4.8 ---- 3.15 30.24Sqm
Deduct door 1X2 1.05 ---- 1.95 -4.10Sqm
Add for sides 1X2 ---- 0.13 1.95 0.51Sqm
26.65Sqm
13
Ceiling of Room-I 1X1 5.45 3.78 ---- 20.60Sqm
Sides of T-Beams 1X2 3.78 ---- 0.3 2.27Sqm
Ceiling of Room-II 1X1 8.4 4.7 ---- 39.48Sqm
Sides of T-Beams 2x2 4.7 ---- 0.45 8.46Sqm
Ceiling of Room-III 1X1 5.54 4.7 ---- 26.04Sqm
Sides of T-Beams 1X2 3.78 ---- 0.45 3.40Sqm
Brick Masonry in CM(1:8) using 2nd class Bricks including cost and conveyance of all materials and all labour
charges etc.complete for walls in 2nd floor on roof with lift charges
Plastering with 12mm thick in CM(1:5) including cost and conveyance of all materials and all other labour
charges,sienorage charges and other incidental charges like scaffolding charges etc.complete in Ground Floor
Ornamental Plastering with 6mm thick in CM(1:3) proportion with dubara sponge finishing including cost and
conveyance of all materials at work site and all operational,incidental,sienorage charges and all labour charges
RCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing and vibrating charges,sienorage charges but excluding cost and fabrication charges of
steel for Lintels
RCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials and all labour charges
including machine mixing charges,sienorage charges but excluding cost and fabrication charges of steel for sun
shades of 0.60m width,0.075m thick at fixed end and 0.05m thick at free end for 1st floor
Brick Masonry in CM(1:8) using 2nd class Bricks including cost and conveyance of all materials and all labour
charges etc.complete for walls in Ground Floor
Brick Masonry in CM(1:8) using 2nd class Bricks including cost and conveyance of all materials and all labour
charges etc.complete for walls in 1st floor with lift charges
S.No Description of item Nos Quantity Rate Per Amount
Length Bredth Depth
Measurements
Ceiling of Toilet&Front open portion 1X1 3.78 2.05 ---- 7.75Sqm
Ceiling of Corridor 1X1 14.63 1.35 ---- 19.75Sqm
Sun shades 1X8 1.35 0.8 ---- 8.64Sqm
136.39Sqm
14
In side:-
Room-I on left side 1X1 19.38 ---- 3.35 64.92Sqm
Deduct Door 1X1 1.05 ---- 2.15 -2.26Sqm
Add for sides of door 1X2 ---- 0.13 2.15 0.56Sqm
Deduct windows 1X3 1.5 ---- 1.35 -6.08Sqm
Add for sides of windows 2x3 ---- 0.13 1.5 1.17Sqm
Add for sill 1X3 1.35 0.13 ---- 0.53Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Add for sides of ventilators 1X5 1.66 0.19 ---- 1.58Sqm
Room-II on right side 1X1 27.12 ---- 3.35 90.85Sqm
Deduct Door 1X2 1.05 ---- 2.15 -4.52Sqm
Add for sides of door 2x2 ---- 0.13 2.15 1.12Sqm
Deduct windows 1X3 1.5 ---- 1.35 -6.08Sqm
Add for sides of windows 2x3 ---- 0.13 1.5 1.17Sqm
Add for sill 1X3 1.35 0.13 ---- 0.53Sqm
Deduct ventilators 1X7 0.6 ---- 0.23 -0.97Sqm
Add for sides of ventilators 1X7 1.66 0.19 ---- 2.21Sqm
Room-III on right side 1X1 16.24 ---- 3.35 54.40Sqm
Deduct Door 1X1 1.05 ---- 2.15 -2.26Sqm
Add for sides of door 1X2 ---- 0.13 2.15 0.56Sqm
Deduct windows 1X2 1.5 ---- 1.35 -4.05Sqm
Add for sides of windows 2x2 ---- 0.13 1.5 0.78Sqm
Add for sill 1X2 1.35 0.13 ---- 0.35Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Add for sides of ventilators 1X5 1.66 0.19 ---- 1.58Sqm
In side walls of Toilet room left side 1X2 2.05 ---- 3.35 13.74Sqm
Deduct Door 1X1 0.7 ---- 2.2 -1.54Sqm
Add for sides of door 1X2 ---- 0.13 2.2 0.57Sqm
Deduct ventilator 1X1 0.6 ---- 0.23 -0.14Sqm
Add for sides of ventilators 1X1 1.66 0.19 ---- 0.32Sqm
Back side wall 1X1 1.35 ---- 3.35 4.52Sqm
212.18Sqm
15
Out side:-
Right side A/R 1X1 39.58 ---- 3.35 132.59Sqm
Deduct Doors 1X3 1.05 ---- 2.15 -6.77Sqm
Deduct Windows 1X5 1.5 ---- 1.35 -10.13Sqm
Deduct ventilators 1X12 0.6 ---- 0.23 -1.66Sqm
Back side wall out side 1X1 1.35 ---- 3.35 4.52Sqm
Right side room A/R 1X1 20.30 ---- 3.35 68.01Sqm
Deduct Doors 1X1 1.05 ---- 2.15 -2.26Sqm
Deduct Windows 1X3 1.5 ---- 1.35 -6.08Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Out side walls of Toilet room1X2 2.05 ---- 3.35 13.74Sqm
Deduct Door 1X1 0.7 ---- 2.2 -1.54Sqm
Deduct ventilator 1X1 0.6 ---- 0.23 -0.14Sqm
189.59Sqm
16
1X1 4.55 4.25 0.1 1.93Cum
17
Parapet wall A/R 1X1 55.50 ---- 1.6 88.80Sqm
Add for brick pillar sides 2x28 ---- 0.13 0.75 5.46Sqm
94.26Sqm
Plastering with 12mm thick in CM(1:5) including cost and conveyance of all materials and all other labour
charges,sienorage charges and other incidental charges like scaffolding charges etc.complete in 2nd Floor
Plastering with 12mm thick in CM(1:5) including cost and conveyance of all materials and all other labour
charges,sienorage charges and other incidental charges like scaffolding charges etc.complete in 1st Floor
Plastering with 20mm thick in CM(1:5) including cost and conveyance of all materials and all other labour
charges,sienorage charges and other incidental charges like scaffolding charges etc.complete in 1st Floor
CC(1:2:4) mix using 20mm HBG metal including cost and conveyance of all materials,sienorage charges and all
labour charges etc.complete for flooring
S.No Description of item Nos Quantity Rate Per Amount
Length Bredth Depth
Measurements
18
In Judge room 1X1 4.55 4.25 ---- 19.34Sqm
Extra at entrance 1X1 0.95 0.3 ---- 0.29Sqm
Extra at Court hall entrance with steps 1X1 1.05 1.15 ---- 1.21Sqm
Skirting A/R room 1X1 17.6 ---- 0.1 1.76Sqm
Deduct main doors 1X3 1.05 ---- 0.1 -0.32Sqm
Deduct toilet door 1X1 0.75 ---- 0.1 -0.08Sqm
22.20Sqm
19
Ceiling in Judge room 1X1 4.55 4.25 ---- 19.34Sqm
20
Ceiling of Room-I 1X1 5.45 3.78 ---- 20.60Sqm
Sides of T-Beams 1X2 3.78 ---- 0.3 2.27Sqm
Ceiling of Room-II 1X1 8.4 4.7 ---- 39.48Sqm
Sides of T-Beams 2x2 4.7 ---- 0.45 8.46Sqm
Ceiling of Room-III 1X1 5.54 4.7 ---- 26.04Sqm
Sides of T-Beams 1X2 3.78 ---- 0.45 3.40Sqm
Ceiling of Toilet&Front open portion 1X1 3.78 2.05 ---- 7.75Sqm
Ceiling of Corridor 1X1 14.63 1.35 ---- 19.75Sqm
Room-I on left side 1X1 19.38 ---- 3.35 64.92Sqm
Deduct Door 1X1 1.05 ---- 2.15 -2.26Sqm
Add for sides of door 1X2 ---- 0.13 2.15 0.56Sqm
Deduct windows 1X3 1.5 ---- 1.35 -6.08Sqm
Add for sides of windows 2x3 ---- 0.13 1.5 1.17Sqm
Add for sill 1X3 1.35 0.13 ---- 0.53Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Add for sides of ventilators 1X5 1.66 0.19 ---- 1.58Sqm
Room-II on right side 1X1 27.12 ---- 3.35 90.85Sqm
Deduct Door 1X2 1.05 ---- 2.15 -4.52Sqm
Add for sides of door 2x2 ---- 0.13 2.15 1.12Sqm
Deduct windows 1X3 1.5 ---- 1.35 -6.08Sqm
Add for sides of windows 2x3 ---- 0.13 1.5 1.17Sqm
Add for sill 1X3 1.35 0.13 ---- 0.53Sqm
Deduct ventilators 1X7 0.6 ---- 0.23 -0.97Sqm
Add for sides of ventilators 1X7 1.66 0.19 ---- 2.21Sqm
Room-III on right side 1X1 16.24 ---- 3.35 54.40Sqm
Deduct Door 1X1 1.05 ---- 2.15 -2.26Sqm
Add for sides of door 1X2 ---- 0.13 2.15 0.56Sqm
Deduct windows 1X2 1.5 ---- 1.35 -4.05Sqm
Add for sides of windows 2x2 ---- 0.13 1.5 0.78Sqm
Add for sill 1X2 1.35 0.13 ---- 0.35Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Add for sides of ventilators 1X5 1.66 0.19 ---- 1.58Sqm
In side walls of Toilet room left side 1X2 2.05 ---- 3.35 13.74Sqm
Deduct Door 1X1 0.7 ---- 2.2 -1.54Sqm
Add for sides of door 1X2 ---- 0.13 2.2 0.57Sqm
Deduct ventilator 1X1 0.6 ---- 0.23 -0.14Sqm
Add for sides of ventilators 1X1 1.66 0.19 ---- 0.32Sqm
335.41Sqm
21
In Judge room 1X1 17.60 ---- 3.05 53.68Sqm
Deduct Main doors 1X3 1.05 ---- 1.95 -6.14Sqm
Deduct toilet door 1X1 0.75 ---- 1.95 -1.46Sqm
Deduct windows 1X2 1.35 ---- 1.5 -4.05Sqm
Other side of Judge room 1X1 4.80 ---- 2.75 13.20Sqm
In court room 1X2 1.10 ---- 2.65 5.83Sqm
Deduct ventilator 1X1 0.60 ---- 0.3 -0.18Sqm
60.88Sqm
Flooring with Ceramic glazed tiles of all shades of 7.3mm thick pointed with CM(1:6)--12mm thick including cost
and conveyance of all materials and all labour charges etc.complete
Painting with white cement paint two coats over anewly plastered surface including cost and conveyance of all
materials and all labour charges etc.complete inside rooms Ground floor
Painting with white cement paint two coats over a newly plastered surface including cost and conveyance of all
materials and all labour charges etc.complete inside rooms for 1st floor
Painting with snowcem paint two coats over a primary coat of white cement paint including cost and conveyance of
all materials and all labour charges etc.complete inside rooms Ground floor
S.No Description of item Nos Quantity Rate Per Amount
Length Bredth Depth
Measurements
22
Right side A/R 1X1 39.58 ---- 3.35 132.59Sqm
Deduct Doors 1X3 1.05 ---- 2.15 -6.77Sqm
Deduct Windows 1X5 1.5 ---- 1.35 -10.13Sqm
Deduct ventilators 1X12 0.6 ---- 0.23 -1.66Sqm
Back side wall out side 1X1 1.35 ---- 3.35 4.52Sqm
Right side room A/R 1X1 20.30 ---- 3.35 68.01Sqm
Deduct Doors 1X1 1.05 ---- 2.15 -2.26Sqm
Deduct Windows 1X3 1.5 ---- 1.35 -6.08Sqm
Deduct ventilators 1X5 0.6 ---- 0.23 -0.69Sqm
Out side walls of Toilet room1X2 2.05 ---- 3.35 13.74Sqm
Deduct Door 1X1 0.7 ---- 2.2 -1.54Sqm
Deduct ventilator 1X1 0.6 ---- 0.23 -0.14Sqm
In side of Back side wall 1X1 1.35 ---- 3.35 4.52Sqm
Sun shades 1X8 1.35 0.8 ---- 8.64Sqm
23
Parapet wall A/R 1X1 55.50 ---- 1.6 88.80Sqm
Add for brick pillar sides 2x28 ---- 0.13 0.75 5.46Sqm
94.26Sqm
24
Size 1.05X2.15 1X4 ---- ---- ---- 4Nos
25
Size 0.76X2.15 1X1 ---- ---- ---- 1Nos
26 Supplying Aluminium anodised openable sliding window,ventilator including anodisation cost
85Kgs
27 Sun control to the glazed window partitions including labour charges
Windows 1X8 1.5 ---- 1.35 16.20Sqm
28 Cost and supply of plain float glass 4mm thick
Windows 1X8 1.5 ---- 1.35 16.20Sqm
29
Windows 8x2.75 1.5 ---- 1.35 44.55Sqm
Doors 4x2.25 1.05 ---- 2.15 20.32Sqm
Toilet door 1x2.25 1.05 ---- 2.15 5.08Sqm
69.95Sqm
30 Cost and supply of steel reinforcement including fabrication charges 2830.00Kg
31 Provision for VAT@2.8% --------------LS--------------------
32 Provision for engaging technical person --------------LS--------------------
33 Provision for insurance --------------LS--------------------
34 Deduct tender percentage --------------LS--------------------
35 Provision for unforeseen items during execution --------------LS--------------------
TOTAL
Painting with snowcem paint two coats over a primary coat of white cement paint including cost and conveyance of
all materials and all labour charges etc.complete inside rooms of 1st floor
Painting with snowcem paint two coats over a primary coat of white cement paint including cost and conveyance of
all materials and all labour charges etc.complete inside rooms of 2nd floor
Supplying and fixing of Sal wood fully panelled(Hyderabad) Doors of various sizes including fixing of necessary
furnitures and fittings like Z- hold fasts,tower bolts,hinges,Aldrops,wind appliances,door bufferes and all labour
charges etc.complete
Supplying and fixing of Sal wood fully panelled(Hyderabad) Doors of various sizes including fixing of necessary
furnitures and fittings like Z- hold fasts,tower bolts,hinges,Aldrops,wind appliances,door bufferes and all labour
charges etc.complete
Painting with Synthetic enamil paint two coats over a primary coat of wood primer including cost and conveyance of
all materials and all labour charges etc.complete for 1st floor
Name of the work:-Buildings and amenities to the Degree college at Ichapuram
Est.Cost.Rs.20.00 lakhs
S.No Quantity Description of item Rate Per Amount
Ground floor
1 Earth work exacavation and depositing on the bank with an initial
lead and lift in loamy and clayey soils as per SS-20B by manual
labour
1.00Cum Earth work excavation 28.00 1.00Cum 28.00
1.00Cum Seinorage charges 20.00 1.00Cum 20.00
Add MBA 20% 5.60
Add TOT@4% 2.14
TOTAL 55.74
2 Cement Mortor (1:3) (1:5) (1:6)
1.00Cum Cost of sand 182.64 182.64 182.64
2700/1MT Cost of Cement 1296.00 777.60 648.00
1.00Cum Mixing charges 19.00 19.00 19.00
Add MBA 20% 3.80 3.80 3.80
1501.44 983.04 853.44
3 Plastering with CM(1:5) 20mm thick including all materials and all labour charges etc.complete
0.21Cum Cost of CM(1:5) 983.04 1.00Cum 206.44
10Sqm Labour charges 674.44 10Sqm 674.44
Add MBA 20% 134.89
Add TOT@4% 40.63
TOTAL 1056.40
4 Plastering with CM(1:5) 12mm thick including all materials and all labour charges etc.complete
0.15Cum Cost of CM(1:5) 983.04 1.00Cum 147.46
10Sqm Labour charges 311.97 10Sqm 311.97
Add MBA 20% 62.39
Add TOT@4% 20.87
TOTAL 542.69
5 Plastering with CM(1:3) 20mm thick with approved cement colour for threading and dotting of walls for black
board including all materials and all labour charges etc.complete
0.21Cum Cost of CM(1:3) 1501.44 1.00Cum 315.30
2.00Kg Cost of approved cement colour 50.00 1.00Kg 100.00
10Sqm Labour charges 674.44 10Sqm 674.44
Add MBA 20% 134.89
Add TOT@4% 48.99
TOTAL 1273.62
6 Cement Concrete(1:4:8) mix using 40mm HBG metal including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 40mm HBG metal 438.70 1.00Cum 403.60
0.46Cum Cost of sand 182.64 1.00Cum 84.01
166.00Kg Cost of cement 2700.00 1000.00Kg 448.20
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
DATA SHEET
S.No Quantity Description of item Rate Per Amount
Add MBA 20% 70.11
Add TOT@4% 56.76
TOTAL 1475.73
7 Cement Concrete(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 20mm HBG metal 639.70 1.00Cum 588.52
0.46Cum Cost of sand 182.64 1.00Cum 84.01
330.00Kg Cost of cement 2700.00 1000.00Kg 891.00
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
Add MBA 20% 70.11
Add TOT@4% 81.87
TOTAL 2128.55
8 Brick Masonry in CM(1:6) using 2nd class Bricks including cost and conveyance of all materials
and all labour charges etc.
512Nos Cost of bricks 1462.88 1000Nos 748.99
0.20Cum Cost of CM(1:6) 853.44 1.00Cum 170.69
1.00Cum Labour charges 474.18 1.00Cum 474.18
Add MBA 20% 94.84
Add TOT@4% 59.55
TOTAL 1548.25
9 R.R.Masonry in CM(1:6) using Rough stone(OTG) including cost and conveyance of all materials
and all labour charges etc.
1.10Cum Cost of Rough Stone(OTG) 209.20 1.00Cum 230.12
0.34Cum Cost of CM(1:6) 853.44 1.00Cum 290.17
1.00Cum Labour charges 528.86 1.00Cum 528.86
Add MBA 20% 105.77
Add TOT@4% 46.20
TOTAL 1201.12
10 Cement Concrete(1:6:10) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.90Cum Cost of 40mm HBG metal 438.70 1.00Cum 394.83
0.54Cum Cost of sand 182.64 1.00Cum 98.63
130.00Kg Cost of cement 2700.00 1000.00Kg 351.00
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
Add MBA 20% 70.11
Add TOT@4% 51.84
TOTAL 1347.95
11 RCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 20mm HBG metal 639.70 1.00Cum 588.52
0.46Cum Cost of sand 182.64 1.00Cum 84.01
330.00Kg Cost of cement 2700.00 1000.00Kg 891.00
1.00Cum Labour charges 620.28 1.00Cum 620.28
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
Add MBA 20% 124.06
TOTAL 2370.37
12 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
S.No Quantity Description of item Rate Per Amount
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for beams,Columns,Pedastals
1.00Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2370.37
1.00Cum Centring charges 689.00 1.00Cum 689.00
Add TOT@4% 122.37
TOTAL 3181.75
13 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for plinth beams&lintels
1.00Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2370.37
1.00Cum Centring charges 561.00 1.00Cum 561.00
Add TOT@4% 117.25
TOTAL 3048.63
14 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Sun shades
0.0375Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 88.89
1.00Rmt Centring charges 31.50 1.00Rmt 31.50
Add TOT@4% 4.82
TOTAL 125.20
15 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for T-Beams
1.00Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2370.37
1.00Cum Centring charges 813.00 1.00Cum 813.00
Add TOT@4% 127.33
TOTAL 3310.71
16 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Bed blocks
1.00Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2370.37
1.00Cum Centring charges 434.00 1.00Cum 434.00
Add TOT@4% 112.17
TOTAL 2916.55
17 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Hand rails
1.00Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2370.37
1.00Cum Centring charges 1189.00 1.00Cum 1189.00
Add TOT@4% 142.37
TOTAL 3701.75
18 Acco-proof plastering with CM(1:3) 12mm thick including all materials and all labour charges etc.complete
0.15Cum Cost of CM(1:3) 1501.44 1.00Cum 225.22
1.44Kg Cost of acco-proof compound 17.00 1.00Kg 24.48
10Sqm Labour charges 311.97 10Sqm 311.97
Add MBA 20% 62.39
TOTAL 624.06
19 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
S.No Quantity Description of item Rate Per Amount
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for roof slab of 120mm thickness including acco-proof plastering in CM(1:3)
12mm thick including all materials and all labour charges etc.complete for Roof slab
1.20Cum Cost of RCC(1:2:4) 2370.37 1.00Cum 2844.45
10Sqm Centring charges 730.00 10Sqm 730.00
10Sqm Acco proof plastering 624.06 10Sqm 624.06
Add TOT@4% 167.94
TOTAL 4366.45
20 Flooring with CC(1:6:10) 80mm thick,CC(1:2:4) 40mm thick and top finished with CM(1:3) 7mm thck
including all materials and all labour charges etc.complete
0.80Cum Cost of CC(1:6:10) 901.27 1.00Cum 721.02
0.40Cum Cost of CC(1:2:4) 2046.69 1.00Cum 818.67
0.07Cum Cost of CM(1:3) 1501.44 1.00Cum 105.10
Add TOT@4% 65.79
TOTAL 1710.59
Ist Floor
21 Cement Mortor (1:3) (1:5) (1:6)
1.00Cum Cost of sand 182.64 182.64 182.64
2700/1MT Cost of Cement 1296.00 777.60 648.00
1.00Cum Mixing charges 19.00 19.00 19.00
1.00Cum Lift charges 7.40 7.40 7.40
1.00Cum Scaffolding charges 35.00 35.00 35.00
Add MBA 20% 3.80 3.80 3.80
1543.84 1025.44 895.84
22 Cement Concrete(1:6:10) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.90Cum Cost of 40mm HBG metal 438.70 1.00Cum 394.83
0.54Cum Cost of sand 182.64 1.00Cum 98.63
130.00Kg Cost of cement 2700.00 1000.00Kg 351.00
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Lift charges 37.00 1.00Cum 37.00
Add MBA 20% 70.11
Add TOT@4% 53.32
TOTAL 1386.43
23 Cement Concrete(1:4:8) mix using 40mm HBG metal including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 40mm HBG metal 438.70 1.00Cum 403.60
0.46Cum Cost of sand 182.64 1.00Cum 84.01
166.00Kg Cost of cement 2700.00 1000.00Kg 448.20
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
1.00Cum Lift charges 37.00 1.00Cum 37.00
Add MBA 20% 70.11
Add TOT@4% 58.24
TOTAL 1514.21
24 Cement Concrete(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 20mm HBG metal 639.70 1.00Cum 588.52
S.No Quantity Description of item Rate Per Amount
0.46Cum Cost of sand 182.64 1.00Cum 84.01
330.00Kg Cost of cement 2700.00 1000.00Kg 891.00
1.00Cum Labour charges 350.54 1.00Cum 350.54
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
1.00Cum Lift charges 37.00 1.00Cum 37.00
Add MBA 20% 70.11
Add TOT@4% 83.35
TOTAL 2167.03
25 RCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 20mm HBG metal 639.70 1.00Cum 588.52
0.46Cum Cost of sand 182.64 1.00Cum 84.01
330.00Kg Cost of cement 2700.00 1000.00Kg 891.00
1.00Cum Labour charges 620.28 1.00Cum 620.28
1.00Cum Machine mixing charges 31.00 1.00Cum 31.00
1.00Cum Vibrating Charges 31.50 1.00Cum 31.50
1.00Cum Lift charges 37.00 1.00Cum 37.00
Add MBA 20% 124.06
TOTAL 2407.37
26 Brick Masonry in CM(1:6) using 2nd class Bricks including cost and conveyance of all materials
and all labour charges etc.
512Nos Cost of bricks 1462.88 1000Nos 748.99
0.20Cum Cost of CM(1:6) 895.84 1.00Cum 179.17
1.00Cum Labour charges 474.18 1.00Cum 474.18
1.00Cum Lift charges 30.50 1.00Cum 30.50
Add MBA 20% 94.84
Add TOT@4% 61.11
TOTAL 1588.79
27 Plastering with CM(1:5) 20mm thick including all materials and all labour charges etc.complete
0.21Cum Cost of CM(1:5) 1025.44 1.00Cum 215.34
10Sqm Labour charges 674.44 10Sqm 674.44
Add MBA 20% 134.89
Add TOT@4% 40.99
TOTAL 1065.66
28 Plastering with CM(1:5) 12mm thick including all materials and all labour charges etc.complete
0.15Cum Cost of CM(1:5) 1025.44 1.00Cum 153.82
10Sqm Labour charges 311.97 10Sqm 311.97
Add MBA 20% 62.39
Add TOT@4% 21.13
TOTAL 549.31
29 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for beams,Columns,Pedastals
1.00Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2407.37
1.00Cum Centring charges 689.00 1.00Cum 689.00
Add TOT@4% 123.85
TOTAL 3220.23
30 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for plinth beams&lintels
S.No Quantity Description of item Rate Per Amount
1.00Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2407.37
1.00Cum Centring charges 561.00 1.00Cum 561.00
Add TOT@4% 118.73
TOTAL 3087.11
31 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Sun shades
0.0375Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 90.28
1.00Rmt Centring charges 31.50 1.00Rmt 31.50
Add TOT@4% 4.87
TOTAL 126.65
32 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for T-Beams
1.00Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2407.37
1.00Cum Centring charges 813.00 1.00Cum 813.00
Add TOT@4% 128.81
TOTAL 3349.19
33 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Bed blocks
1.00Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2407.37
1.00Cum Centring charges 434.00 1.00Cum 434.00
Add TOT@4% 113.65
TOTAL 2955.03
34 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Hand rails
1.00Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2407.37
1.00Cum Centring charges 1189.00 1.00Cum 1189.00
Add TOT@4% 143.85
TOTAL 3740.23
35 Acco-proof plastering with CM(1:3) 12mm thick including all materials and all labour charges etc.complete
0.15Cum Cost of CM(1:3) 1543.84 1.00Cum 231.58
1.44Kg Cost of acco-proof compound 17.00 1.00Kg 24.48
10Sqm Labour charges 311.97 10Sqm 311.97
Add MBA 20% 62.39
TOTAL 630.42
36 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for roof slab of 120mm thickness including acco-proof plastering in CM(1:3)
12mm thick including all materials and all labour charges etc.complete for Roof slab
1.20Cum Cost of RCC(1:2:4) 2407.37 1.00Cum 2888.85
10Sqm Centring charges 730.00 10Sqm 730.00
10Sqm Acco proof plastering 630.42 10Sqm 630.42
Add TOT@4% 169.97
TOTAL 4419.24
37 Flooring with CC(1:6:10) 80mm thick,CC(1:2:4) 40mm thick and top finished with CM(1:3) 7mm thck
S.No Quantity Description of item Rate Per Amount
including all materials and all labour charges etc.complete
0.80Cum Cost of CC(1:6:10) 1333.10 1.00Cum 1066.48
0.40Cum Cost of CC(1:2:4) 2083.69 1.00Cum 833.47
0.07Cum Cost of CM(1:3) 1543.84 1.00Cum 108.07
Add TOT@4% 80.32
TOTAL 2088.35
38 Snowcem paint over a prime coat of white cement paint including cost and conveyance of all materials
and all labour charges etc.complete
1.34Kg Cost of White cement paint 13.00 1.00Kg 17.42
3.50Kg Cost of Snowcem paint 32.00 1.00Kg 112.00
10Sqm Labour charges 315.54 10Sqm 315.54
Add MBA 20% 63.11
Add TOT@4% 20.32
TOTAL 528.39
39 Cost,supply and fabrication charges of steel including cost of binding wire and all labour
charges etc.complete
1.00Kg Cost and supply of steel 28.00 1.00Kg 28.00
1.00Kg Fabrication charges of steel 4.00 1.00Kg 4.00
Add MBA 20% 0.80
Add TOT@4% 1.31
TOTAL 34.11
40 Supply and fixing of fully panelled best country wood door of size 1.20X2.55m including all fixtures and labour
charges etc.complete including 0.45m height ventilator
0.0614Cum Cost of Salwood for frames 22950.00 1.00Cum 1409.13
0.0759Cum Cost of Kamba planks for shutters 28000.00 1.00Cum 2125.20
3.06Sqm Labour charges 330.00 1Sqm 1009.80
2Nos MS Tower bolts 300mm long at top 36.00 1No 72.00
2Nos MS Tower bolts 150mm long at bottom 15.00 1No 30.00
6Nos MS 'Z' Hold fasts 18.00 1No 108.00
6Nos MS Butt hinges 150mm long 18.00 1No 108.00
1No MS Aldrop 300mm long 70.00 1No 70.00
1No MS Door handle 150mm long 19.00 1No 19.00
0.54Sqm MS Fly proof mesh 16X20 Gauge 103.00 1Sqm 55.62
3.79Kg 16mm MS bars to strengthen the ventilator 27.50 1.00Kg 104.15
Add for nails etc. 15.00 15.00
Add MBA 20% 201.96
Add TOT@4% 213.11
TOTAL 5540.97
41 Supply and fixing of fully panelled best country wood window of size 1.80X1.80m including all fixtures and labour
charges etc.complete including 0.45m height ventilator
0.090Cum Cost of Salwood for frames 22950.00 1.00Cum 2067.80
0.072Cum Cost of Kamba planks for shutters 28000.00 1.00Cum 2016.00
3.24Sqm Labour charges 419.00 1Sqm 1357.56
31.90Kg 16mm MS bars 27.50 1.00Kg 877.25
6Nos MS Tower bolts 150mm long 15.00 1No 90.00
4Nos MS 'Z' Hold fasts 18.00 1No 72.00
6Nos MS Butt hinges 150mm long 18.00 1No 108.00
0.81Sqm MS Fly proof mesh 16X20 Gauge 103.00 1Sqm 83.43
5.68Kg 16mm MS bars to strengthen the ventilator 27.50 1.00Kg 156.20
Add for nails etc. 15.00 15.00
Add MBA 20% 271.51
Add TOT@4% 284.59
TOTAL 7399.34
S.No Quantity Description of item Rate Per Amount
42 Painting with Synthetic enamel paint two coats over a primary coat of white lead including cost and conveyance
of all materials and all labour charges etc.complete
0.60Kg Cost of white lead 52.00 1.00Kg 31.20
1.00Kg Cost of whitening 20.00 1.00Kg 20.00
0.60Kg Linseed oil 15.00 1.00Kg 9.00
2.80Lts Synthetic enamil paint 90.00 1.00Lt 252.00
10Sqm Labour charges 259.73 10Sqm 259.73
Add MBA 20% 51.95
Add TOT@4% 24.96
TOTAL 648.83
Asst.Executive Engineer Dy.Executive Engineer
PR(spl),Ichapuram PR,Ichapuram
Executive Engineer
PR,Tekkali
Name of the work:-Buildings and amenities to the Degree college at Ichapuram,Est.Cost.Rs.20.00 lakhs
S.No Description of item Name of the quarry Initial Conveyance Seinorage Blasting Muncipal Deduct Total
MR CT Total Cost charges Border stacking
Allowance
1 Sand for filling Bahuda river 3.50 0.00 3.50 28.00 80.50 36.00 0.00 2.54 (-)7.40 139.64
2 Sand for Mortar Bahuda river 3.50 0.00 3.50 71.00 80.50 36.00 0.00 2.54 (-)7.40 182.64
3 40mm HBG metal-SS5 Rattakanna 0.50 0.00 0.50 269.00 80.90 45.00 53.00 3.00 (-)12.20 438.70
4 20mm HBG metal-SS5 Rattakanna 0.50 0.00 0.50 470.00 80.90 45.00 53.00 3.00 (-)12.20 639.70
5 Bricks Loddaputti 4.60 0.00 4.60 1250.00 168.30 45.00 0.00 5.48 (-)5.90 1462.88
6 Rough stone(OTG) for RR Rajapuram 0.50 0.00 0.50 92.50 80.90 45.00 0.00 3.00 (-)12.20 209.20
Masonry
1.Certified that the above leads are correct to the best of my knowledge
2.Certified that the above work spot lies within 12 Km from the Muncipal limits
Asst.Executive Engineer Dy.Executive Engineer Executive Engineer
PR(spl),Ichapuram PR,Ichapuram PR,Tekkali
LEAD STATEMENT
Lead in Kms
Name of the work:-Buildings and amenities to the Degree college at Ichapuram,
Est.Cost.Rs.20.00 lakhs
Grant:-College Education
Bahuda River
Orissa 229/5 Visakhapatnam
Ichapuram
1.20Km 227/2
Degree College
500m
Quarry
Rattakanna
Asst.Executive Engineer Deputy Exe.Engineer Executive Engineer
PR(spl),Ichapuram PR,Ichapuram PR,Tekkali
Quarry Chart
O.N.Submitted:-
Sir,
Sub:-Govt.Degree College,Ichapuram-Budget allocated for the year 2004-05 towards building works
for strengthening of existing physical infra structure and maintenance-Execution of work
through the Panchayat Raj Engineering Department-Approval requested-Regarding
Ref:-Progs.Rc.No.126/AII-1/2004-05 Dt.18.3.2005 of the Director of Collegiate Education,AP
It is submitted that an amount of Rs.20.00 lakhs was allocated for the year 2004-05
towards building works for strengthening of existing physical infra structure and maintenance of Govt.Degree
College at Ichapuram vide reference cited.
Further,in the above reference it self,it was instructed to take up the works with the above
amount through any Govt.Construction agencies like Panchayat Raj,R&B etc.with the approval of the
Dist.Collector.
In this connection,it is submitted that the Panchayat Raj department has already
executed buildings for the Degree College,Ichapuram for an amount of Rs.23.00 lakhs and at present another
work of worth Rs.10.00 lakhs is under progress.
An estimate prepared by the Panchayat Raj department with the details of works
proposed to be taken up is herewith put up for favour of perusal.
As such,necessary orders may be issued to take up the works with the above amount
through the Panchayat Raj Engineering Department.
PRINCIPAL DISTRICT COLLECTOR
GOVT.DEGREE COLLEGE SRIKAKULAM
ICHAPURAM
***********
// Put up for orders on ( C )//
Sub:-Govt.Degree College,Ichapuram-Budget allocated for the year 2004-05 towards building works
for strengthening of existing physical infra structure and maintenance-Execution of work
Ref:-Progs.Rc.No.126/AII-1/2004-05 Dt.18.3.2005 of the Director of Collegiate Education,AP
It is submitted that an amount of Rs.20.00 lakhs was allocated for the year 2004-05
towards building works for strengthening of existing physical infra structure and maintenance of Govt.Degree
Further,in the above reference it self,it was instructed to take up the works with the above
In this connection,it is submitted that the Panchayat Raj department has already
executed buildings for the Degree College,Ichapuram for an amount of Rs.23.00 lakhs and at present another
An estimate prepared by the Panchayat Raj department with the details of works
As such,necessary orders may be issued to take up the works with the above amount
***********
// Put up for orders on ( C )//
9.46m
W
W
W
Beams 0.3X0.6
0.23m thick
7.96m Brick wall
Beams 0.23X0.42

D W D
3.00m
Columns 0.23X0.3
A
Asst.Exe.Engineer Deputy.Exe.Engineer Exe.Engineer
PR,Ichapuram PR,Ichapuram PR,Tekkali
Plan of the Proposed Additional Accomodation for the Degree College
Varandah
PLAN OF THE ADMINISTRATIVE BLOCK
12.46m 4.2m 12.23m
W W W W W W W W
Beams 0.23X0.45
0.23m thick
7.96m Brick wall
Beams 0.23X0.3

D W W D D W W D
3.00m
Columns 0.23X0.3
Stair case Parapet wall
A
Asst.Exe.Engineer Deputy.Exe.Engineer Exe.Engineer
PR,Ichapuram PR,Ichapuram PR,Tekkali
12.46
4.2
12.23
-0.23
28.66
Plan of the Proposed Additional Accomodation for the Degree College
Varandah
PLAN OF THE 1st FLOOR

You might also like