ABSTRACT OF COST DATA SHEET 2009-10

Labour Charges
Total cost of Estimate
only casual
(In
(In Rs.)
Rs.)

Cost Data
Sheet No.

PARTICULARS

Unit
Material + Labour
(Both casual and
Regular)

Labour

11 kV 3-Ph SC line with 40 mtrs span on


9 mtr supports using Rabbit conductor

Km

206075

20225

11 kV 3-Ph SC line with 50 mtrs span on


9 mtr supports using Rabbit conductor

Km

182471

17280

11 kV 3-Ph SC line with 50 mtrs span on


8 mtr supports using Rabbit conductor

Km

161631

15449

11 kV 3-Ph SC line with 40 mtrs span on


9 mtr supports using coyote conductor

Km

367031

23295

11 kV 3 Ph. SC Line and 3 phase - 4 wire LT


line on 9.0 mtr supports with an average
span of 50mtrs using Rabbit Conductor for
H.T. and WEASEL for L.T Lines

Km

299786

30350

11 kV 3 Ph. SC Line and 3 phase - 4 wire LT


line on 9.0 mtr supports with an average
span of 40 mtrs using Rabbit Conductor for
H.T. and L.T Lines

Km

360271

36887

3 Ph. 4 wire LT line on 8 mtr supports with 60


mtrs span using Rabbit Conductor (IP Set
installations)

Km

122759

12798

3 Ph. 4 wire LT line on 8 mtr Supports with


40 mtrs span using Rabbit Conductor

Km

176988

17205

3 Ph. 4 wire LT line on 9 mtr Supports with


40 mtrs span using Rabbit Conductor

Km

200898

19530

10

3 Ph. 5 wire LT line on 9.0 mtr supports


Using Rabbit conductor with a span of
40mtrs (For Cities, Towns and Residential
layouts)

Km

236461

22119

11

3 Ph. 5 wire LT line with 8.0 mtr Supports


Using Rabbit conductor with a span of 50
mtrs

Km

192351

17266

12

3 Ph. 5 wire LT line with 8.0 mtr Supports


Using Weasel with a span of 40 mtrs

Km

128987

14097

13

L.T 3 Ph. 5 wire LT line with continuous earth


wire on 9.0 mtr supports using RABBIT for
phase, neutral and street light control and 8
SWG G.I. wire for continuous ground wire
with 40 mtrs span in vertical configuration

Km

235418

22229

14

11 kV 3 ph. SC line on 9 mtr supports using


rabbit conductor with 40 mtrs span with
vertical configuration in congested area

Km

233160

26055

Labour Charges
Total cost of Estimate
only casual
(In
(In Rs.)
Rs.)

Cost Data
Sheet No.

PARTICULARS

Unit
Material + Labour
(Both casual and
Regular)

Labour

a) 8 mtr RCC

Per unit

33318

3440

b) 9 mtr RCC

Nos

35880

3542

16

Providing 3 Pole Structure using 9 Mtrs RCC


Poles

Nos

30581

3370

17

Providing Metering to IP Set installations


using SMC Box

Nos

5673

300

18

Laying of 1km length of 11kV 3 core 95


Sq.mm XLPE UG Cable

Km

676207

113854

19

Laying of 1km length of 11kV 3 core 240


Sq.mm XLPE UG Cable

Km

978695

115262

20

Laying of 1km length of 11kV 3 core 400


Sq.mm XLPE UG Cable

Km

1344262

116669

21

a) Erection of 3-ph, 11 kV/433V Distribution


Transformer center using 8M Supports with
LA
i) 25 kVA

Per unit

89339

4523

ii) 63 kVA

Per unit

122813

4763

iii) 100 kVA

Per unit

164352

4996

iv) 250 kVA

Per unit

290742

5436

i) 25 kVA

Per unit

92188

4766

ii) 63 kVA

Per unit

125662

5006

iii) 100 kVA

Per unit

167107

5180

iv) 250 kVA

Per unit

293497

5620

Per unit

79256

3391

Per unit

112716

3622

a) With LT Distribution Box

Per unit

151458

3751

b) With LT Protection Kit

Per unit

141076

3751

15

Providing 2 pole structrue at the tapping


point using RCC pole

b) Erection of 3-ph, 11 kV/433V Distribution


Transformer center using 9mtr Supports with
LA

22

23

24

Erection of 25 kVA , 11kV/433V , Single pole


mounted transformer centre on 9mtr RCC
pole Square section
Erection of 63 kVA , 11kV/433V , Single pole
mounted transformer centre on pmtr RCC
pole Square section
Erection of 100 kVA , 11kV/433V , Single
pole mounted transformer centre on 9mtr
RCC pole Square section

Labour Charges
Total cost of Estimate
only casual
(In
(In Rs.)
Rs.)

Cost Data
Sheet No.

PARTICULARS

Unit
Material + Labour
(Both casual and
Regular)

Labour

25

Erection of 250 kVA, 11kV/433V, Single pole


mounted Distribution Transformer on 11mtrs
spun pole with 3 GOS system

Per unit

339449

6149

26

Providing Compact RMU 11kV class


VCB/SF6 Type (1 Incomer+2 Breakers+1
Outgoing)

Per unit

683302

7102

27

Providing Compact RMU 11kV class


VCB/SF6 Type (1 Incomer+1Breakers+1
Outgoing)

Per unit

400534

5552

28

Providing Compact RMU 11kV class


VCB/SF6 Type (1 OD)

Per unit

118948

2451

29

Providing Compact RMU 11kV class


VCB/SF6 Type (1VL)

Per unit

229908

2451

30

Running Single Circuit 11 kV 3 Phase Power


line on 9 mtr RCC supports with average
span of 30 mtrs using
3x95
Sqmm+1x95 Sqmm Aerial Bunched Cables
(ABC)

Km

73745

90209

31

Running Single Circuit 1.1 kV 3 Phase 5 wire


Power line on 9 mtr RCC supports with
average span of 40 mtrs using 3x70 +1x16
+1x50 Sqmm Aerial Bunched Cables (ABC)

Km

374667

42490

32

Erection of Compact Pre-fabricated


Packaged Sub-station 11kV / 433 V
a) With 500 kVA oil cooled transformer

Per unit

159163

7056

b) With 750 kVA oil cooled transformer

Per unit

1611072

7056

c) With 990 kVA oil cooled transformer

Per unit

1961610

7056

d) With 500 kVA dry type transformer

Per unit

1997538

7056

c) With 750 kVA dry type transformer

Per unit

2294518

7056

c) With 990 kVA dry type transformer

Per unit

2590559

7056

Labour Charges
Total cost of Estimate
only casual
(In
(In Rs.)
Rs.)

Cost Data
Sheet No.

PARTICULARS

33

providing Electronic Trivector Meters with


associated CT's Metering Box etc., on LT
side of Distribution Transformer Center

Unit

i) 15/25 kVA (with meter)


a)

Labour

9466

504

5221

228

9148

504

4903

228

8923

504

4678

228

8923

504

4678

228

8923

504

4678

228

Per unit
ii)5/25 kVA (without meter)
i) 50/63 kVA (with meter)

b)

Per unit
ii) 50/63 kVA (without meter)
i) 100 kVA (with meter)

c)

Per unit
ii) 100 kVA (without meter)
i) 250 kVA (with meter)

d)

Per unit
ii)250 kVA (without meter)
i) 500 kVA (with meter)

e)

Per unit
ii) 500 kVA (without meter)

34

Material + Labour
(Both casual and
Regular)

providing LT Capacitors to the Distribution


Transformers
a) 3 kVAr

Per unit

868

193

b) 9 kVAr

Per unit

1274

193

c) 18 kVAr

Per unit

2110

227

d) 27 kVAr

Per unit

3174

266

e) 54 kVAr

Per unit

5311

278