Professional Documents
Culture Documents
Winter Status
Brian Molefe
Acting Chief Executive
17 June 2015
Content
Introduction
Half-year performance
Winter Outlook
Build Programme
Conclusion
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
Overview
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
Benefits from the Build Programme contribute to the grid: 100 MW from Sere, and
up to 800 MW from Medupi during peak periods
100%
90%
In the recent
months, Eskom
had to implement
regular load
shedding due to
the unavailability
of some of the
generation units
80%
Not
Supplied
60%
50%
40%
Eskom supplied
on average 96%
of the demand
during the period
30%
20%
10%
Apr-15
Mar-15
Feb-15
Jan-15
Dec-14
Nov-14
Oct-14
Sep-14
Aug-14
Jul-14
Jun-14
May-14
0%
Apr-14
Demand
70%
Feb-15
Sun
Mon
Tue
Wed
Thu
1
Fri
2
Sat
3
Sun
1
Mon
2
Tue
3
Wed
*4
Thu
*5
Fri
6
Sat
7
10
10
* 11
12
13
14
11
12
13
14
15
16
17
* 15
16
17
18
19
20
21
18
19
20
21
22
23
24
22
23
24
25
26
27
28
25
* 26
* 27
28
29
30
31
Mar-15
Apr-15
Sun
1
Mon
2
Tue
3
Wed
4
Thu
5
Fri
6
Sat
7
Sun
Mon
Tue
Wed
1
Thu
2
Fri
3
Sat
4
10
11
12
13
14
10
11
15
16
17
18
19
20
21
12
13
* 14
* 15
* 16
17
18
22
23
24
25
26
27
28
19
20
21
22
* 23
24
25
29
30
31
26
27
28
29
30
May-15
Sun
Mon
Tue
Wed
Thu
Fri
1
Sat
2
*6
*7
*9
10
* 11
12
13
* 14
15
16
17
24
18
25
19
26
20
27
21
28
22
29
23
30
No load shedding
Stage 3
Stage 2
* stage change
Jan-15
Feb-15
Sun
Mon
Tue
Wed
Thu
1
Fri
2
Sat
3
Sun
1
Mon
2
Tue
3
Wed
*4
Thu
*5
Fri
6
Sat
7
10
10
* 11
12
13
14
11
12
13
14
15
16
17
* 15
16
17
18
19
20
21
18
19
20
21
22
23
24
22
23
24
25
26
27
28
25
* 26
* 27
28
29
30
31
Mar-15
Apr-15
Sun
1
Mon
2
Tue
3
Wed
4
Thu
5
Fri
6
Sat
7
Sun
Mon
Tue
Wed
1
Thu
2
Fri
3
Sat
4
10
11
12
13
14
10
11
15
16
17
18
19
20
21
12
13
* 14
* 15
* 16
17
18
22
23
24
25
26
27
28
19
20
21
22
* 23
24
25
29
30
31
26
27
28
29
30
Key insights
May-15
Sun
Mon
Tue
Wed
Thu
Fri
1
Sat
2
*6
*7
*9
10
* 11
12
13
* 14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
Winter outlook:
While the system will be tight, Eskom will only
implement load shedding as a last resort
Winter 2015 is likely to be colder than last year, with a higher expected
demand in electricity during the peak periods.
We anticipate to supply 100% of electricity most days and 96% during peak
periods from 6am to 10am and 5pm to 10pm.
Even during the cold front that hit from Wednesday, 3 June, Eskom
implemented only 5 hours of load shedding on Sunday, 7 June. This after 10
consecutive days of no load shedding.
The recent load shedding from Monday, 8 June 2015 to Friday, 12 June 2015
was the result of an increase in demand and an increase in unplanned
breakdowns
Localised power outages in urban areas and illegal connections generally
increase during winter due to increased levels of customer demand and hence
cause greater stress on the system.
11
12
Increase in
demand
from 5pm to 10 pm
Increase in
demand
from 6am to 10am
13
40
36.5 GW
35
34 GW
35GW
+ 1 500 MW
operating
reserves
20
15
Maximum demand
36GW instantaneous
25
Maximum demand
33GW instantaneous
32.5GW
30
Gw
Summer Demand
Winter Demand
10
5
0
Capacity
Philosophy maintenance
Safety maintenance
Statutory maintenance
Maintenance
Unplanned
maintenance
Risk maintenance
Breakdowns (Total and
partial load losses)
15 of a total of 18 maintenance outages (83%) are on power plants that are classified
as Risk 1/Risk 2/Risk 3
13 of a total of 18 maintenance outages (80%) is also philosophy maintenance
This provides coal supplies to all six units via mobile equipment and temporary coal
stock piles.
A contract was awarded on 2 March 2015 for the interim solution which replaces
the mobile equipment with conveyor belts running from the permanent stockpiles to
ensure greater efficiency in the coal handling process.
Design consultants have been appointed and construction is expected to begin early
January 2016, once a construction contractor has been appointed.
16
The incident investigation has been completed and the primary cause
was noted as a build-up of unburnt fuel within the boiler, which ignited
in an uncontrolled manner
A process is under way to address all the recommendations from the
report, and key learnings have been shared with other power stations.
Negotiations have started with a boiler supplier and once technical,
financial and commercial issues have been agreed, repair work
should begin in July 2015.
17
Stage
Old schedules
New schedules
Stage 1
1 000 MW
1 000 MW
Stage 2
2 000 MW
2 000 MW
Stage 3
4 000 MW
3 000 MW
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
xx
MW added to
the network
Post MYPD3
Commissioned in
early Feb 2015
Additional 100MW
added to the
network
100
800
Feb 2015
Sere Wind Farm
Mar 2015
Majuba
Recovery
1200
Unit 4 to be
commissioned Apr
2016
333
Aug 2015
Medupi Unit 6
Jan 2016
Ingula
Unit 3
333
Unit 3 to be
commissioned
Jan 2016
Mar 2016
Ingula Unit 4
May 2016
Ingula
Unit 2
333
Unit 2 to be
commissioned
May 2016
Unit 1 to be
commissioned
Aug 2016
Kusile 1 will be
commercially
operating Aug
2017
333
800
Jul 2016
Ingula Unit 1
Aug 2017
Kusile 1
2015/16
1 466 MW
Medupi x1 unit
Ingula x2 units
Total MW
5 532
Sep 2017
Medupi 5
2019/2020
Duvha 3
Recovery
800
500
Medupi 5
commercial
operation date is
Sep 2017
Duvha 3 will be
fully recovered in
2019/2020
This project falls
out of MYPD3
window
21
Eskom issues Power Alert system bulletins and holds a Quarterly system status media
briefing to provide regular updates
2. Switch off all geysers and pool pumps (all day until
9pm), and invest in a timer
3. Switch off all non-essential lighting and appliances
4. Respond to Power Alert messages by switching off all
appliances that are not being used
23
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
Thank you