PROJECT: Proposed Chiller Plant System Replacement for International Centre at 17 Ngo
Quyen Street, Hoan Kiem District, Hanoi, Vietnam
Site meeting
Minutes of meeting No. 201
Date : 1422 April 2015
Time : 39:3000 pam
Venue : International Centres Management Office
Present:
Mr. Lim Sin On
Ms. Le Linh Lan
Mr. Tran The Hung

- Senior Manager (Engineering)HQ )


- Marketing & Property Manager
)
- Chief Engineer
)

Keppel Land
International Centre
International Centre-

Mr. Mok Teck Heng


Mr. Le Trung Kien

- Associate
- Project Manager

)
)

Tham&Wong ME
Tham&Wong ME

Mr. Tran Duc Trung


- Director
Mr. Nguyen Viet Dung - Vice Director
Corp-.
Mr. Huynh Van An
- Project Manager
Corp.-

)
)

TSC M&E Engineering Corp.


TSC M&E Engineering

TSC M&E Engineering

Tham&Wong ME

Absent with Apologies


Mr. Mok Teck Heng
- Associate
Abbreviations:
Keppel Land
International Centre
Tham&Wong ME
TSC M&E
Main Switch Board
Building Management System
NO.

- KL
- IC
- TW
- TSC
- MSB
- BMS

MATTERS DISCUSSED

1.

TSW and IC was informeded TSC that the Engineer


Instruction EI01 & EI02 had been issued to TSC.
TSC confirmed that they had received and will reply to all
parties on 16 April 2015
the extension time claim offor 5 days extension from
TSCschedule caused stopping by for the traffic police will
be requiredrequired the relevant governmentauthoritys
documentacknowledgement. If not, it should not be
consideraccepted.

2.

For the faulty of broken down issue of compressor labelNo.22A of chiller No. 11, TSC was W & IC required by IC

TARGET
DATE
16 Apr
2015ASAP

ACTION

INFO27 Apr
2015

TSC
TW

TSC

Page 1 of 3

THAM & WONG VN Co., Ltd

NO.

MATTERS DISCUSSED

TARGET
DATE

and TWTSC to check all the repairing effect which may


have on the working schedulewith supplier to replace and
update on the schedule of replacement.
TSC should be ready for any necessary action Based on the
current working schedule submitted by TSC, they confirms
that they are able to finish the work before 28.05.2015 and
do not need to extend the Bank guarantee. In case they
need to extend, they will need around one week to finish
the procedure forto extensiond bank guarantee with same
condition. TSC is required to get the written confirmation
from the bank on the above for project.

ACTION
IC

TSC informeds that they have been working with Trane


Vietnam on this matter. They required time for ordering
and delivery of the new compressor will be is around 1
week (by air freightplane). The replacement of this
compressor shall not affect to finishing schedule of project.
TSC was requested to work with Trane Vietnam for the
official letter in English version about issue on the faulty
compressor and also the proposed solution and target
schedule to finish the replacement.
TSC request to prepare the method of statement for
replacement of this compressor.
TSC was reminded to get prepared for the bank guarantee
extension if needed.
TW & IC inform TSC againwas highlighted that Iincase
TSC need to extend bank guarantee and TSC may not able
to get the bank guarantee before the deadline, TW & IC
will hold back the 10% of contract from the TSCs
Progress Claim and will release when the work is
completed or the bank guarantee is extended, TSC
agreesClient will hold back 10% of contract value if we
foreseepredict any issue affectaffecting to finishingthe
completion date..
3.

TSC requested IC again to be release the Bbank


Gguarantee for Advance Ppayment Bbond.
IC agrees but due to internal office matter, IC will try to
feedback to TSC soon.

INFO

4.

TSC requested to submitted variation order on the addition 203 Apr 2015
and omission of the items from the contract. to TW and
then

TSC
TW
IC
TSCTW

Page 2 of 3

THAM & WONG VN Co., Ltd

NO.

MATTERS DISCUSSED

TARGET
DATE

ACTION

1627 Apr
2015

TSC

27 Apr 2015

TSC

TW will to review and issue the Engineer Instruction for


the above. on tomorrow.
5.

Mr. Lim Sin OnKL requested TSC and Trane to correct and
tidy the From the log sheet done by TSC, IC & TW request
TSC to contact with Trane Vietnam to check on the
compressor No.2 of first new Chiller and also the startingup procedure and check list for both Cchillers No. 1 &
Chiller No.2.
TSC will arrange the Trane to visit the site on 16 April
2015 and together with IC & TW will check on these
matters.

6.

TW & IC request TSC again to work with Trane Vietnam


to get official letter from Trane Vietnam (in English) about
issue on broken downthe faulty compressor and also the
proposed solution and target schedule to finish theing of
ordering, replacement.
TSC request to prepare the method of statement for
replacement of this compressor.

7.

TSC had rectified the defect list commented by IC and TW.


TW requested TSC to prepare a defect list and sign off by
IC and TW.

1723 Apr
2015

TSC

8.

TSC was reminded to clean-up the unused material,


garbage on both lower roof and upper roof, to tidy-up the
working site.

ASAP

TSC

9.

TSC request to submit the working schedule on next public


holidays to IC.

17 Apr 2015

TSC

Meeting was ended at 511:00pam. The next meeting will be held on 21529 April April May 2015 at
3:030pm at International Centres Management Office.