Professional Documents
Culture Documents
13
risk identification;
risk analysis; and
risk responses
Rao Tummala and Y.H. Leung,
[17] developed a methodology for risk
management that looks at risk identification, measurement, assessment,
evaluation, risk control and monitoring. Their methodology was developed for managing the cost risk of an
EHV transmission line project.
T.M. Williams [19] examined various project risk management
research. He describes various risk
identification and analysis tools being
used by researchers and practitioners
and the management structures and
procedures needed to manage risk.
Project Plan
et
c.
pa
ck
ag
e
pa
ck
ag
e
W
or
k
W
or
k
W
or
k
D
wo o a
n rk ny
as eed pa of t
se a ck h
ssm ri ag e
en sk es
t?
pa
ck
ag
e
Yes
Risk Assessment
Identify Risks
Assess Risks
Determine Consequence
scenarios
Determine Control Measure
No
Implement
e
th l
Is idua
s
re risk ble?
ra
le
to
No
Review the
work package
plan
Yes
Figure 3Risk Management Flow Chart
duration and which activities are critical in
determining that duration. Many authors
have presented the distribution of time
duration of activities as classical Beta distribution [10]. J. Berny, [1] proposed his own
distributions for practical simulations. P.K.
Dey used Monte Carlo simulation for ana-
Definition
Explanation
Equal importance
3
5
7
Moderate importance
Essential or strong importance
Demonstrated importance
Extreme importance
2, 4, 6, 8
Intermediate values
Technical
Risk
Financial
& Economic
Risk
3
1
1/2
1/4
1/3
Technical Risk
1
Financial and Economic Risk 1/3
Organizational risk
1/4
Acts of God Risk
1/5
Clearance Risk
1/5
Consistency Ratio: 0.042. acceptable
project risk analysis. The AHP allows the
active participation of decision-makers in
reaching agreement and it gives managers
a rational basis on which to make decisions.
Formulating the decision problem in
the form of a hierarchical structure is the
first step. In a typical hierarchy, the top
level reflects the overall objective or focus
of the decision problem. The elements
affecting the decision are represented in
intermediate levels. The lowest level comprises the decision options. Once the hier-
Organizational
Risk
Acts of
God Risk
Clearance
Risk
Likelihood
4
2
1
1/2
1/3
5
4
2
1
1/2
5
3
3
2
1
0.479
0.228
0.146
0.064
0.083
archy has been constructed, the decisionmaker begins the prioritization procedure
to determine the relative importance of the
elements in each level of the hierarchy.
The elements in each level are compared
pair wise with respect to their importance
in making the decision that is under consideration. The verbal scale used in an
AHP enables the decision-maker to incorporate subjectivity, experience, and knowledge in an intuitive and natural way. After
the comparison matrices have been creat-
Likelihood
Sub-factors
Technical Risk
0.479
Scope change
Technology selection
Implementation methodology
Equipment risk
Materials risk
Engineering and design change
Likelihood
LP
GP
0.36
0.172
0.124
0.059
0.13
0.062
0.073
0.035
0.08
0.038
0.233
0.112
Financial
& Economical
Risk
0.228
Inflation risk
Fund risk
Changes in local law
Changes in Govt. policy
Improper estimate
0.152
0.383
0.105
0.105
0.255
0.035
0.087
0.024
0.024
0.058
Organizational
Risk
0.146
0.106
0.015
0.283
0.448
0.163
0.041
0.065
0.024
Calamity Normal
Calamity abnormal
Environmental clearance
Land acquisition
Explosive clearance
Other clearances
0.44
0.56
0.026
0.461
0.133
0.142
0.028
0.036
0.022
0.038
0.011
0.012
Acts of God
0.064
Clearance risk
0.083
LPLocal percentage
GPGlobal percentage
16
River X-ing
Pipeline
Laying
Station
Construction
Other Work
Packages
Scope change
technology selection
implementation methodology
equipment risk
materials
eng.. and design change
LP
0.17
0.29
0.47
0.33
0.17
0.37
GP
0.029
0.017
0.029
0.012
0.007
0.041
LP
0.39
0.23
0.26
0.21
0.35
0.33
GP
0.067
0.014
0.016
0.007
0.013
0.037
LP
0.31
0.11
0.17
0.28
0.26
0.13
GP
0.053
0.007
0.011
0.010
0.010
0.015
LP
0.13
0.37
0.1
0.18
0.22
0.17
GP
0.022
0.022
0.006
0.006
0.008
0.019
Inflation
Fund
local law
policy
estimate
0.25
0.25
0.18
0.25
0.43
0.009
0.022
0.004
0.006
0.025
0.25
0.25
0.18
0.25
0.43
0.009
0.022
0.004
0.006
0.025
0.25
0.25
0.19
0.25
0.17
0.009
0.022
0.005
0.006
0.010
0.25
0.25
0.25
0.25
0.08
0.009
0.022
0.006
0.006
0.005
0.33
0.37
0.21
0.49
0.005
0.015
0.014
0.012
0.3
0.33
0.29
0.13
0.005
0.014
0.019
0.003
0.27
0.22
0.4
0.15
0.004
0.009
0.026
0.004
0.1
0.08
0.1
0.23
0.002
0.003
0.007
0.005
Calamity Normal
Calamity abnormal
0.41
0.32
0.012
0.011
0.35
0.47
0.010
0.017
0.14
0.09
0.004
0.003
0.1
0.12
0.003
0.004
Environmental
Land acquisition
Explosive clearance
Other clearance
0.25
0.13
0.25
0.25
0.005
0.005
0.003
0.003
0.25
0.51
0.28
0.25
0.005
0.020
0.003
0.003
0.25
0.3
0.36
0.15
0.005
0.011
0.004
0.002
0.25
0.06
0.11
0.35
0.005
0.002
0.001
0.004
0.286
0.317
0.229
0.169
Rank
Methodology
The methodology adopted for risk
management in this article is explained in
Change in policy
Capability of
owners project
group
Consultants
capability
Implementation
methodology
Fund risk
Improper estimate
Materials risk
High
S
e
v
e
r
i
t
y
Medium
Low
Land acquisition
Technology selection
Engineering and Design change
Contractors capability
Vendors capability
Calamity abnormal
Scope change
Inflation risk
Environmental
clearance
CCE clearance
Other clearances
Low
Medium
High
Probability
Selecting the best option through sta- India. The pipeline has a length of 1300
km. Its diameter is 22 inches for a length of
tistical analysis.
1112 km, 18-inches for a length of 218 km,
and 10.75 inches for a length of 123-km (a
branch line). The pipeline is designed for 5
million metric tons per annum (MMTPA)
Application
The above steps will be explained throughput. The project also consists of the
through the case of a cross-country petrole- construction of three pump stations, one
um pipeline project in the western part of pumping-cum-delivery station, two scraper
Scope change
Engineering and design change
Technology selection
Land acquisition
Contractors capability
Vendors Capability
Calamity abnormal
Implementation methodology
Fund availability
Improper estimate
Materials risk
18
Probability
0.172
0.112
0.059
0.038
0.041
0.065
0.036
0.062
0.087
0.058
0.038
Severity
Time
over-run
(in months)
US $)
8
5
6
4
6
8
12
3
2
2
3
Cost
Over-run
(in Millions)
90
30
20
0
30
30
90
0
0
0
0
stations, four delivery stations, and two terminal stations. The project cost was estimated as 600 million in US dollars. A
detailed description of the project is available in Deys Planning for Project Control
Through Risk Analysis, A Case of a
Petroleum Pipeline Laying Project [5].
Figure 3 shows a flow chart for risk
management. A risk management group
was formed to do a risk analysis study for
the project in this article. The group consisted of one member each from mechanical, electrical, civil, tele-communication,
instrumentation, finance, and materials of
project function. They were entrusted with
collecting data, analyzing, interpreting and
preparing recommendations with active
interactions with the project groups.
river crossing;
Table 6The Cost Data (Million US $) for Each Package Against Various Responses
Responses
Pipeline
laying
pipeline laying;
stations construction; and
telecommunication and SCADA
system
scope change;
technology selection;
implementation methodology
selection;
equipment risk;
12
Building
& colony
construction
3
1.5
1.5
22
16
10
River
crossing
Station
TelecommunConstruction ication & CP
11
56
32
32
140
10
10
Acts of God
inflation risk;
fund risk;
changes of local law;
changes in government policy; and
improper estimation
Organizational Risk
environmental clearance;
land acquisition;
clearance from chief controller of
explosives (CCE); and
other clearance from government
authorities
19
Cost
Probability
(million of failure **
US$)
Effect
Time
(months)
Expected Value
Time
Cost
(months) (million
US$)
3.8
6.97
0.32
0.64
1.9
3.5
0.64
1.3
0.1
0.1
Cost
(million
US$)
22
4
22
4
2
Do nothing
0
0.317
12
Carrying out detailed survey
12
0.158
2
Using superior technology
3
0.158
12
Engaging expert project team
22
0.317
2
Taking all responses as
56
0.05
2
indicated in table
*EMV = 0 + 3.8 X 7.5 + 6.97 = 35.5
(Return on investment is 7.5 million US $ per month i.e. 15% of 600 million US $ per annum)
Do nothing
Carrying out detailed
survey and using
superior technology
Engaging expert
project team
Taking all responses
as indicated in table
20
Probability
of failure
Effect
Time
(months)
0
12
0.286
0.143
15
15
16
0.286
20
2.3
5.72
39
32
0.05
0.1
0.4
33.15
Cost
(million
US$)
40
40
Expected Value
Time
Cost
(months) (million
US$)
4.3
11.44
2.15
5.72
EMV*
(million US$)
43.7
33.85
EMV*
(million US$)
35.5
15
21
28
56.9
Do nothing
Carrying out detailed
survey and using
superior technology
Engaging expert
project team
Taking all responses
as indicated in table
Probability
of failure
Effect
Time
(months)
0
9
0.229
0.115
12
0.6
10
0.229
0.4
0.46
0.92
14.5
32
0.05
0.1
0.2
33
Cost
(million
US$)
24
12
Expected Value
Time
Cost
(months) (million
US$)
2.75
5.5
0.7
1.32
EMV*
(million US$)
26.2
15.06
Do nothing
Carrying out detailed
survey and using
superior technology
Engaging expert
project team
Taking all responses
as indicated in table
Probability
of failure
Effect
Time
(months)
0
4.5
0.169
0.085
2
2
Cost
(million
US$)
2
2
0.169
0.5
0.085
0.17
3.8
0.05
0.5
0.025
0.05
10.25
10
Expected Value
Time
Cost
(months) (million
US$)
0.34
0.34
0.17
0.17
EMV*
(million US$)
3
5
21
Risk Mapping
All the factors were organized as per
their probability and severity (effect on
time and cost) characteristics as indicated
in table 4. The factor scope change has
been identified as the most vulnerable for
the project under study as it has a high
probability of occurrence, as well as high
severity. If there is a change in scope of any
of the work packages, there will be consid-
Failure
Do nothing
Detailed survey
-12
Time
(Months)
Cost
(Million US $)
12
22
12
22
P = 0.317
No failure
P = 0.683
Failure
P = 0.158
No failure
P = 0.842
Failure
Superior technology
-3
Expert project team
-22
P = 0.158
No failure
P = 0.842
Failure
P = 0.317
No failure
P = 0.683
No failure
All response
P = 0.05
No failure
-56
P = 0.95
Detailed survey
and superior
technology
-12
Expert project team
-16
All response
-32
are rated as having medium probability, as Let X be a random variable. The rth
adequate planning for the project under moment of X about zero is defined by
study prompts the executives to perceive
Failure
Do nothing
P = 0.286
No failure
P = 0.714
Failure
P = 0.143
No failure
Time
(Months)
Cost
(Million US $)
15
40
15
40
20
P = 0.857
Failure
P = 0.246
No failure
P = 0.714
Failure
P = 0.05
No failure
P = 0.95
r = ( r) =
r f(x)dx
if X is continuous
(equation 2)
(equation 3)
r = ( )r =
(x- )r f(x)dx
if X is continuous
(equation 4)
23
Failure
Do nothing
Detailed survey
and superior
technology
-9
Expert project team
-12
All response
-32
P = 0.229
No failure
P = 0.771
Failure
P = 0.115
No failure
Time
(Months)
Cost
(Million US $)
12
24
12
P = 0.885
Failure
P = 0.229
No failure
P = 0.771
Failure
P = 0.05
No failure
P = 0.95
[t - ] / =
(equation 5)
Xt = increase in duration of time of
project/ work package
= Expected increase in project duration, 4.88 months
= Standard deviation of duration distribution, 2.616
Z = Corresponding value from normal
distribution chart against probability
value (90 percent confidence level in
this case), 1.29.
2 = E(X - )2
Detailed survey
and superior
technology
-4.5
Expert project team
-3
All response
-10
P = 0.813
Failure
P = 0.085
No failure
P = 0.915
Failure
P = 0.169
No failure
P = 0.813
Failure
to avoid;
to reduce;
to transfer; and
to absorb.
0.5
0.5
P = 0.05
No failure
P = 0.95
Risk Responses
Risk analysis results lead one to derive
a few effective risk responses in line with
the following principles:
his study suggests a project management model with the application of risk management principles. A decision support system
(DSS) has been developed in an analytic
hierarchy process (AHP) and decision tree
analysis (DTA) framework. This helps the
management of projects and helps in making objective decisions. The DSS identifies
risk factors that are inherent in the project,
analyzes their effect on various activities,
and derives responses in line with project
objectives, the organizations policy, and
business opportunities.
Risk is by nature subjective. However,
AHP allows one to objectively analyze the
effect of risk on a project by determining
the probability of its occurrences. The
probability and severity of each risk factor
are determined through the active involvement of field experienced persons in an
interactive environment. The information
is collected in a very structured format in
line with AHP requirements and processed
using available computer programs.
Additionally, sensitivity utility of AHP provides an opportunity to the risk management group to observe the nature of model
outcomes in different alternative decision
situations. DTA helps in selecting from
among various decision alternatives. Risk
management using a combined AHP and
DTA approach provides the following benefits.
do nothing;
carrying out detailed survey (or additional survey work);
Figures 6, 7, 8, and 9 show the decision trees for the work packages (pipeline
laying, pipe laying across river, station construction, and telecommunication and
cathodic protection) of the project under
study. The probability and severity (time
and cost) for each decision alternative are
derived from the risk analysis study of each
package and the expert opinions gained
through brainstorming.
The expected money values (EMV)
are then calculated for each alternative
decision for all the packages. Tables 7-10
show the calculations of decision tree
approach of risk management. Table 11
shows the decisions emerge from the decision tree approach of risk management.
26
References
1. Benry, J.A. New Distribution Function
for Risk Analysis. Journal of the
Operational Research Society, 40
(1989): 1121-1127.
2. Canavos, G.C. Applied Probability
and Statistical Methods, Little,
Brown and Company, 1984.
3. Chapman C.B. and D.F. Cooper. Risk
Analysis: Testing Some Prejudices.
European Journal of Operational
Research, 14 (1983) 238-247.
4. Cooper, D.F., D.H. MacDonald, and
C.B. Chapman. Risk Analysis of a
Construction
Cost
Estimate.
International Journal of Project
Management 3, no. 3 (1985) 141-149.
5. Dey, P.K. M.T. Tabucanon and S.O.
Ogunlana. Planning for Project
Control through Risk Analysis; A Case
of Petroleum Pipeline Laying Project.
International Journal of Project
Management 12, no. 1, (1994) 23-33.
6. Dey, P.K. Symbiosis of Organizational
Re-engineering and Risk Management
for Effective Implementation of
Projects, Doctoral thesis, Jadavpur
University, India, 1997.
7. Dey, P.K. Process Re-engineering for
Effective Implementation of Projects.
International Journal of Project
Management, 17, no. 3 (1999) 147159.
8. Dey, P.K. Project Time Risk Analysis
Through
Simulation.
Cost
Engineering 43, no. 7 (July 2001): 2432.
9. Dilworth, J.B. Operations Management: Providing Value in Goods and
Services, The Dryden Press, 2000.
10. Farnum N.R., and L.W. Stanton. Some
Results Concerning the Estimation of
Beta Distribution Parameters in PERT.
Journal of the Operational Research
Society 38 no. 3 (1987): 287-290.
11. Forman, E.H. and T.L. Saaty. Expert
Choice Expert Choice, Pittsburgh, PA
1983.
12. Halman, J.I.M. and J.A. Keizer. Risk
Management in Product Innovation
Projects. International Journal of
Project
and
Business
Risk
Management 2, no. 2 (1998).
13. Kangari, R. and L.S. Riggs.
Construction Risk Assessment by
Linguistics. IEEE Trans. Eng.
Manag. 36 no. 2 (1989): 126-131.
14. Mustafa, M.A. and J.F. Al-Bahar.
Project Risk Assessment Using the
Cost Engineering Vol. 44/No. 3 MARCH 2002
15.
16.
17.
18.
19.
20.