Professional Documents
Culture Documents
Critical Chain
Critical Chain
1) If safety time has been removed and it has been reduced by 50% of the
scheduled then the different safety time for tasks is as follows:
a. 24 days
b. 11 days
c. 8 days
d. 4 days
e. 9 days
f. 9 days
This would total to 65 days safety time. So the project buffer should be
somewhere around half which would mean approximately 33.5 days.
2) We square the duration of the tasks so it would be (24 2+112+82+42+92+92)
and the answer would be a project buffer of about 30.6 days.
3) I feel that Paul would be the constraint here because it jumps straight from
him to peter and there is no buffer.
4)
Using the same SSQ method the duration would be 61.6 days
PROBLEM #2
1)