Professional Documents
Culture Documents
1
ADVANTAGES OF USING CPA
DEPENDENCIES (1)
2
DEPENDENCIES (2)
Start to start
Foundation
Excavation
DEPENDENCIES (3)
Finish to finish
Commissioning Commissioning
section 1 section 2
3
DEPENDENCIES (4)
Start to finish
CONSTRAINTS TO BE CONSIDERED
§ Finish on constraint.
§ Finish no earlier than constraint.
4
TIME FRAMES
TERMONOLOGY
5
DUMMY ACTIVITIES ON ACTIVITY ON NODE
A C
Start Finish
B D
6
THE WORK BREAKDOWN STRUCTURE (3)
House
Design
7
PREPARE THE PROJECT TIME SCHEDULE
USING CPA
8
DETERMINE THE ACTIVITY DURATION
A Wake up in the
morning
B Have a shower
C Make coffee
D Make breakfast
F Get dressed
G Leave for
varsity
9
CALCULATE THE RESOURCE REQUIRMENTS (1)
§ R e s o u rc e s re l a t e t o m a t e r i a l , m a n p o w e r,
equipment etc. and initially we need to assume
that we have unlimited resources available for the
project.
§ We do however need to find out what the resource
availability is to determine the realistic duration for
an activity e.g. if 5 bricklayers are available we
can reduce the duration from 100 days to 20 days.
10
EXAMPLE OF AN ACTIVITY LIST
B Have a shower 5 1
C Make coffee 3 1
D Make breakfast 2 1
F Get dressed 6 1
G Leave for varsity 5 1
11
DETERMINE THE PROJECT LOGIC (2)
12
CONSTRUCT THE LOGIC DIAGRAM (1)
ACTIVITY BLOCK
Description Float
13
CONSTRUCT THE LOGIC DIAGRAM (2)
B F
A G
C
D E
B F
5 5 10 10 6 16
A G
C 18 5 23
0 5 5 5 3 8
D E
5 2 7 8 10 18
14
DETERMINE THE PROJECT DURATION - THE
BACKWARD PASS (2)
7 12 12 18
B F
5 5 10 10 6 16
18 23
0 5 5 8 G
A C 18 5 23
0 5 5 5 3 8
6 8 8 18
D E
5 2 7 8 10 18
7 12 12 18
2 B 2 2 F 2
5 5 10 10 6 16
18 23
0 5 5 8 0 G 0
0 A 0 0 C 0 18 5 23
0 5 5 5 3 8
6 8 8 18
1 D 1 0 E 0
5 2 7 8 10 18
15
DETERMINE THE PROJECT DURATION - THE
CRITICAL PATH (4)
A
B
C
D
E
F
G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
16
VERIFY THE PROJECT DURATION
A 1 1 1 1 1
B 1 1 1 1 1
C 1 1 1
D 1 1
E 1 1 1 1 1 1 1 1 1 1
F 1 1 1 1 1 1
G 1 1 1 1 1
1 1 1 1 1 3 3 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1
17
CONSTRUCT THE RESOURCE HISTOGRAM (2)
1 1 1 1 1 3 3 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1
A 1 1 1 1 1
B 1 1 1 1 1
C 1 1 1
D 1 1
E 1 1 1 1 1 1 1 1 1 1
F 1 1 1 1 1 1
G 1 1 1 1 1
1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
18
CONSTRUCT THE RESOURCE HISTOGRAM (4)
1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
19
ALLOCATING THE CALENDER (1)
20
DEFAULT CALENDER FIVE DAY AND EIGHT HOUR
WORKING WEEK
21
REDUCE THE PROJECT DURATION (1)
22
REDUCE THE PROJECT DURATION (3)
23
SOLUTION EXAMPLE 1
0 2 2 6
A C 0
0 2 2 2 4 6
0 6 8 8 9
START E 0 F
0 6 2 8 8 1 9
2 3 3 6
B 2 D 2
0 1 1 1 3 4
24
SOLUTION EXAMPLE 2
7 11
E 0 13
0 5 4 9
F
0 2 2 5 11 13 I
S A 0 B 0 F N
T 0 2 2 2 3 5 5 11 11 2 13 I
A S
D 0
R H
T
5 6 11
0 9 13 13
C 7
2 4 6
READINGS IN LIBRARY
25