You are on page 1of 5

ESTIMATE FOR THE CONSTRUCTION OF IIND FLOOR BUILDING FOR

LIBRARY AT SHANTI BHAWAN

4 X 4 X 4 X 5 = 320 cft.
320 cft @ Rs. 8/ cft
2. P.C.C.

= Rs. 2560.00

4 x 4 x 4 x 6 = 32
1 x 10 x 10 x 4= 33
65
65 cft @ Rs. 100 / cft.

3. Sand Filling

= Rs. 6500.00

4 x 4 x 4 x 3 6 = 224
1 x 10 x 10x1 8= 166
390
390 cft. @ Rs. 15 / cft.

= Rs. 5850.00

4. R.C.C.
4 x 4 x 4 x 1
4 x 4 x 4 x 8
4 x 9 x 1 x 5
3 x 40 x 9 x 1
4 x 9 x 1 x 19
40 x 9 x 6
1 x 10 x 10 x 5
1 x 40 x 5 x 4
1 x 10 x 10 x 4
1 x 10 x 10 x 4
2x1 x40x 9 x 1

= 64
= 42
= 15
= 90
= 57
= 15
= 42
= 66
= 33
= 33
= 60
517
=517 cft @ Rs. 250/ sft.

= Rs. 129250.00

5. Reinforcement
15 m3 @ 120 kg / m3 = 1800 kg.
1800 kg @ Rs. 50 / kg.
6. Brick Work

1 x 40 x 9 x 2
1 x 40 x 9 x 9
1 x 40 x 9 x 5

= 60
= 270
= 150
480

480 cft. @ Rs. 100 / cft.

7. Plastering

= Rs. 90000.00

= Rs. 48000.00

2 x 1 x 40 x 10 = 800
1 x 10 x 10
= 100
1 x 40 x 5 = 200
2 x 1 x 40 x 10 = 200
1300
1300 Sft. @ Rs 18 / sft.

= Rs. 23400.00

8. Tank Platform 1 x 40 x 5
= 200
1 x 10 x 10= 100
300
300 sft @ Rs.22 / Sft..
9. Door (Iron)

= Rs. 6600.00

1 x 3 6 x 7
25 x 3 k

= 25
= 75 Kg.

75 Kg. @ Rs. 70 / kg.


10. Motor

= Rs. 5250.00

Submersible Motor
1.5 HP Single phase
Wire & Tx
Pipe 200 2 Role Pipe
Labour charges

15000
10000
10000
10000

Total

= Rs. 45000.00
= Rs. 362410.00

POND

1. Earth work (JCB)-

2. PCC

3. Stone Work

1 x 50 x 50 x 20 = 50000
4 x 50 x 3 6 x 1= 700
4 x 50 x 15 x 5 = 15000
65700 x 3

= Rs. 197100.00

4 x 50 x 3 x 6

= Rs. 30000.00

= 300 x 100

4 x 50 x 3 x 10 = 6000 x 70

4. RCC

= Rs. 420000.00

2 x 4 x 50 x 3 x 6= 600 x 250= Rs. 150000.00

5. Reinforcement 17.14 x 120 Kg.= 2057 x 50

= Rs. 102850.00

4 x 60 x 15 = 3600 x 25 / sft.

= Rs. 90000.00

4 x 70 x 1 6 x 2 6= 1050 x 70

= Rs. 73500.00

4 x 70 x 1 6 x 4= 139 x 100

= Rs. 13900.00

6. Stonbe Patching
7. Stone work

8. P.C.C.
8. Earth dressing

= Rs. 100000.00
Total

= Rs. 1177350.00

V-CARE CONSTRUCTIONS
Architects, Engineers & Builders
BUDHARAJA, AINTHAPALI, SAMBALPUR (ODISHA)
Ref. No. ________

Date _______

ESTIMATE FOR THE SHEET ROOFING OF


SHANTI BHAWAN AT RAYAGADA
1. Sheet laying :
Angle frame (30/5 Angle) pillar with truss
4 x 2 pipe and 1 purline top powder
Coated colour sheet 0.5 mm and 6 half
Pipe fitted in 25/5 hooks for drainage.
6681.00 Sft. @ Rs. 220/ Sft.

Rs. 14,69,820.00

2. Rainwater Pipe

Rs.

3. Preparing of parapet (painting of building


Or parapet is not included)
Total

50,000.00

Rs.
30,000.00
Rs. 16,39,820.00

(Rupees sixteen lakhs thirty nine thousand eight hundred and twenty only)