Construction of 60 L.M.

of RC Canal
A. Concrete Works Class A
Volume of Concrete V = (0.5 + 0.5 + 0.3)(0.1) x 60 = 7.80 c.m.
Req’d Volume of MSA ¾ Gravel = 7.80 c.m.
Req’d Volume of Sand = 3.90c.m.
Req’d Bags of Portland Cement = 67 bags
Productivity Rate = 10.88 c.m./day/1 mason & 3 laborers
Suggested Item Labor Cost = P990/c.m.

B. Formworks A = 26.40 s.m.


No. Of Usage = 4 times
Length per set = 60/4 = 15 m.
Area per set A = (0.5+.6)(2)x15x2 = 6.60 s.m.
Req’d Plywood per set = 13 pcs-10mm x 1.20m x 2.40m
Req’d Battens per set = 50 pcs-2x2x12
Req’d CWNails= 16 kgs (Assorted CWNails)

1. Fabrication of forms
Productivity Rate = 7.37 s.m/day/1 Carpenter
Suggested Item Labor Cost = P50/s.m.
2. Installation/Removal of forms
Productivity Rate = 13.08 s.m./day/2 Carpenters & 1 Laborer
Suggested Item Labor Cost =P80/s.m.

C. Reinforcement
Req’d No. of Reinforcing Bars
110 pcs-10 dia. mm x 6.0m Grade 33/40 = 248.16 kgs.
110 pcs-12 dia. mm x 6.0m Grade 33/40 = 376.64 kgs.
Total = 624.80 kgs.

1. Fabrication of Rebars
Productivity Rate = 51.95 kgs./day/1 Steelman
Suggested Item Labor Cost = P12.00/kg

2. Installation of Rebars
Productivity Rate = 66.31 kgs/day/Steelman
Suggested Item Labor Cost = P9.00/kg.

Prepared by:

Felixander Collado Falgui


Project Consultant