Professional Documents
Culture Documents
COLLEGE PALANPUR
EN.Number :- 180610106052
1. Introduction of project
2. Equipment used on site
3. Pile foundation
4. Analysis of pile
5. Analysis Pile cap
6. RMC plant
7. Different test on field
7.1)core cutter method forbulk density of soil
7.2)calcium carbide method for moisture content
7.3)compressive strength of cube using compression testing machine (IS:516)
Project information:
Uses:
-digging of holes, foundations.
-pile dismantling
-river dredging etc..
(2) Pile rig machine
Piling rigs are mainly used to drill/create piles in soil, clay, etc. It is widely used for
cast-in-place piles, diaphragm walls, and foundation reinforcement.
Price :3 crore
Rent:1200/m.
(3) Joseph Cyriln Benford (JCB)
Bucket Capacity : 0.3 m³
(4) Hydraulic hoister
bentonite slurry is used to prevent the collapse of the soil in the pile bore to a larger
extent.
Bentonite helps to maintain the quality of concrete in the pile foundation. If
bentonite is not used, the soil particles may get mixed with the poured concrete,
resulting in a lower grade of concrete.
Bearing capacity of soil in pile foundation!!!
Pile length=pile cutoff level -pile termination level
=212.327-192.327
=20.0m
Dia of pile =1 m
C-cohesion of soil:
For medium stiff clay cohesion varies from 96 kN/m^2 to 198 kN/m^2,
So take average of its value the cohesion in medium stiff clay is 144 kN/m^2.
• Height of pier:10.553 m
• Width of pier:1.35 m
• Length of pier:4.8 m
• Total quantity of wet concrete =10.553×1.35×4.8
=68.38 m^3.
• Total quantity of dry concrete. =68.38+0.52×68.38
• quantity of dry concrete in one rectangular pier =103.9376
m^3.
• concrete grade used in pier =M35.
Drawing of piercap :
Analysis of reinforcement in pier cap :
• ANALYSIS OF PIER CAP
• PIER CAP
• Total quantity of steel used in one pier cap
=13655.39 kg
=13.655 tonm
Concrete used in piercap :
• Railway portion pier
• Danta portion piers were
rectangular in shape
comperatively the railway
portion contains circular shape.
• These piers contains one pile cap
as support for two pier.
• The height of main pile is 13.2m.
• The outer part of the main pier is
known “protection pier” and
inner pier is known as “main
pier”.
• Height of protection pier 8.8m.
• P.C.C. in base plate of girder
• The soil surface will not be properly levelled
• The base plate will help the casting in
properly levelled surface.
• The pcc is done around 150mm depth.
• Prestressed concrete girder
• M-45 grade of concrete is used.
• Height of girder = 2.5 meter.
• Reinforcement cover : 40 mm.
• Prestressing method used.
• There are 4 profiles in a single girder.
• Girder are I in shape.
• DRAWING OF GIRDER
• ANALYSIS OF GIRDER
• Total quantity of steel used in one girder
=15247.49 kg
=15.2 tonn
• CONCRETING IN GIRDER
• Concrete pump:
• A concrete pump is a machine
used for transferring liquid
concrete by pumping.
• Pumping rate=30 cubic meters/
hour
• Initial load test on piles:
• This test is performed for ensure the safe Load capacity of
piles.
• Load tests on piles are conducted on completion of 28 days
after casting of piles.
• Test is conducted as per IS 2911(part-IV) 1995.
• Application of load:
• The applied load on the piles is 2.5 times the vertical load
capacity of the pile.
• The test will be carried out by applying a series of vertical
displacement load each increment of about 20% of the
taste load on the pile.
• The load will be applied through the hydraulic Jack on the pile with
the use of the reaction frame girder.
• the maximum test loads shall be subjected to 24 hours.
• The safe load on a single pie should be the list of the following:
• (1)2/3rd of the final load at which the total displacement attains a
value of 18mm or Maximum Of 2% of pile dia, whichever is less.
• (2)50% of the final load at which the total displacement equals 10%
of the pile diameter in case of uniform diameter piles or 7.5% of the
bulb diameter in case of under reamed piles.
• The maximum settlement should not excced 18 mm.
• ultimate load at 18 mm settlement is=2010tonn.
• pile load capacity=2/3 of 2010=1340 tonn.
• cost of test=300rs/tonn.
• PILE LOAD TEST
• Oven dry method for determination of water
content of soil: