Manage Your Health Inc MYH Part1 PDF
Manage Your Health Inc MYH Part1 PDF
Table of Contents
Summary of projects .................................................................................................................................... 2
Summary of projects Memo ........................................................................................................................ 3
Weighted Decision Model ............................................................................................................................ 4
Weighted Decision Matrix for Manage Your Health, Inc. ........................................................................... 5
Business Case for Recreation and Wellness Intranet Project ..................................................................... 6
Project Charter ............................................................................................................................................. 9
Roles and Responsibilities.......................................................................................................................... 10
Change Request Form ................................................................................................................................ 11
Change Category: Scope Schedule Cost Technology Other ...................................................... 11
Approach for Collecting Requirements for Recreation and Wellness Intranet Project ........................... 12
Requirements Matrix for Recreation and Wellness Intranet Project....................................................... 13
Scope Statement (Version I) ...................................................................................................................... 14
Work Breakdown Structure for Recreation and Wellness Intranet ......................................................... 16
Gantt Chart draft ........................................................................................................................................ 17
Scope verification and change control ...................................................................................................... 18
Scope verification.................................................................................................................................... 18
Change control ........................................................................................................................................ 18
Activities that can be added ...................................................................................................................... 19
Milestones .................................................................................................................................................. 20
WBS Final .................................................................................................................................................. 201
Gantt Chart Final ....................................................................................................................................... 202
Network Diagram ...................................................................................................................................... 203
Resource Assignments ............................................................................................................................... 24
1|Page
Summary of projects
Project name
Project 3 Cross-Selling
System
Project 4 Web-Enhanced
Communications
System
Supports
business
strategies
Potential
financial
benefits
Reducing
internal costs
and improve
employee health
Reducing
internal costs.
Lower health
insurance
premiums.
Improve crossselling
Improve
development
and delivery of
products and
services
Increase profits
lower premiums
with insurance
companies
Save company
about $2 million
each year
Other benefits
Initial
assessment
value
Improve employee
health within one year.
Healthier employees =
better productivity
History of employee
health care expenses
and company health
care costs
Increase sales
Better communication
and employees,
customers and
suppliers work together
2|Page
$2 million each year and improve communication between employees, customers and suppliers
to better work together. This also improve sales that will improve profits. When people work
together their work productivity improves as well. Initial assessment value 3 out of 4.
3|Page
4|Page
5|Page
7|Page
8|Page
Project Charter
Project Title:
Budget Information: The Company has allocated $200,000 the project. The majority of cost for this
project will be internal labor.
Project Manager: Tony Prince, 0715985221, tonyprinc3@gmail.com
Project Objectives: This is a crucial project for the company. This is the first charter for the project, and
the objective is to complete the application in six months and start the implementation of the project in
the beginning of next year. This application must allow employees to register for company-sponsored
recreational programs and for company-sponsored classes and programs. It will track data on employee
involvement in these recreational and health-management programs and offer incentives for people to
join the programs and do well in them.
Main Project Success Criteria: The software must meet all written specifications, be thoroughly tested,
and be completed on time. The CEO will formally approve, the project with advice from other key stake
holders.
Approach:
Use internal staff as much as possible for planning, analysis and installation
Develop a survey to see what activities employees wish to participate in.
Develop a test application in three months and then the final in 3 months with testing every
week
Hold weekly progress review meetings with the project team and the sponsor
Test the software
Implement the application on the intranet
9|Page
Name
Organization/
Contact Information
Position
Sponsor
Roger Mat-abele
CEO
rogerm@gmail.com
Manager
Tony Prince
Project Manager
tonyprinc3@gmail.com
Manager
Yusaff Yang
HR Manager
yusaffy@gmail.com
Team Member
Cassandra Koste
Finance
kotsecassan@gmail.com
Team Member
Programmer
bonniejvr@gmail.com
Team Member
Lucas Olivier
Programmer
lucaso@gmail.com
Team Member
Patrick Kent
Network specialist
patrickk@gmail.com
Team Member
Nancy Drau
Business analyst
nancyd@gmail.com
Sign-off: (Signatures of all above stakeholders. Can sign by their names in table above.)
10 | P a g e
Date
4/2/2013
4/2/2013
4/2/2013
4/2/2013
Approve/Reject
Approve
Approve
Approve
Approve
11 | P a g e
12 | P a g e
Requirement Name
Date: 4/2/2013
Category
Source
Status
Health
Project charter
No.
R01
Recreational programs
Recreational programs
R02
Health
Project charter
R03
Software
Project charter
employee data
R04
Incentives
Developing application to
use the database
Other
Project charter
R05
Stay in budget of
Financials
Project charter
Still in budget
Schedule
Project charter
Still on Schedule
$200,000
R06
13 | P a g e
participate in.
3. Classes and programs: Organizing classes and programs that can help employees manage
their weight, reduce stress, stop smoking, and manage other health-related issues
4. Incentives: Determine incentives that will motivate employees to join and complete
programs.
5. Database: In order to track employee data on involvement for analysis.
6. Analyse data: To negotiate lower health insurance premiums.
7. Testing: Test the application and make sure it is user friendly.
8. Training: After project completion employees should be trained to use the application.
Scheduling workshops should help employees.
9. Promotion: To motivate employees and to announce the benefits for the employees.
10. Project benefits measurement plan: A project benefit plan will measure the financial value
of the project.
15 | P a g e
16 | P a g e
Change control
If a change to the project scope is needed the process for recommending changes to the scope
of the project must be carried out. Any project team member or sponsor can request changes
to the project scope. All change requests must be submitted to the Project Manager in the
form of a project change request document. The Project Manager will then review the
suggested change to the scope of the project. The Project Manager will then either deny the
change request if it does not apply to the project or hold a change control meeting between the
project team and Sponsor to review the change request further and perform an impact
assessment of the change. If the change request receives initial approval by the Project
Manager and Sponsor, the Project Manager will then formally submit the change request to the
Change Control Board.
If the Change Control Board approves the scope change the Project Sponsor will then formally
accept the change by signing the project change control document. Upon acceptance of the
scope change by the Change Control Board and Project Sponsor the Project Manager will
update all project documents and communicate the scope change to all project team members.
This is just to ensure that not just any changes can be made to the project and to ensure that
everyone stays within the scope of the project.
18 | P a g e
In the Collect requirements task the activity collect questioners can change to collect and
extract data from questioners. This mean that not only should we collect the questioners, but
after we collected them we should extract and analyze the data recovered from them. With this
data we can more accurately prioritize the requirements needed. This activity can take up to
five days because it is a large amount of data to process.
After holding group interviews with employees and team member we can then review all the
requirements we have gathered to determine the requirements that the project needs. This will
be done in the activity determine requirements. This can take up to two days. Now that we
have all the requirement we can then review the scope and WBS to finalize the documents with
this new requirements that we found were important and should be added to the project.
In the Company-sponsored Activities task were we determine where, what and how we are
going to present classes to the employees, we will meet with health experts. We will get a good
idea of what activities will be required to help the employees the best.
19 | P a g e
Milestones
Project kick-off Milestone: This is the first millstone, it symbolizes the beginning of the project
and the success that the project has been accepted. This milestone will be met when the
project start after the kick off meeting.
Finish Planning Milestone: This is the second milestone for the project. This milestone will be
successfully met when the planning of the project is successfully completed in the time it was
given. This milestone also symbolizes the beginning of the next task.
Finish Requirements Milestone: The third milestone will be successful when we successfully
determined all the requirements for the project in the time it was given.
Application finished Milestone: This milestone will be successful when the application is
finished on time without any problems. This milestone is very important, because it is the
biggest and top priority.
Project running as planned Milestone: This milestone is also important. It follows the
monitoring and controlling of the project which goes parallel with the project to monitor the
status of the project giving a status report at the end of each week. It will be successful when
the project ran as planed without any fallback or problems. It is met after a successful progress
report.
Project finished Milestone: This milestone is the big one also the last. It symbolizes the end of
the project if it were to be successful. It is when the project has finished successfully in time and
on budget.
WBS Final
Gantt Chart Final
Network Diagram
20 | P a g e
1 Initiating
1.1 Identify key stakeholders
1.2 Prepare project charter
1.3 Prepare Business case
1.4 Hold project kick-off meeting
Project kick-off Milestone
2 Planning
2.1 Hold team planning meeting
2.1.1 Prepare team contract
2.1.2 Hold Brainstorming meeting
2.1.3 Formulate Questioners
2.2 Identify, discuss, and prioritize risk
2.3 Prepare scope statement
2.4 Prepare WBS
2.5 Prepare Schedule and cost baseline
2.5.1 Determine resources
2.5.2 Determine Durations
2.5.3 Determine dependencies
2.5.4 Create draft Gantt chart
2.5.5 Review and finalize Gantt chart
Finish Planning Milestone
3 Executing
3.1 Collect requirements
3.1.1 Collect and extract data from Questioners
3.1.2 Hold Group interviews
3.1.3 Determine requirements
3.1.4 Review Scope and WBS
finish Requirements Milestone
3.2 Company-sponsored Activities
3.2.1 Meeting with experts
3.2.2 Recreational programs
3.2.3 Classes and programs
3.2.4 Determine incentives
3.3 Application design
3.4 Application development
3.5 Application Testing
3.6 Application Promotion
3.7 Application Roll-out
Application finished Milestone
3.8 Employee training
4 Monitoring and Controlling
4.1 Progress reports
Project running as planned Milestone
5 Closing
5.1 Prepare final project report
5.2 Prepare final project presentation
5.3 Lessons learned
Project finished Milestone
4 days
1 day
1 day
1 day
1 day
0 days
10 days
6 days
1 day
1 day
2 days
1 day
1 day
1 day
3.5 days
1 day
1 day
1 day
1 day
1 day
0 days
121 days
14 days
5 days
5 days
2 days
1 day
0 days
2 days
1 day
1 day
1 day
1 day
25 days
50 days
20 days
5 days
1 day
0 days
5 days
135 days
135 days
0 days
5 days
2 days
2 days
1 day
0 days
Mon 7/15/13
Mon 7/15/13
Tue 7/16/13
Wed 7/17/13
Thu 7/18/13
Thu 7/18/13
Fri 7/19/13
Fri 7/19/13
Fri 7/19/13
Mon 7/22/13
Mon 7/22/13
Wed 7/24/13
Thu 7/25/13
Fri 7/26/13
Mon 7/29/13
Mon 7/29/13
Mon 7/29/13
Mon 7/29/13
Tue 7/30/13
Wed 7/31/13
Thu 8/1/13
Fri 8/2/13
Fri 8/2/13
Fri 8/2/13
Fri 8/9/13
Fri 8/16/13
Tue 8/20/13
Wed 8/21/13
Thu 8/22/13
Thu 8/22/13
Fri 8/23/13
Fri 8/23/13
Fri 8/23/13
Mon 8/26/13
Mon 9/30/13
Mon 12/9/13
Mon 1/6/14
Wed 1/8/14
Fri 1/10/14
Mon 1/6/14
Mon 7/15/13
Mon 7/15/13
Fri 1/17/14
Mon 1/20/14
Mon 1/20/14
Wed 1/22/14
Fri 1/24/14
Fri 1/24/14
Thu 7/18/13
Mon 7/15/13
Tue 7/16/13
Wed 7/17/13
Thu 7/18/13
Thu 7/18/13
Thu 8/1/13
Fri 7/26/13
Fri 7/19/13
Mon 7/22/13
Tue 7/23/13
Wed 7/24/13
Thu 7/25/13
Fri 7/26/13
Thu 8/1/13
Mon 7/29/13
Mon 7/29/13
Mon 7/29/13
Tue 7/30/13
Wed 7/31/13
Thu 8/1/13
Fri 1/17/14
Wed 8/21/13
Thu 8/8/13
Thu 8/15/13
Mon 8/19/13
Tue 8/20/13
Wed 8/21/13
Fri 8/23/13
Thu 8/22/13
Fri 8/23/13
Fri 8/23/13
Fri 8/23/13
Fri 9/27/13
Fri 12/6/13
Fri 1/3/14
Fri 1/10/14
Wed 1/8/14
Fri 1/10/14
Fri 1/10/14
Fri 1/17/14
Fri 1/17/14
Fri 1/17/14
Fri 1/24/14
Tue 1/21/14
Thu 1/23/14
Fri 1/24/14
Fri 1/24/14
2
3
4
5
1
9
9
11
12
13
18
19
20
7
24
25
26
27
23
30
30
30
33
34
35
36
38
36
42
22
72
73
74
21 | P a g e
22 | P a g e
23 | P a g e
Resource Assignments
Name
Roger Matabele
Tony Prince
Yusaff Yang
Position
CEO
Project Manager
HR Manager
Lucas Olivier
Programmer/
Assistant Project
Manager
Patrick Kent
Network specialist
Nancy Drau
Business analyst
Bonnie Janse v
Rendberg
Programmer
Cassandra
Koste
Finance
Assignments/ Tasks
days
Hours
2.1, 2.5.5
3.1.4, 3.6
5.2
1.1, 1.4
2.1, 2.5
3.1, 3.2, 3.3, 3.6, 3.7
5.1, 5.2, 5.3
2.1
3.1, 3.2, 3.6, 3.8
2
2
1
2
10
60
5
1
5
9
9
5
16
70
500
30
4
25
1.2, 1.3
2.1, 2.3, 2.4, 2.5.5
3.3, 3.4, 3.5, 3.6, 3.7
5.1, 5.2, 5.3
2.1
3.3, 3.4, 3.5, 3.6, 3.7
2
5
100
5
1
100
9
25
450
23
4
350
2.1, 2.2
3.1, 3.2
4
5.1
2.1
3.3, 3.4, 3.5, 3.6, 3.7
2
16
135
2
1
100
9
70
270
8
4
450
2.1
3.1, 3.2
1
16
4
70
24 | P a g e