Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

Rev. No. 00

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Page 1 of 9

Project Title
ESNAAD Main Gate Complex

Document Title
Method Statement for Cable Pulling & Termination of MV Cables

Re
v.
No.

Date

Descripti
on /
Remarks

Revision and Approval History


CONTRACTOR
EMPLOYER
Prepar
ed

Reviewe
d

Approve
d

Approved

Approva
l Status

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 HEALTH AND SAFETY ARRANGEMENTS
8.0 PROCEDURE
8.3 CABLE TERMINATION & INSTALLATION
8.4 TESTING & COMMISSIONING
9.0 DOCUMENTATION

Rev. No. 00
Page 2 of 9

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

Rev. No. 00

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Page 3 of 9

1.0 PURPOSE
This method statement is applicable for laying & termination of MV Cables
for ESNAAD MAIN GATE TRUCK X-RAY COMPLEX in accordance with the
specified standards and regulations in project specifications.
2.0 SCOPE
The Scope of works includes the delivery to site, installation, precommissioning, testing, commissioning and guarantee of the system as
described in the specification/contract documents and drawings.
3.0 REFERENCES
3.1
3.2
3.3
3.4
3.5
3.6

Project Contract Specifications


Approved Project Quality Plan: EMG-PQP-01 Rev.01
Approved Project HSE Plan: EMG-HSE-01 Rev.00
ESNAAD HSE Procedures
Approved AFC Drawings
Approved Materials

4.0 DEFINITIONS
:

ATS Group/Advanced
(ATS/AIS)

Customer

CICPA

Operating Company
Contractor/Contractor

:
:

ESNAAD
Aegis Contracting L.L.C. (Aegis).

Subcontractor/Subtiers

Organization employed by Contractor for


executing part of the works

Supplier

Organization used by Contractor and /or


subcontractors
for supply of approved
Materials.

IR

Inspection Request

Employer/ Client

Integrated

Systems

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

HSE

Rev. No. 00
Page 4 of 9

Health, Safety and Environment

5.0 RESPONSIBILITIES
5.1 The Project Manager is over all responsible for implementation of
this Method Statement and to ensure that his site team of
Engineers and Foremen are aware of this Method Statement and all
resources, manpower, material and equipment are available to
carry out the work as planned and without any delay.
5.2 The Construction Manager/Site Engineer will co-ordinate with the
MEP Sub contractors and the Safety Officer, Foreman for a safe and
proper execution of works.
5.3 The Site Supervisor/General Foreman along with Foreman will
ensure that, the installation is carried out according to the
Specifications/Drawings and the Method Statement.
5.4 Lead QA/QC Engineer, in close interaction with MEP Site personnel,
will ensure that, the works are carried out as per the project
requirements. He is also responsible for the implementation of
QA/QC related to works as detailed in this procedure and for
completing Quality Documents for the Installation works.
5.5 Lead Safety Engineer will ensure implementation of all safety
procedures, Safety measures related to the nature of works being
carried out in accordance with Project HSE Plan EMG-HSE-01
Rev.00
6.0 EQUIPMENT

Cable Rollers
Cable Pulling Grip
Hand Cable cutter
Manual Cable Crimpers
Hacksaw blade
Power Tools
Tool Box
Measuring Tape
Ladders / Scaffoldings/Platform
Hand tools Hilti Drill Machine

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Rev. No. 00
Page 5 of 9

Hilti Concrete Bit (6mm to 16 mm)


Anchor Bolt/Screw
Screw Driver
Adjustable Spanner
Hammer
Electricians Knife
Multi Meter
1 KV / 5 KV IR Test Kit
Continuity Tester
Torque wrench
VLF Test Kit

7.0 HEALTH AND SAFETY ARRANGEMENTS


The hazards associated with the Cable Pulling & Termination of
MV Cables have documented (Ref: Job Hazard analysis Doc. No.
HSE/RA/__. Control measures as identified in the documents
will be complied with the approved Project HSE Plan.
8.0 PROCEDURE
8.1 Preparation
8.1.1 Excavation

Permit to Work (PTW) shall be raised for the excavation


clearly mentioning the location of work, size of
excavation and levels.

Excavations area shall be surveyed and marked to the


lines and levels as shown on the drawings.

The area of excavation will be cordoned off using safety


devices.

Ensure the working area at any confined space is free


from any Hazardous Gas by proper Gas testing using the
Gas testing instrument.

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Rev. No. 00
Page 6 of 9

8.1.2 Materials

Not necessary for the construction shall be removed


carefully and stored neatly for reinstating after the
construction works.

The material received from the client shall be stored in


designated area of store.

Arrangements shall be made to protect against effects of


weather and environment.

8.2 Cable Pulling

Insulation resistance of the cables shall be checked


before laying cables.

After the test, the end of the cable shall be sealed to


prevent the ingress of moisture.

Location of the panels / equipment shall be identified.

Cables shall be lubricated if bends in conduits are


encountered in a run to facilitate drawing in.

Cables must not be bent to a radius of less than 12 times


the overall diameter of the cable.

Rollers must be used where cables are installed in an


open trench using a pulling rope and eye; cable rollers
are to be used at frequent intervals to support the cables
and must never be more than 3 meters apart.

The rollers are to be placed securely to prevent


movement.

The pulling rope must be equipped with a swivel and be


attached to the cable by a stocking grip with pulling eye.

The cable drum intended for cable pulling shall be


identified as per that indicated in the drum schedule.

The cable drums shall be un-packed and placed on a


cable roller, as required.

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Rev. No. 00
Page 7 of 9

Cable laying will generally start from one end of the route
length or at any suitable point, as necessary.

Depending on the weight and size of the drum, suitable


size of the cable rolling shaft (Spindle) shall be placed
inside the central axis of the drum.

Suitable jacks shall be placed firmly on the ground and


jacked-up to allow clearance from the ground depending
on the size of the cable drum.

The drum shall be lifted by required equipment and


placed on the jacks.

The cable drum will be correctly positioned and the


direction of cable pulling as indicated by arrow on the
drum shall be complied.

The cable shall be drawn into the trench smoothly with a


minimum of stops and at an average speed of between
9-12 meters per minute, to avoid irregular movement.

8.3 Cable Termination & Installation

Termination point inside the panels / equipment shall be


considered for suitable spare length to be left available
during pulling of cable termination.

After cutting the cable to the required length the


termination work will be conducted as per ADDC
Standard.

Jointing and Termination will be carried out as per ADDC


standards. All jointing and termination work will be
carried out by trained technicians, experienced in such
work for the operating voltage concerned.

Proper crimping tools shall be used compression type


lugs. All cables are to be terminated used glands of
proper type and size as per area classification.

The gland shall be assembled strictly in accordance with


manufacturers instruction, particular attention being
paid to ensure good mechanical and electrical contact

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Rev. No. 00
Page 8 of 9

between parts without excessive strain or distortion of


cable.

The entire body of the cable must enter the gland. The
cable shall be on a straight axis from a point at least six
diameter before entering the gland. Seals shall be
checked for correct size at the point of application.

Unused cable entries shall be closed with plug suitable


for the degree of protection classification.

After completion of indoor and outdoor termination the


cable is ready for Testing.

8.4 Testing & Commissioning

The following calibrated testing instruments will be used:

1 KV / 5 KV IR Test Kit - 1 no.


Multi Meter - 1 no.
Continuity Tester - 1 no.
Continuity Tester - 1 no.
Torque wrench - 1 no.
VLF - Test Kit

Before starting the test, the corresponding Circuit


Breakers at both ends of the cables are racked out and
earthed properly.

Test will be conducted at the MV panel end. The opposite


end of the cable termination will be secured & protected.
Testing engineer will be at the end where high voltage is
applied and another Engineer to monitor at the opposite
end of the cable.

Insulation Resistance will be done first: (a) between


termination lugs; (b) Phase, Neutral and Earth
termination lug; (c) conductor to termination lug. This will
be done one minute each at 5kV, and the results are
noted as per approved test report format.

Employer

Contractor:

Operating Company (OC):

ESNAAD
AEGIS CONTRACTING LLC

Document Title:

Method Statement for Cable Pulling & Termination of MV


Cables

Document No. EMG-LAS-MSBGxxx-xx-015

Project Title:

Date:

ATS/AIS/DERA/028/2013- Esnaad Main Gate Complex- Design


and Build, Site development and Buildings-Dera Security Project

Rev. No. 00
Page 9 of 9

Note: The cables and conductors must discharged


per test.

The continuity test and phase sequence tests would be


carried out and results would be recorded for records and
future reference.

9.0 DOCUMENTATION
9.1 Request of Inspections will be issued for all hold and witness points
as indicated on the Quality Control Plans
9.2 QC Forms will be jointly completed and signed off at the end of
Inspection.
9.3 Attachment:
Quality Checklist - Cable Pulling & Termination of MV
Cables Inspection
Risk Assessment