iLO4 Milestone plan is below, and this is the current up-to-date schedule.
iLO4 2.00 Milestone
MRD Approved
POR Approved (SW-PAC)
Functional Spec Review
Dev Complete Test Plan Review
Date
QA Phase 1 Start
1/15/2014
QA Phase 2 Start
3/1/2014
UI Translation
Med /Low Cut-of
High cut-of
RC
RC / 100% QA Attempted w/ <
10% failure
Firmware
PMR
Launch (Web Rel)
4/23/2013
12/16/2013
4/14/2014
5/5/2014
6/17/2014
7/2/2014
8/18/2014
Date
QA Phase 1 Start
6/13/2013
QA Phase 2 Start
9/13/2013
UI Translation
9/3/2013
9/13/2013
10/18/2013
10/11/2013
11/14/2013
11/7/2013
Date
12/18/2013
4/23/2013
6/13/2013
6/1/2013
12/2/2013
10/1/2013
1/9/2014
11/1/2013
1/17/2014
11/30/2013
2/20/2014
12/20/2013
12/12/2013
1/24/2014
2/21/2014
3/13/2014
4/24/2014
Date
NA
Pending
9/13/2013
9/1/2013
8/1/2013
9/13/2013
10/18/2013
11/14/2013
12/18/2013
10/11/2013
1/9/2014
2/20/2014
N/A
QA Phase 1 End
11/1/2012
High cut-of
RC
Firmware
Dali Launch (Web Rel.)
11/5/2012
11/19/2012
12/11/2012
6/6/2013
8/16/2013
N/A
PMR
QA Phase 1 End
12/1/2013
High cut-of
RC
Firmware
12/12/2013
1/24/2014
2/20/2014
PMR
1/9/2014
Bug fix and development of new features on ARM processors and 32 bit
microcontroller
Communicate with developers and managers from external teams to root cause and
eliminate cross-product issues.
Track Issues with respect to development team and QA team before and after the
release of firmware to customers.
Update release notes and build the final component to release it on the web for
customers.