Mphasis is involved in all the three products iLO4, iLO3, and iLO2.

iLO4 Milestone plan is below, and this is the current up-to-date schedule.
iLO4 2.00 Milestone
MRD Approved
POR Approved (SW-PAC)
Functional Spec Review
Dev Complete Test Plan Review

Date

QA Phase 1 Start

1/15/2014

QA Phase 2 Start

3/1/2014

UI Translation
Med /Low Cut-of
High cut-of
RC
RC / 100% QA Attempted w/ <
10% failure
Firmware
PMR
Launch (Web Rel)

4/23/2013
12/16/2013

4/14/2014
5/5/2014
6/17/2014

7/2/2014
8/18/2014

iLO4 1.40 Milestone


MRD Approved
POR Approved (SW-PAC)
Functional Spec Review
Dev Complete Test Plan Review

Date

QA Phase 1 Start

6/13/2013

QA Phase 2 Start

9/13/2013

UI Translation

9/3/2013
9/13/2013
10/18/2013
10/11/2013
11/14/2013
11/7/2013
Date
12/18/2013

Med /Low Cut-of


High cut-of
iLO3
1.50 Milestone
RC
MRD Approved
RC / 100%
QA Attempted
POR
Approved
(SW-PAC) w/ <
10% failure
Functional Spec Review
Firmware
Dev Complete PMR
Test Plan Review
Launch
Rel)
QA
Phase(Web
1 Start
QA Phase 2 Start
UI Translation
Med /Low Cut-of
High cut-of
RC
RC / 100% QA Attempted w/ <
10% failure
Firmware
PMR
Launch (Web Rel)

4/23/2013
6/13/2013
6/1/2013

12/2/2013
10/1/2013
1/9/2014
11/1/2013
1/17/2014
11/30/2013
2/20/2014
12/20/2013
12/12/2013
1/24/2014
2/21/2014

3/13/2014
4/24/2014

ILO3 is Maintenance project, the schedule is shared below.


iLO3 1.70 Milestone
MRD Approve
POR Approved (Biz)
Functional Spec Review
Dev Complete Test Plan Review
QA Phase 1 Start
QA Phase 2 Start
Low /Med Cut-of
High Cut-of
RC
RC / 100% QA Attempted w/ < 10%
failure
LP translation complete
Firmware
PMR
Launch (Web Rel.)

Date
NA
Pending
9/13/2013
9/1/2013
8/1/2013
9/13/2013
10/18/2013
11/14/2013
12/18/2013

10/11/2013
1/9/2014
2/20/2014

here is the schedule

2.15 Dev Complete

N/A

QA Phase 1 End

11/1/2012

High cut-of
RC
Firmware
Dali Launch (Web Rel.)

11/5/2012
11/19/2012
12/11/2012
6/6/2013
8/16/2013

2.23 Dev Complete

N/A

PMR

QA Phase 1 End

12/1/2013

High cut-of
RC
Firmware

12/12/2013
1/24/2014

Dali Launch (Web Rel.)

2/20/2014

PMR

1/9/2014

iLO2 is sustenance project and

Bug fix and development of new features on ARM processors and 32 bit
microcontroller

Communicate with developers and managers from external teams to root cause and
eliminate cross-product issues.

Track Issues with respect to development team and QA team before and after the
release of firmware to customers.

Responsible for build, releasing the firmware after QA Test.

Update release notes and build the final component to release it on the web for
customers.

Develop customer-facing documentation to describe new functionality and fixes in


firmware releases

Debug and fixing firmware issues using MULTI debugger tool.

Represented the product during the design, development, and prototyping of


multiple new Industry Standard Servers.