Page 1 Luana Forms

CONTRACTOR'S DAILY REPORT

PROJECT : Hue Hotel Boracay WEATHER : 2400 hrs


LOCATION : Boracay Island, Malay, Aklan Sunny/Fair/Cloudy
OWNER/CLIENT : Luana Lifestyle & Leisure Hotel Inc. Rainy 0600 hrs
CONTRACTOR : RVN Construction & Trading Int'l. Inc. Havy Rain
DATE : 6-Jan-17 Typhoon
1200 hrs

MANPOWER NO. MAJOR & MINOR EQUIPMENT USED UNIT


1. Operation Manager 0 Handrill 44
2. Project Manager 0 Air Compressor Machine 2
3. Project in Charge 2 Welding Machine 1
4. QA/QC 1 Edge grinder 18
5. Safety Officer / Nurse 1 Spray Gun 4
6. Admin Head 3 Circular saw 2
7. Warehouse Man 2 Ramset 1
8. Time Keeper 2 Laser level 1
9. Foreman 3 Jigsaw Machine 3
10 Driver 1 Riveter 10
11. Security Guard 0 Pneumatic brad nailer 4
12. Installer 17 Flat sander 10
13. Carpenter 10 Hammer drill 4
14. Painter 13 Tile cutter 2
15. Helper 17 Aviation Snip 7
16. Tile Setter 9
17. Leadman 0
18. Genset Operator / Maintenance 1

GRAND TOTAL 82
WORK ACTIVITIES / LOCATION
- Installation of luggage wall veneer @ 3rd floor and 4th floor
- Installation of headboard support veneer @ 3rd floor and 4th floor
- Installation of shower exterior veneer @ 3rd floor and 4th floor
- installation of baseboard @ 5th floor
-Painting works at accent drop ceilling on street market
-tile insatallation on hallway @3rd flr. And Market Place

PROBLEM ENCOUNTERED

PREPARED BY: NOTED BY:

Pamela Loraine Garcia Jerome Raymond F. Garcia


QA/QC PROJECT MANAGER
PROJECT Hue Hotel Boracay
LOCATION Boracay Island, Malay, Aklan
OWNER / CLIENT Luana Lifestyle & Leisure Hotel Inc.
CONTRACTOR RVN Construction & Trading Int'l. Inc.
DATE 6-Jan-17

DAILY MANPOWER REPORT

CLASSIFICATION DESIGNATION EMPLOYED DAY SHIFT NIGHT SHIFT ABSENT LEAVE PRESENT PRESENT SUB-TOTAL

Operation Manager 1 1 0 1 0
Project Manager 1 1 0 1 0
Project in Charge 2 2 0 2
QA/QC 1 1 0 1
Safety Officer/ Nurse 1 1 0 1
STAFF 12
Admin Head 4 4 0 3
Time Keeper 2 2 0 2
WareHouse Man 2 2 0 2
Genset
0
Operator/Maintenance 1 1 1
ForeMan 4 4 1 3
Driver 1 1 0 1
Security Guard 0 0 0 0
installer 29 29 12 17
SUPPORT Carpenter 29 29 19 10 70
Painter 25 25 12 13
Helper 33 33 16 17
Tile Setter 21 21 12 9
Leadman 2 2 2 0
TOTAL 159 159 74 2 82 82

Prepared by: Noted By: Received By:

Pamela Loraine Garcia Jerome Raymond Garcia Al Tefora


QA/QC RVN-Project Manager Luana- Technical Assistant