GRAND TOTAL 82
WORK ACTIVITIES / LOCATION
- Installation of luggage wall veneer @ 3rd floor and 4th floor
- Installation of headboard support veneer @ 3rd floor and 4th floor
- Installation of shower exterior veneer @ 3rd floor and 4th floor
- installation of baseboard @ 5th floor
-Painting works at accent drop ceilling on street market
-tile insatallation on hallway @3rd flr. And Market Place
PROBLEM ENCOUNTERED
CLASSIFICATION DESIGNATION EMPLOYED DAY SHIFT NIGHT SHIFT ABSENT LEAVE PRESENT PRESENT SUB-TOTAL
Operation Manager 1 1 0 1 0
Project Manager 1 1 0 1 0
Project in Charge 2 2 0 2
QA/QC 1 1 0 1
Safety Officer/ Nurse 1 1 0 1
STAFF 12
Admin Head 4 4 0 3
Time Keeper 2 2 0 2
WareHouse Man 2 2 0 2
Genset
0
Operator/Maintenance 1 1 1
ForeMan 4 4 1 3
Driver 1 1 0 1
Security Guard 0 0 0 0
installer 29 29 12 17
SUPPORT Carpenter 29 29 19 10 70
Painter 25 25 12 13
Helper 33 33 16 17
Tile Setter 21 21 12 9
Leadman 2 2 2 0
TOTAL 159 159 74 2 82 82