Date: March 22, 2019

Project Name: THE ARTON STRIP


Subject: POURING REPORT FOR THE PERIOD COVERED July 19, 2018 - September 18, 2018
Supplier: PREMIERE READY MIXED CONCRETE INC.
PRS NO.

VOLUME 5000 PSI


DATE OF POURING TYPE OF STUCTURE (LOCATION) SUPPLIED 3/8 PCD DR NO.
(cu.m) @ 28D
8 0166291
8 0166292
7 0166294
CISTERN TANK WALLS (CTW-1,2,3)(RW- 7 0166300
July 19, 2018 2,2A,3)(C-15 2 SETS, C-16,C-17,C-21 (2 SETS) B-F/1-4,C/1,D/1,E/1,C/2,D/2,E/2 62
(1st LIFT) 8 0166305
8 0166310
8 0166312
8 0166315
6 0169366
RW-1, C-21, C-15 (2 SETS) (1ST LIFT)
August 9, 2018 B-E/1-2,C/1,D/1,E/1 17 6 0169373
(BASEMENT 2)
5 0169386
10 0172626
RW-1,C-14A,C-14 (2 SETS),C-15 (2 SETS)(1ST 18
August 31, 2018 E-H/1,H/1-3,H/1,H/2,H/3 8 0172629
LIFT)(BASEMENT 1 - LOWER GROUND LEVEL)
6 6 0145081
RW-2, C-15 (2 SETS), C-21 (2 SETS),C-17 (2
September 18, 2018 SETS), C-16 (2ND LIFT)(BASEMENT 1 - A-E/1-2,C/2,D/2,C/1,D/1,E/1,D/2,E/2,E/3 8 8 0174881
LOWER GROUND)
111.00 111.00

Prepared By: Checked By:

ACEBOY SIBBALUCA RUSSEL G. MORALES


CS Concreting Works Construction Manager
REMARKS