QA/QC Inspection Checklist

design coordinates, inc. CP No. __________________


VECTOR THREE
Northgate, Cyberzone, Filinvest Corporate City,
Alabang, Muntinlupa City

Building Element/System: D40 Fire Protection Systems


Category: D4010.15330 Wet Pipe Fire Sprinkler System
Items to be Inspected: Valves/Alarm Check
Date Inspected:
Supplier:
Location:

Non - Not Remarks / Due


Conform.
Conform. Avail.
N/A Open Close
ITEM / REQUIREMENT Corrective Actions Date

A SUBMITTALS:
A.1 Materials
1. Type :
2. Brand :
3. Origin :
4. Type of Joint :
5. Conformance to standards
A.2 Shopdrawings

B INSTALLATIONS:
Is alarm check valve assembly
with accessories
B.1 installed in areas
accessible and easily
visible?
Is the water supply line
thoroughly flushed
B.2 from all foreign
matter before valves
installation?
Condition of valve clapper and
B.3
other accessories
Is flow direction arrow on the
valve body with the
B.4 appropriate gaskets, bolts
and/or couplings same with
direction of water flow?
Provision for viewing the
B.5
alarm line drain water
Are valve and accessories
B.6 protected from physical
damage?
Are all valve accessories
B.7
completely installed?
Is there requirement for
optional equipment like retard
B.8
chamber, pressure switch,
excess pressure pump, etc.
B.9 Valves identification

DCI-QIC rev. 01 Page 1 of 2


QA/QC Inspection Checklist
design coordinates, inc. CP No. __________________
VECTOR THREE
Northgate, Cyberzone, Filinvest Corporate City,
Alabang, Muntinlupa City

General Notes, Comments and Recommendations:

Inspected by : Noted by : Concurred by :

________________________________ ___________________________________ ________________________________


Construction Project Engineer / Architect Construction Project Manager Supplier

Distribution:

Supplier Customer/ Developer DCI File

Note: A separate Notice to Comply (DCI-NTC) can be issued to the supplier/contractor if the non-conforming item may
take time to rectify and complete.