Professional Documents
Culture Documents
:
PROJECT TITLE
OPERATION
REQUEST FOR INSPECTION (RFI)
Subcontractor : Date :
Location : Time :
Reference Reference
Drawing Documents
Work Item
Activity
Originator Acknowledged by
Participant Main Contractor Main Contractor Consultant's Engineer *Owner's Rep / Engineer
(Operation) (QA/QC) Representative *(if applicable)
Signature
Name
Date
To be attended by
Inspection Results :
Remedial works listed below to be completed and inspection is required after remedial works
Rejected
Remarks/Comments :
Inspected by
Main Contractor Main Contractor Consultant's Engineer *Owner's Rep / Engineer
Participant
(Operation) (QA/QC) Representative *(if applicable)
Signature
Name
Date
To be attended by
DOC. REF. :
PROJECT TITLE
Electrical Services
Conduit- Installation & Inspection Checklist
Location :
Identity :
Checking
Item Descriptions Yes No Date Remarks
Method
General Visual Inspection Checklist:
1 Check conduits and fittings used are of approved type Visual
Check the routes, sizes and positions as per approved
2 Visual
shop drawing.