You are on page 1of 204

Technical Proceedings-

Presentations
TH
6 CUSTODY MEASUREMENT
TECHNICAL EXCHANGE MEETING
(CMTEM 2011)

November 21-23, 2011


Dammam Office Building
Saudi Aramco
Maintain Measurement Accuracy
from Design to Operation

Authors:
Peter Jakubenas Installed Product Services Manager, FMC Technologies
Bryan Partridge After Market Manager, FMC Technologies
Jeffery MacKenzie Global Aftermarket Manager, FMC Technologies

Presented by:
Peter Sims Business Development Manager FMC Technologies
APPLICATIONS

PIPELINE TERMINALS
EXPORT TERMINALS
IMPORT TERMINALS
FLOATING PRODUCTION STORAGE VESSELS -
FPSO AND FSO
CUSTODY TRANSFER AGREEMENTS

BUYERS
SELLERS
CUSTOMS
GOVERNMENT
SHIPPERS
FISCALIZATION ACCURACY

QUANTITATIVE MEASUREMENT
QUALITATIVE MEASUREMENT
TRACEABILITY TO RECOGNIZED STANDARDS

We are seeking the truth!


QUANTITATIVE MEASUREMENT

METERS
PROVERS
FLOW COMPUTERS
CONTROL SYSTEMS
QUALITATIVE MEASUREMENT
DENSITY OR GRAVITY
TEMPERATURE
PRESSURE
VISCOSITY
SAMPLING
BS & W
DESIGN OBJECTIVES

ACCURACY- HIGH CERTAINTY- LOW


UNCERTAINTY- BOTH INITIAL AND ONGOING
SAFETY
RELIABILITY
OPERATOR EASE
LOW ONGOING OPERATING COSTS
LOW CALIBRATION COSTS
LOW MAINTENANCE COSTS
VALUE
SYSTEMS APPROACH

ULTIMATE PERFORMANCE
PROPERLY SELECTED COMPONENTS TO ACHIEVE
LOW UNCERTAINTY
TURNKEY CONTRACT
EXPERIENCED
SUPPLER WITH PRODUCT LINE KNOW HOW AND
COMMITMENT
SUPPLIER WITH ONGOING SUPPORT SERVICES
HISTORY
WHAT ACCURACY CAN BE
ACHIEVED?

METERING +/- O.1 %


TO +/- 0.25%
OVERALL
TANK GUAGING +/-
0.7% UNDER BEST OF
CONDITIONS
COST OF UNCERTAINTY
ASSUME 10,000 BBL PER HOUR @ $100 per
BBL (10 Pipeline)
ASSUME 0.5 % UNCERTAINTY BETTER THAN
TANK GUAGING- $0.50 per BBL
$120,000 AT RISK PER DAY
$3,600,000 AT RISK PER MONTH
$43 MILLION AT RISK PER YEAR
UNCERTAINTY- RISK

Under Registration
Deprives the seller of entitled revenue
Over Registration
Customer complaints and loss of good will
Possible retroactive rebates
Potential lawsuits
We are seeking the truth (CERTAINTY) in
measurement
Uncertainty is RISK associated with the
transaction
TYPICAL SYSTEM P&ID

DESIGN FOR LOWEST TOTAL


OWNERSHIP COST

TOTAL COST FOR ASSET OVER LIFE =


INITIAL COST
+ Y x YEARLY ENERGY COST TO OPERATE
+ Y x YEARLY OPERATOR LABOR COST
+ Y x YEARLY CALIBRATION LABOR COST
+ Y x YEARLY MAINTENANCE LABOR AND
MATERIALS COSTS

Where Y represents life of project, typically 20


years.
OPERATING ENERGY COST
CONSIDERATIONS
PUMPING COSTS DUE TO PRESSURE DROP
PRESSURE DROP DUE TO
HEADER SIZE AND DESIGN
STRAINER DESIGN (EXCEPT FOR ULTRASONIC METER SYSTEMS)
METER TECHNOLOGY SELECTED
o ULTRASONIC

o POSITIVE DISPLACEMENT

o HELICAL TURBINE

o CONVENTIONAL TURBINE

o CORIOLIS

SAMPLER MIXING METHOD


o JET MIXER- PUMP REQUIRES ENERGY

o STATIC MIXER

BLOCK VALVE SIZING


CONTROL VALVE SIZING
METER SELECTION -

FLOW RATE
VISCOSITY
METER RUN QTY. VS SIZE
METER SELECTION RULE OF
THUMB BASED ON FLOW RATE
AND VISCOSITY
QUALITY SKID
LINE EXTRACTION DEVICES
SLIP STREAM PUMPS
DENSITOMETER(S)
VISCOMETER(S)
FLOW METER AND CONTROL VALVE IN LOOP
BS & W MONITOR
SAMPLER
SKID AUTOMATION

MOTOR OPERATED VALVES


REMOTE READOUT EQUIPMENT
METER TRANSMITTERS
TEMPERATURE
PRESSURE
CONTROL ROOM OR SKID MOUNTED FLOW
COMPUTER I/O
CONTROL ROOM INSTRUMENTS-
FOR OPERATOR EASE
FLOW COMPUTERS
GRAPHIC PANELS FOR BACKUP
REDUNDANT CONFIGURATIONS
PLC FOR VALVE INTERLOCK
CONTROL ROOM INSTRUMENTS

SUPERVISORY COMPUTERS
CONTROL
DATA COLLECTION
AUTOMATED PROVING
EXTENSIVE REPORTING AND ARCHIVING
SOPHISTICATED MAN MACHINE INTERFACES
COMMUNICATION INTERFACES
METER AND PROVER DIAGNOSTICS
TYPICAL HMI SCREEN
TYPICAL CRT SCREEN
Meter Performance Analysis
Software
MAINTENANCE and CALIBRATION
ISSUES

PROPER MATERIALS AND COATINGS TO BATTLE


INTERNAL AND EXTERNAL CORROSION
EASE OF ACCESS TO EQUIPMENT ROUTINELY
CALIBRATED OR SERVICED
SET UP MAINTENANCE INTERVALS BASED ON
EXPERIENCE AND OBSERVED STABILITY OF
EQUIPMENT
INSTALL REDUNDANT EQUIPMENT AND DO
CONDITION BASED MAINTENANCE
TRACK ALL MAINTENANCE
Case Study - Metering

Maintenance Contract Overview


Start Date: 1 October 2004
st

Duration: 5 years plus 5 x 1


year options
Original Scope
UK (1 onshore plant, 16
offshore platforms, 68,000
man hours)
NL (157 onshore sites, 22
offshore platforms, 38,000
man hours)
NO (1 onshore site, 1 offshore
platform, 11,000 man hours)

26
Contract Framework
Program Management

Administration Planning and Operations Consultancy and Engineering

Client reputation protection


Compliance Delivery Technical measurement support
Work control systems Mismeasurements
Purchasing
Breakdown response Audit support
Work registration
Scheduling and planning Management of audit actions
Invoicing
Work Preparation Calibration verifications
Payment problems resolution
1st technical line support Metering philosophy development
Subcontract management
SAP Improvements Procedure writing
Monthly commercial reporting
Field Execution Calibration sheet design
Monthly forecasting
Test equipment management Engineering design review
Spares management PMA Collaboration
Monthly operational reporting Project support
QA

27
Contract Personnel
Total of 65 people:

Program Management (1)

Administration (6) Planning and Operations (44) Consultancy and Engineering (14)

UK UK UK
1 Contract Manager (50%)1 3 Planning Engineers1 1 Senior Consultant1
3 Administrators1 22 Metering Technicians1 6 Metering Engineers1

NL NL NL
2 Administrators 3 Planning Engineers 1 Senior Consultant
1 Financial controller (20%) 12 Metering Technicians2 4 Metering Engineers

NO NO NO
1 Administrator (10%) 3 Metering Technicians 1 Senior Consultant
1 Analyser Specialist3 1 Metering Engineer

28
Equipment Supported
SCOPE OF EQUIPMENT SUPPORTED
FLOW COMPUTERS:
S500S, S600S, MICRO 5000S, OMNI, SOLARTRON 7915, 7951, 7925, 7922, 7955,
869M,INTROMET FC500, FC2000, NETOIL, DANIELS S103, PROMAC, CONTREC

PRIMARY AND SECONDARY DEVICES:


MAGFLOWS, MULITPHASE METERS, TURBINE METERS, ULTRASONIC METERS, ORIFICE
METERS, V-CONE METERS, ANNUBARS, CORIOLIS METERS, POSITIVE
DISPLACEMENT METERS, DP AND PT TRANSMITTERS, TEMPERATURE
TRANSMITTERS, 3095 MV, GAS AND OIL DENSITY TRANSDUCERS
MICROMETER, YOKOGAWA, SOLARTRON, FOXBORO, E+H, ABB, KROHNE, ROXAR,
FRAMO, FAURE HERMAN, BROOKS, DANIELS, ROSEMEOUNT, PECO, HECO, FMC,
MICRO MOTION
1, 2, 3, 4, 5, 6, 8, 10, 12.
Equipment Supported
SCOPE OF EQUIPMENT SUPPORTED
ANALYSERS:
OIPW ANALYSERS, WIO ANALYSERS, RD ANALYSERS, PYCNOMETERS, CHROMATS,
DEW POINT ANALYSERS, H2S ANALYSERS
ROXAR, DANIELS, SOLARTRON, E+H, SIEMENS, MICHELL, AMETEK, ABB, HOBRE

PROVERS AND MASTER METERS (10 36):


12 SITES

SAMPLING SYSTEMS:
WELKER, JISKOOT
PERFORMANCE MANAGEMENT:
KPIs
HSE

Behavioural

Performance

Innovations

Savings

31
CONTRACT BENEFITS: MANAGEMENT
SYSTEMS

32
CONTRACT BENEFITS: MANAGEMENT
SYSTEMS

33
CONTRACT BENEFITS

Complete bespoke management system and infrastructure


developed and implemented:
Operational infrastructure
Operating systems and procedures
Planning and scheduling tools
Work instructions
Calibration sheets
Mismeasurement management
Audit Management

34
CONCLUSIONS

Ongoing costs of operation and


maintenance of petroleum custody
transfer measurement systems over a 20
year project life can predominate over
initial equipment investment.
It is important to design the equipment for
low ongoing costs. Initial cost may be
higher to do this.
Sophisticated diagnostic systems and
equipment can reduce ongoing costs; for
example condition based maintenance.
CONCLUSIONS

Operation and maintenance of these


systems requires specialists trained on the
large variety of components comprising
the systems with oversight by engineers.
Systematic scheduling of preventive
maintenance and corrective maintenance
can lead to lower maintenance costs.
A sophisticated reporting system enables
greater transparency of total costs and
facilitates decisions to optimize costs.
CUSTODY MEASUREMENT
STANDARDS GLOBALIZATION
INITIATIVE

KHALID A. AL-FADHL
Chairman, Custody Measurement Standards Committee
Saudi Arabian Oil Company (Saudi Aramco)
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

Outlines:
1. Introduction
2. What is Standards Globalization?
3. Benefits of Globalization
4. Saudi Aramco Engineering Standards Structure
5. Globalization Approach and Strategy
6. Custody Measurement Standards Globalization
Initiative
7. Challenges
8. Conclusions
9. Recommendations

Slide # 1
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

1. Introduction

Saudi Aramco Engineering Standards are at the


center of engineering intellectual know-how and
serve as the safety net for building safe, reliable
and cost effective facilities.

Are the standards aligned with International


Standards?
Are they the main reason behind the
exponentially increasing capital projects cost?
or, they need optimization?

Slide # 2
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

2. What is Standards Globalization?

Globalization is a process to enhance the


alignment Saudi Aramco Engineering Standards
with the international or Industry standards.

A result of Benchmarking Exercise conducted in


2007 against regional and International oil
companies and standards organizations such as
GSO, OGP and ISO.

Slide # 3
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

2. What is Standards Globalization? (Conted)

Exercise showed that Saudi Aramco is in the


leading edge in terms of engineering standards
management practices and systems

Chairmen and Subject Matter Experts are required


to revisit the requirements that do not add value
to the design.

Participate in the activities of the international


standards organizations to inject the Saudi Aramco
mandatory requirement to these organizations

Slide # 4
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization
Eliminate special requirements that may
increase project costs

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization
Eliminate special requirements that may
increase project costs
Increase the number of potential suppliers of
material

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization
Eliminate special requirements that may
increase project costs
Increase the number of potential suppliers of
material
Reduce manpower required to maintain
company standards

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization
Eliminate special requirements that may
increase project costs
Increase the number of potential suppliers of
material
Reduce manpower required to maintain
company standards
Help build local industry around international
standards to better compete in the global
market

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

3. Benefits of Globalization
Eliminate special requirements that may
increase project costs
Increase the number of potential suppliers of
material
Reduce manpower required to maintain
company standards
Help build local industry around international
standards to better compete in the global
market
Develop cost estimates more economically.

Slide # 5
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

Board of Engineers chaired by Engineering


Services Chief Engineer bears the responsibility
of the Saudi Aramco Engineering Standards and
Specifications

Slide # 6
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

Slide # 7
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

More than 2300 standards; from which, more


than 1200 are considered mandatory.

Slide # 7
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

More than 2300 standards; from which, more


than 1200 are considered mandatory.

37 standards committees with members of more


than 500 people from 17 different organizations

Slide # 7
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

More than 2300 standards; from which, more


than 1200 are considered mandatory.

37 standards committees with members of more


than 500 people from 17 different organizations

Corporate management systems have been


established to manage the review and approval
process of the engineering standards

Slide # 7
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

4. Saudi Aramco Engineering Standards Structure

Corporate management systems have been


established to manage the review and approval
process of the engineering standards.

Slide # 8
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

Standard Review Model

Slide # 9
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

5. Globalization Approach and Strategy

Slide # 10
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

5. Globalization Approach and Strategy

Developing a snapshot of the current state of


Saudi Aramco standards and conducting Gap
Analysis by Saudi Aramco Subject Matter
Experts each in his discipline.

Slide # 10
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

5. Globalization Approach and Strategy

Developing a snapshot of the current state of


Saudi Aramco standards and conducting Gap
Analysis by Saudi Aramco Subject Matter
Experts each in his discipline.

Performing Value Engineering studies for the


engineering standards.

Slide # 10
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

5. Globalization Approach and Strategy

Developing a snapshot of the current state of


Saudi Aramco standards and conducting Gap
Analysis by Saudi Aramco Subject Matter
Experts each in his discipline.

Performing Value Engineering studies for the


engineering standards.

Participating in International Standards


Development

Slide # 10
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

Slide # 11
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

A. Custody Measurement Engineering Documents:

4 SAEPs (Engineering Procedures)


5 SAESs (Engineering Standards
14 SAMSSs (Material System Specifications)

In addition to Standards Drawings, ISSs, &


Inspection Forms

Slide # 12
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

B. Development and Revision Process of Custody


Measurement Engineering documents

Slide # 13
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

B. Development and Revision Process of Custody


Measurement Engineering documents

C. Gap Analysis
Exception Format is used to develop
documents that have a reference
international document.
Normative Format is used to develop
documents that do not have a reference
international document.

Slide # 13
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

D. Value Engineering Studies:

Three value engineering studies were


performed on most important measurement
documents.

Slide # 14
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

No. of VE Estimated
Document No. of VE
Document Title Date Recommend Cost
No. Proposals
-ations Avoidance ($)
SAES-Y-101 Custody Metering of 14 30 7,400,000
Hydrocarbon Gases
5/9-13/2009
SAES-Y-103 Royalty/Custody Metering of 18 33 30,000,000
Hydrocarbon Liquids
34-SAMSS-119 Bi-directional prover 4 19 816,200

34-SAMSS-120 Uni-directional meter prover 4 6 816,200

34-SAMSS-121 Small Volume Prover 8/2-4/2010 2 33 880,000

34-SAMSS-122 Atmospheric Portable Tank 0 9 0


Prover
34-SAMSS-112 Orifice Meter for Gas Custody 1 8 TBD
Measurement
10/4-5/2011
34-SAMSS-114 Ultrasonic Flow Meter for Gas 2 11 TBD
Custody Measurement

Slide # 15
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

D. Value Engineering Studies:(Cont.ed)

Two value engineering studies are planned to


be performed

Slide # 16
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

Document No. Document Title Date

SAES-Y-501 Dynamic Sampling of Hydrocarbon Liquids for Royalty/Custody


Transfers
34-SAMSS-525 Automatic Sampling Systems for Crude Oil and Refined Products July 2012

34-SAMSS-526 Automatic Sampling Systems for Hydrocarbon Gases

34-SAMSS-841 Flow Computer for Custody Transfer Measurement of


Hydrocarbon Liquids
34-SAMSS-846 Flow Computers for Custody Transfer Measurement of
Hydrocarbon Gases October 2013
34-SAMSS-847 Preset Controller for Truck Loading and Unloading Systems

34-SAMSS-851 Metering Supervisory Computer for Custody Transfer


Measurement of Hydrocarbon Liquids

Slide # 17
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

E. Participation in the International Standards


Organizations:

American Petroleum Institute (API) Petroleum


Measurement subcommittees
(COGFM, COMA, COLM & COMQ)

Slide # 18
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

E. Participation in the International Standards


Organizations:

American Society for Testing and Materials


(ASTM)
Committee D02 on Petroleum Products and
Lubricants

Slide # 19
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

E. Participation in the International Standards


Organizations:

International Organization for Standards


(ISO)
Saudi Standard, Metrology and Quality
Organization (SASO) delegated Saudi Aramco
represented by CMU to review and vote on
the international standards submitted by ISO
TC-28, Petroleum products and lubricants.

Slide # 20
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

6. Custody Measurement Standards Globalization


Initiative:

E. Participation in the International Standards


Organizations:

American Gas Association (AGA)


CMU participates in AGA activities by
reviewing the reports developed in the field
of gas measurement.

Slide # 21
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges:

Slide # 22
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges:

a) Implementation process of the initiative differs


from one discipline to another.

Slide # 22
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges:

a) Implementation process of the initiative differs


from one discipline to another.
b) Involvement of the Subject Matter Experts in the
increasing day-to-day activities.

Slide # 22
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges:

a) Implementation process of the initiative differs


from one discipline to another.
b) Involvement of the Subject Matter Experts in the
increasing day-to-day activities.
c) Standards Cross Referencing

Slide # 22
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges:

a) Implementation process of the initiative differs


from one discipline to another.
b) Involvement of the Subject Matter Experts in the
increasing day-to-day activities.
c) Standards Cross Referencing
d) Shortages in the local and international subject
matter experts

Slide # 22
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges: (Conted)

e) Geographical diversity do not permit attending


International standards organizations working
group meetings

Slide # 23
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges: (Conted)

e) Geographical diversity do not permit attending


International standards organizations working
group meetings
f) Long time for developing and approving the
reference standard document

Slide # 23
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

7. Challenges: (Conted)

e) Geographical diversity do not permit attending


International standards organizations working
group meetings
f) Long time for developing and approving the
reference standard document
g) Marketing SA standards requires referring to
international standards not SA document

Slide # 23
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

8. Conclusion
Saudi Aramco, through Globalization Initiative,
made a significant progress in optimizing the
alignment of its technical requirements with the
international standards.
Some of the Saudi Aramco standards were
adopted by GSO and others were submitted to ISO
for adaptation.

Slide # 24
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

9. Recommendations:

All the necessary resources should be allocated to


implement the Globalization Initiative
requirements such as:

Participation of Subject Matter Experts in the


International Standard Organizations activities.
Conducting Value Engineering Studies

Slide # 25
CUSTODY MEASUREMENT STANDARDS GLOBALIZATION INITIATIVE
_______________________________________________________________

Summary:
1. Introduction
2. What is Standards Globalization?
3. Benefits of Globalization
4. Saudi Aramco Engineering Standards Structure
5. Globalization Approach and Strategy
6. Custody Measurement Standards Globalization
Initiative
7. Challenges
8. Conclusion
9. Recommendations
Questions?
JISKOOTTM QUALITY SYSTEMS

Real-world proving and maintenance of


sampling/quality measurement system
accuracy using international standards

CMTEM Saudi Aramco - Nov 2011


Jon Moreau Cameron Measurement Systems - Jiskoot
Mark Jiskoot Cameron Measurement Systems Jiskoot
Change in the last 20 years?
1990s 2011
How much has your quality measurement changed?
Real world sampling accuracy - topics
International losses
Quantity v- quality measurement
Proving the accuracy of quality measurement
systems
Proving acceptance criteria
The performance of different system designs
Effects on density and OWD measurement
Maintaining system accuracy
EI HMC4 Measurement committee crude oil losses
Potential quality measurement loss > $300m pa @ 0.16%
$500,000,000

$450,000,000

$400,000,000

$350,000,000

$300,000,000

$250,000,000
Losses

$200,000,000

$150,000,000

$100,000,000

$50,000,000

$0
0.000% 0.040% 0.080% 0.120% 0.160% 0.200% 0.240%
Effect of quality measurement on overall accuracy??
Importance of accuracy
Crude oil cargo - 300,000 m3
1cc sample grabs taken, 10,000 per batch
10 litre sample taken to lab for analysis
1 100ml analysed for water - depending on method
Volume analysed can be 1 in 300 BILLION

1 in 300,000,000,000
Sampling standards
34SAMSS 525
SAESY-501

ISO 3171
API 8.2 called by above
IP 6.2 & ASTM 4177
(same as API)

Under the Phoenix agreement


EI and API are being merged and
it will then be balloted to replace
ISO 3171

Will include refined products!


Water injection proving the process
Proving results criteria ISO/IP

Proving to IP or ISO standard


Complies with API, ISO and IP!!
Proving to the API complies on with API
Remember planned unification of ISO and API
Proving results some systems fail!!
Independently certified systems ISO pass
Proving certificates!!!!!
Different sampling system types

Fast loop sampling system CoJetix sampling system


(External mixing needed if required) (Combined mixing and sampling)

In-line (probe based) sampling system


(External mixing needed if required)
Relative accuracy of crude oil sampling systems
1.40%
In line sampling system with poor
mixing
in-line sampling system with compliant
1.20%
mixing
Fast loop sampling system with
compliant mixing
1.00%

EFFECT
0.80%
OF POOR
Accuracy

MIXING

0.60%
ON WATER
CONTENT
MEASUREMENT
0.40%

0.20%

0.00%

Number of water injection tests


Performance of fast loop sampling systems (inc mixing)
Performance of in-line sampling systems (inc mixing)
Density measurement errors
Density measurement configuration bias
Reducing uncertainty and maintaining accuracy
Specify, design, install and commission correctly

Pipeline mixing LARGEST EFFECT ON ACCURACY


Step 1

Representative sampling of the batch


Step 2

Sample handling and mixing


Step 3

Laboratory analysis process


Step 4

Prove the system in accordance with standards


Step 5
Collecting a representative batch sample
Performance Criteria for Permanent Sampling System
Installations
Grab factor
Performance factor
Flow sensor accuracy
Sampling time factor
Loop velocity (fast loops)

Fully automated with the control system monitoring and


controlling the sampler only informing the operator if a
failure occurs
Sample handling and mixing
Reduce the number of steps - Portable receivers
reduce uncertainty

L2)

Fixed receivers with


mixing in the field create a
second L2 step in an
environment outside lab
control
Maintaining system performance
Prove
installed
system by
water
injection

Confirm
Validate and
mixing
ensure
performance
system
v design
reliability
parameters Certified
quality
measurement
system

Validate
Validate
handling,
system
laboratory
performance
process
Summary

1.
Design and
specification
8. 2.
Revalidation Installation
and proving and
as required commission

7. Certified 3.
Confirm accuracy Proving in
operating & accordance
envelope
reduced with
same as
standards
design losses

6. 4.
Validation of Batch
sampling certification
and analysis of
process performance
5.
Maintenance
schedule
So what does your quality measurement look like?
1973 OR - 2011?
Thank You
Questions?

November 2011
BTU Gas Measurements
Challenges & Optimization
Abdulaziz A. Al-Faraj
Saudi Aramco

Copyright 2011, Saudi Aramco. All rights reserved.


Objective

Share with you our experience and challenges


encountered to accurately measure the BTU for
a widely distributed gas network
Outlines
Background

Existing Methods

Challenges

Optimization Methods

Conclusion
Background
Ras Al KhairJubail Royal Commission Pressure : 300 1000 PSIG
The MasterBerri
GasPower
System
Plant consists of:
Jubail Royal Commission Flow : around 4.2 BSCFD in
the Eastern Province
1-KGP
Major gas plant producers
Temperature : 70 150 F
2- ComplexBerri
pipelines network Wusta BTU: 900 1280
Desalination Plant
Berri Junction
3-BGP
Major junction sites Ghazlan Power Plant 1 & 2

Refinery and Fractionation


Juaymah Junction
4- Low pressure distribution system
Azizyiah Desalination Plant
5- Metering skids Dammam/Khobar Area
Qatif Junction Dammam Industrial Plants
SGP,UGP,
HGP, HYGP
Importance of Gas Sampling
Flow On-Line
Computer Analyzer

FT High FCV (A)


FT Low PT TT

SAUDI
ARAMCO CUSTOMER

Class-I
Valve Orifice FCV (B)
Metering Skid Classification
Secondary
20 MM SCFD
Small Gas Metering System
Composite Sampler

Primary
200 MM SCFD Primary 20 MM SCFD
Medium Gas Metering System Online GC
or a representative sample from another GC

Major
> 200 MM SCFD
Large Gas Metering System
Independent Online GC required
SAMPLING METHODS

Automatic (Composite) Sampling Online Sampling


LIMITATIONS

Is Not Based ON Real-time Value


Composite
Sampling

The Process Labor/Time Intensive

Laboratory Dependent
Online Analyzer
LIMITATIONS

High Initial Cost

Need of Highly Skilled Personnel

Requires Carrier & Calibration Gas


Challenges
Challenges
1- Continuously Improve the Accuracy in Determining the
Value of BTU In Order to Reduce Uncertainty
Challenges
2- Improve Efficiency
Challenges
3- Gas Composition Variations
Challenges
4- Enhance Coordination Efforts Amongst Involved Parties in
Determining the BTU Value

Engineering

Maintenance
Operation

Laboratory
Challenges
5- Match BTU With That of Our Customers to Eliminate
Potential Claims

Using different standards

Using different measurement methods

Involvement of different parties


Challenges
5- Special Maintenance Requirements

Periodical PM

Require Special Crew

Supply Carrier & Calibration of


Gas

Secure Resources
Optimization Methods
1- Automate Gas Sampling Processes In Order to Reduce
Manual Activities
Optimization Methods
2- Network Enhancement
Centralized
Location

Gas Composition

BTU
& other Data to BTU
AIT F.C

Costumer A
Update MMBTU at
Local Flow Computer
Costumer A
Sample line

Costumer C

Sales Gas Header Costumer B Costumer D


Update MMBTU for selected flow
computers at the costumers sites
Optimization Methods
3- Continuously Improve Workforce Skills and
Competencies
Optimization Methods

4- Improve Existing Policies and Regulations


Conclusion
Determining the Most Accurate BTU Value is Highly Critical to any
Sales Organizations.

Gas Sampling Method Selection Shall be Based on Achieving Best


BTU Results

Online Gas Chromatographs Are in Most Cases More Cost Effective

Optimization Shall Be Adopted Continuously


Thank You
Custody and Royalty Metering Skids
Operation and Maintenance Challenges

November 21, 2011

Ahmad I. Al-Shaye
Saudi Aramco
NA Pipelines Department
Copyright 2011, Saudi Aramco. All rights reserved.
Outline
System Overview
Our Customers
Duties and Responsibilities
Challenges
Optimization Methods
Conclusion
Overview

Saudi Aramco Pipelines Mission

Transport hydrocarbons throughout


the kingdom safely, reliably and in
an environmentally responsible way
Ras Al-Khair

Jubail

Ras Tanura

Dhahran
Our Customers
Sector # Metering Stations Total #
RC Primary 42
Industries
Sales Gas RC Secondary 20
& Ethane Industries 77
(Custody) Electricity &Water 10
Desalination
Others 5
Crude Oil Refineries 2
(Royalty) Petrochemicals 1 3
The Sales Gas Ring
JUBAIL
KAYAN
SECONDARY
INDUSTRIES
CHEMANOL SEPC 20 Customers
HADEED
ALRAZI

NCP SCP SPC SIPCHEM


JUPC

APPC

Sales Gas Ring


WAHA

Zamil EAP Sahra- SAMAD


KEMYA Tasnee FARABI

Sahra- IBN AL
IBN SINA
SHARQ BAYTAR
PETROKEMYA Maaden EDC

SABIC- IBN ZAHR SAFCO


SASREF SADAF SIPCHEM
The Secondary Ring

GULF
SODA GLASS FIBER MODECOR JANA HASAD
GUARD

BILAD

NAJI
Secondary Ring

INDIPCO

HAMRANI UNI COIL

SFCCL ASLAK LATEX ACICO UGSCL

TAYF JESCO EPTECO


The Ethane Ring

NCP SEPC JUPC KAYAN SHARQ

Ethane Ring

SABIC SIPCHEM
PETROKEMYA KEMYA SADAF
(ABS) Integrated
Typical Metering Station
Flow Computer Bldg.
Central
Dispatch
System

FT High FT Low PT TT FCV (A)


Isolation
Valve
SAUDI ARAMCO CUSTOMER

Flow Meter
FCV (B)
Duties and Responsibilities

General Requirements
Measurements Operations
Metering Skids Maintenance
Customers Issues
Duties and Responsibilities

General Requirements
Operate and Maintain Safely and Reliably
Conduct Regular Audits
Revalidate Lateral Lines
Replace Obsolete Equipment
Duties and Responsibilities
Measurements Operations

Collect Regular Gas/Crude


Oil Samples and Send to
LAB

Conduct Periodical Proving


on Royalty Crude Oil System
Duties and Responsibilities
Measurements Operations

Enter BTU, API, S&W Values


to Generate Delivery Tickets

Collecting The Daily Delivery


Tickets on Weekly Basis

Generate Monthly Gas


Consumption for Billing
Duties and Responsibilities
Metering Skids Maintenance

Instruments Calibrations

Meter Inspection / Diagnosis

Checking Flow Calculations

Perform Software Back up

Stroking the Main Valve Yearly


Duties and Responsibilities
Customers Issues

Measurement Discrepancies

Operational Mode changes

Expansion or Demolition

New Projects
Challenges
Continuously Improve Gas Measurement
Accuracy In Order to Reduce Uncertainty
Challenges
No. of Metering Stations"
90
Cope with Continuous
Growth 80

70

Flexibility 60
Adaptability 50

40

30

2005
2003
2004

2006
2007
2008
2009
2010
2011
Challenges

Special Logistics
Requirements
Scattered and Restricted
Metering Skids
Challenges
Meeting Company and Customers Demands
Continuously Improve Efficiency of Processes
Maintain Optimum Accuracy and Reliability
Optimization Methods
Deploy Advanced Technologies

Automate Manual Activities

Continue to Perform Regular


Audits by Third Party to Raise
Confidence Level
Optimization Tools

Build up Metering Skills and Competencies

Enhance Planning and Coordination with


Customers
Summary
System Overview
Our Customers
Duties and Responsibilities
Challenges
Potential Improvement Methods
Thank you
Areas for Improvement in
Hydrocarbon Liquid Metering Systems
Dr Mohammed Salim
Saudi Aramco

Copyright 2011, Saudi Aramco. All rights reserved.

1
Partnering for results

"Any fool can make things bigger, more complex and


more violent. It takes a touch of genius - and a lot of
courage - to move in the opposite direction."
Albert Einstein, scientist

2
Presentation overview

Presenting the simplest view of hydrocarbon liquid metering systems

Metering system field components

Metering Control System Architecture

System components

Communication

Intelligence

Testing

Training and certification

Summary

3
Metering system field components

Inlet Outlet

4
Metering system field components

5
Metering system field components

Major field problem component

Impacts measurement!

Is there no other way?

6
Metering system field components

Automatic integrity test on double block and bleed valves

Valves limit switches

Wiring between field and control room

7
Metering system field components

Labor intensive and tedious

Can we not improve?

8
Metering control system architecture

MSC A MSC B

NETWORK

FC A FC B PLC

9
Metering control system flow computer

Is technology simplifying this critical component?

Are configuration/programming tools making it simple to use?

Remote I/Os?

All skid valves for meters it can handle?

10
Metering control system PLC

Simple valve control and interlocks

Failure modes

How to reduce wiring between field and control room

11
Metering control system supervisory computer

Intelligence Key areas


Integration
Redundancy
Reports
Alarms
Documentations
Testing
Training & certification

Major concern No major problems


Application

Communication

Operating system

12
Metering control system integration

Experience in custody transfer measurement process

Minimum number of software modules to design system

Standard off-the-shelf SCADA vs in-house packages

Proprietary vs open source code

13
Metering control system redundancy

SCADA off-the-shelf vs programmed

Data synchronization in redundant systems

Failure modes and recovery

14
Metering control system reports

Reports synchronization in a redundant system

Archiving for ease of reviewing

Historical reports archive management

15
Metering control system alarms

Improve alarm segregation e.g. system, process and measurement

Listing all alarms in provided documentation

system wide acknowledgment

16
Metering control system documentation

Documentation should help in removing black box concept

All documentations should be available online on MSC

One detailed document providing A-Z on re-building system from scratch

17
Metering control system testing

Remote I/Os will resolve wiring issues on skid and control panel at FAT

The FAT documents must demonstrate all design requirements

All FAT tests should be at maximum design

18
Metering control system training & certification

Technician training

Engineer training

Do we have certification programs?

19
Metering control system intelligence

Reducing data monitoring updates

Measurement system performance tracking

Meter history and performance tracking

Prover history and performance tracking

20
Metering control system communication

Failure and recovery modes

Standard platform for approved SCADA packages

Intelligent data monitoring

In-Built redundancy

21
Summary

Highlighted areas for improvements

- Metering system field components

- Metering control system architecture

- Components

- Communication

- Intelligence

- Testing

- Training and certification

22
Thank you for listening

Any Questions?

23
An Integral Approach To
Custody Transfer Data Management

Han van Dal


Spirit Innovative Technologies
Statement

With respect to Custody Transfer Data the current


generation of Metering Control Systems is

dumb

inaccurate

time-consuming
Contents

What is Custody Transfer Data?

What can be improved?

Mismeasurement management

Relation to system uncertainty

Case study

Conclusions
Custody Transfer Data

API MPMS 21.1 (Gas) & 21.2 (Liquid)


Quantity Transaction Records
Configuration Logs
HW & SW Versions
Event Logs
Field Test Reports
Corrections with their reason

Why?
To verify correctness of data
To allow for correction of failures
Old situation

Custody Transfer Data = Set of printouts


Current situation

Custody Transfer Data = Set of electronic files


What can be improved?
Metering Control Systems are made for:
Daily operation

and not for:


Technicians
Metering specialists
Auditors
Accounting staff
Purpose #1: Correctness of data

Are all settings correct?


Any changes in settings, SW or HW?
Calibrations performed in time?
Any maintenance applied?
Have measurement failures occurred?
Have tickets been corrected?
If so, how and why?
Purpose #2: Correction of failures

How big is the error (financial value)?


Is correction worth the trouble?
What is the best guess for the failed input?
How to accurately recalculate the ticket?
How to convince the Buyer?
What else can be improved?

Is the overall system accuracy within spec?


Why wasnt the frozen value detected earlier?
How is my meter doing?
Is any transmitter drifting?
Whats the density of water in all flowcomps?
Integral CT Data Management

Relational data (meter tickets & audit trail)


IT (data storage, cyber-security, integrity)
Configuration management (FC, EFM)
Mismeasurement management
Detection
Overview
Correction
Mismeasurement detection

Flow computer alarms

But also: 1.5

Flow meter diagnostics 1

Smart transmitter diagnostics


0.5

QMI diagnostics -0.5

On-line data validation


-1

-1.5

On-line logical checks


Control Charts
CUSUM Charts
Mismeasurement overview

CT data trend

Measurement Alarms
Historical Meter
Ticket Overview .. with
Financial
Correction
Measurement Events
Mismeasurement correction

Best guess for failed input?


What was the correct setting?
How to recalculate the ticket?
How to convince the buyer?
System uncertainty

Metering equipment
Proving
Sampling
Laboratory analysis
Flow computers
Meter ticket recalculation
API MPMS 12.2
Proving (Meter factor)
Sampling (density, BS&W)

Meter ticket correction


Equipment failures
Faulty data entries
Failed field calibrations
Meter Ticket Recalculation
1. BATCH NUMBER 050511
2. TYPE OF LIQUID NG
3. METER CLOSING READING (DATE/TIME) 05/06/11 00:00
4. METER OPENING READING (DATE/TIME) 05/05/11 00:00
5. NET DELIVERY TIME 24.001 hours
6. METER CLOSING READING 23208593 bbl
7. METER OPENING READING 23167330 bbl
8. INDICATED VOLUME 41263 bbl
9. AVERAGE FLOW RATE 1705.4 bbl/h
10. GROSS VOLUME 41258.87 bbl
11. AVERAGE METER FACTOR 1.0001
12. OBSERVED RELATIVE DENSITY 0.0000 M
13. OBSERVED TEMPERATURE 0.0 F M
14. RELATIVE DENSITY AT 60F 0.6646
15. WEIGHTED AVERAGE TEMPERATURE 94.4 F
16. TEMPERATURE CORRECTION FACTOR (CTLm) 0.9732
17. WEIGHTED AVERAGE PRESSURE 317.6 psig
18. PRESSURE CORRECTION FACTOR (CPLm) 1.0044
19. COMBINED CORRECTION FACTOR (CCFm) 0.9775
20. NET STD VOL AT 60F & 14.696 psia (0 psig) 40355.30 bbls
21. NET STD VOL AT 15C & 101.325 kPa (0 kPa (ga)) 6410.843 m3
22. NET WEIGHT 4185.52 long tons
22. NET WEIGHT 4252.70 metric tons
Meter Ticket Recalculation

100000 bbl
65 API60
100000 bbl
76 F
65 API60
75 F 205 psi
GSV 99120 bbl
195 psi
GSV 99180 bbl

Up to 0.01% difference
at stable conditions

API MPMS 12.2


200000 bbl
65 API60
75.5 F
200 psi
GSV 198320 bbl
Meter Ticket Recalculation

Significant difference
at highly fluctuating
conditions

For example

Flow computer
GSV = 37942 bbl

API MPMS 12.2


GSV = 37978 bbl

Up to 0.10%
Meter Ticket Recalculation
1. METER CLOSING READING (DATE/TIME) 05/06/11 00:00
2. METER OPENING READING (DATE/TIME) 05/05/11 00:00
3. NET DELIVERY TIME 24.001 hours
6. METER CLOSING READING 23388.593 MMSCF
7. METER OPENING READING 23167.330 MMSCF
8. TOTAL VOLUME 221.263 MMSCF
11. AVERAGE FLOW RATE 221.012 MMSCFD
12. AVERAGE DIFF PRESSURE 23.12 inch WC
13. AVERAGE TEMPERATURE 113.3 F
17. AVERAGE STATIC PRESSURE 1317.6 psig
18. AVERAGE DENSITY 6.45 lb/SCF

Inaccurate for
Gas
dP flow meters
q (dP x P) FWA dP is useless
Meter Ticket Correction

Case : Temperature fails for 35 minutes

What is the additional uncertainty of the different


correction methods for liquid and gas ?
Meter Ticket Correction

Basic conventional correction method

Optimal conventional correction method


Meter Ticket Correction

New API MPMS Ch21 based correction method

* Patent pending *
Meter Ticket Correction

Correction Liquid Liquid Gas Gas


Turbine Turbine Orifice Orifice
Steady Fluctuating FWA dP TWA dPxP

Basic correction 0.06% 0.83% 3.22% 0.30%

Optimal correction 0.02% 0.14% 3.22% 0.22%

API 21 based cor. 0.00% 0.00% 0.00% 0.00%

Relative to corrected quantity that would have been calculated at 1 sec resolution
Conclusions

Accurate correction is currently NOT possible for


many applications
New API 21 method is accurate for all meter
types, liquid and gas
Automation of Mismeasurement Management
makes systems smart
saves time and resources
avoids disputes with buyer

dumb smart
inaccurate accurate
time-consuming time-saving
Smart, accurate and highly automated
Metering Control Systems
to achieve comprehensive and integral
Custody Transfer Data Management

THANK YOU FOR YOUR ATTENTION

You might also like