Testing & verification of Automatic Transfer Switch (ATS) EMC (Z-105-36)

Substation No: Report No: Date:

Starting Time: ____________ Finishing Time: ____________

Check points before starting: Parameters:


# Ensure the Permission / Approval for shut down Voltage L1-L2
# Preliminary inspection carried out at generator side Voltage L1-L3
# Preliminary inspection carried out at MV Panel side Voltage L2-L3
# Coolant and Oil are at normal level Frequency
# Battery voltage before starting Charging Voltage
Oil Pressure

# Testing & verification of ATS done successfully

Remarks:

Done By: Witnessed By:


Name Name
Company Company

Signature Signature
Z-105-36)
Daily Activity Report - EMC

Report No: Date:

SI No Facility Activity Done Materials used

Remarks:

Performed By: Reviewed By: Verified By:

Name: Name: Name:

Company: Company: Company:

Signature: Signature: Signature: