You are on page 1of 1

Plan Finish 17-Nov-13

Project Trend Analysis Projected Finish 6-Mar-14


JSW-SMS-3-FES Projected Delay (days) 109
120%

100%

80%

60% Plan
Actual

40%

20%

0%

Month Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 jun-13 jul-13 aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14
Plan 0% 7% 17% 24% 37% 45% 52% 62% 64% 65% 67% 76% 90% 98% 99% 99% 100% 100% 100%
Progress 0% 6% 9% 9% 11% 13% 19% 35% 40% 47% 52% 60% 65% 71% 78% 82% 90% 95% 97%
Difficulty (Month) no value 0.4 1.4 2.5 3.6 4.2 4.4 3.5 3.5 2.8 2.5 2.5 3.6 3.8 3.1 2.8 1.7 0.9 0.5

Prepared by PSM
Approved by Mr. Sanjeev Sharma