Perhitungan Data Curah Hujan Pertahun: 1. Mean
Perhitungan Data Curah Hujan Pertahun: 1. Mean
1. Mean
=> Mean CH 2003 = (91,4 +159,9 + 134,5 +79,4 +37,5+ 25,2 +1+ 0+ 0+ 29,5
+95,8 + 271,6)/12
= 77,15 mm
=> Mean CH 2004 = (272,8 +220 +367,5+ 183,2+ 144,5 +94,5 +44 +0 +17+ 0+
52,5 +306,2)/12
= 141,85 mm
=> Mean CH 2005 = (116 +34+ 43 +75+ 38+ 61+ 16+ 0+ 0+ 52+ 61+
255,5)/12
= 62,63 mm
=> Mean CH 2006 = (116 +126+ 125+ 136,5+ 77 +0 +0+ 0+ 0+ 52+ 61+
255,5)/12
= 79,08 mm
=> Mean CH 2007 = " 40+ 290+ 152+ 114 + 53+ 25+ 0+ 0+ 0+ 76+ 0 +0" /12
= 62,50 mm
=> Mean CH 2008 = " 98 +221+ 203+ 77+ 68+ 0+ 0+ 0+ 13+ 165+ 235+ 106" /
12
= 98,83 mm
=> Mean CH 2009 = " 280+ 184+ 59+ 57+ 129+ 0+ 0+ 0+ 0+ 83+ 0+ 0" /12
= 66,00 mm
=> Mean CH 2010 = " 157,7+ 160,4+ 49,3+ 107,7+ 0+ 42+ 53+ 21+ 0+ 0+ 0+
0" /12
= 49,26 mm
= 0 mm
= 32,48 mm
=> Mean CH 2013 = " 307+ 381+ 109+ 115+ 198+ 113+ 51+ 0,1+ 0+ 30+ 86+
145" /12
= 127,925 mm
= 41,275 mm
=> Mean CH 2015 = (207,7+ 144+ 163,3+ 139,6+ 0,5+ 94,5+ 44+ 0+ 17+
118,6+ 37,8+ 364,4)/12
= 41,275 mm
=> Mean CH pertahun = (77,15+ 141,85+ 62,63+ 79,08+ 62,50+ 98,83+ 66,00+
49,26+ 0,00+ 32,48 +127,925+ 41,275+ 110,95)/13
= 141,3681624 mm
2. Range
= 271,6 - 0
= 271,6 mm
= 367,5 - 0
= 367,5 mm
= 255,5 - 0
= 255,5 m
= 225,5 - 0
= 255,5 m
= 290 - 0
= 290 m
= 235- 0
= 235 m
= 280 - 0
= 280 m
= 160,4- 0
= 160,4m
= 0-0
= 0m
=> Range CH 2012 = data max - data min
= 216 - 0
= 216 m
= 381 - 0
= 381 m
= 240,7- 0
= 240,7 m
= 364,4 - 0
= 364,4 m
= 1702,2 - 0
= 1702,2 m
3. Ragam
= 3646,91
Keterangan =
X1 = Nilai Min
X = Nilai rata-rata
xn = nilai max
n = jumlah data
= 5919,95
=>Ragam CH 2005 = ((X1 - X) + (xn - X))/n
= 3426,89
= 3114,75
= 4638,54
= 2359,12
= 4179,33
= 1231,57
= 0,00
= 2894,46
= 6700,9
=> Ragam CH 2014 = ((X1 - X) + (xn - X))/n
= 3456,16
=> Ragam CH 2015 = ((X1 - X) + (xn - X))/n
= 6378,90
= (( 0 - 876,8615) + (1702,2-876,8615)/12
= 7,558744246
4. Median
= 37,5
= 94,5
= 43
= 61
= 25
= 77
= 0
= 21
= 0
=> Median CH 2012= /2 = 12/2 = 6 (Nilai data ke 6)
= 0
= 109
= 0
= 792
5. Simpangan Baku
= (3646,91)
= 60,39 mm
= (5919,95)
= 76,94 mm
= (3426,888021)
= 58,53 mm
= (3114,751157)
= 55,81 mm
= (4638,54 )
= 68,11 mm
= (2359,12)
= 48,57 mm
=> Simpangan Baku CH 2009 =
= (4179,33)
= 64,65 mm
= (1231,57)
= 35,09 mm
= (0)
= 0 mm
= (2894,46)
= 53,80 mm
= (6700,98)
= 81,86 mm
= (3456,16)
= 58,79 mm
= (6378,90)
= 79,87 mm
= (7,558744246)
= 2,749317051 mm
6.Standar Deviasi
=>Standar deviasi CH tahun 2003 = (((())/(1))
= (857105,64))(857105,64)12)/(121)
= 80,58
Keterangan
y = jumlah CH
= ("2897484,8")(2897484,8)12)/(121)
= 148,16
= ((564752,25)(564752,25)12)/(121)
= 65,41
= (900601)-(90060112)/(121)
= 82,60
= (562500) (562500)12)/(121)
= 65,28
= 103,23
= (627264) (62726412)/(121))
= 68,93
= (349399,21) (349399,2112)/(121)
= 51,45
= (0) (012)/(121)
=0
= (151944,04) (151944,0412)/(121)
= 33,93
= (2356532,01) (2356532,0112)/(121)
= 133,61
= (245322,09) (245322,0912)/(121)
= 43,11
= (1772625,96) (1772625,9612)/(121)
= 115,88
= (902373,3378) (902373,337813)/(131)
= 82,68
7. Skewnnes
= ()/
= 0,66
= ()/
= "141,85-94,5" /"76,94"
= 0,62
= ()/
= "62,63-43" /"65,41"
= 0,34
= ()/
= "79,08-61" /"82,60"
= 0,32
= ()/
= "62,50-25" /"82,60"
= 0,32
= ()/
= "98,8377" /"48,57"
= 0,45
= ()/
= 1,0210396
= ()/
= 0,80507267
= ()/
=0
= ()/
= (32,480)/"58,80"
= 0,55238095
=> Skewnnes (SK) CH 2013 = ()/
= ()/
= (127,925109)/"81,86"
= 0,23118739
= ()/
= (41,2750)/("58," 79)
= 0,70207518
= ()/
= (110,95 94,5)/79,868
= 0,206
= ()/
= (141,3681624792)/82,86
= 51,42
8. Kurtosis
= 1025,21
= 1025,21
= 1025,21
= 1025,21
= 1025,21
= 1025,21
= 1025,21
=0
= 1025,21
= 1025,21
= 1025,21
= 1025,21
9. kuartil
= 1 + 0,5 (25,2 - 1)
= 13,1
= Q2 = X6 = 37.5
= 9,75
= 147,2