Tepng Onshore Const Itt Project Quality Plan PDF
Tepng Onshore Const Itt Project Quality Plan PDF
R00 Apr 05, 2017 First Issue For Review Trust.A. Harrison D. Chilaka U.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Table of Contents
0.0 PURPOSE .......................................................................................................................................... 4
1.0 SCOPE ......................................................................................................................................... 4
2.0 REFERENCES ............................................................................................................................. 5
3.0 DEFINITIONS ............................................................................................................................. 5
3.1 SPECIFIC DEFINITIONS .............................................................................................................. 5
Company ................................................................................................................................................. 5
3.2 ABBREVIATIONS ......................................................................................................................... 6
3.3 DISTRIBUTION LIST .................................................................................................................... 7
3.4 PROCEDURE FOR UPDATING CONTENTS OF THIS PROJECT QUALITY PLAN ...................... 7
4.0 STATEMENT OF QUALITY OBJECTIVES / STRATEGY ............................................................ 7
4.1 QUALITY OBJECTIVES ........................................................................................................... 7
4.2 QUALITY STRATEGY ............................................................................................................. 8
5.0 PROJECT QUALITY POLICY STATEMENT...................................................................................... 9
POLICYSTATEMENT .......................................................................................................................... 9
5.1 KEY ELEMENTS OF THE PROJECT QUALITY PLAN ................................................................ 10
6.0 QUALITY CONTROL PROGRAM .................................................................................................... 11
6.1 PROJECT QUALITY CONTROL ORGANIZATION ...................................................................... 11
6.2 PROJECT RESPONSIBILITIES AND AUTHORITIES ................................................................. 11
6.2.1 PROJECT MANAGEMENT RESPONSIBILITIES ................................................................. 11
6.2.2 OBLIGATIONS AND RESPONSIBILITIES OF OTHER INVOLVED GROUPS ..................... 14
6.3 PROJECT RESOURCE MANAGEMENT AND TRAINING........................................................... 14
7.0 PROJECT QUALITY MANAGEMENT SYSTEM AND QUALITY PLANNING ................................. 14
7.1 PROJECT QUALITY MANAGEMENT SYSTEM .......................................................................... 14
7.1.1. QUALITATIVE ASSESSMENT ............................................................................................ 14
7.1.2. RELATIONSHIPS BETWEEN MANAGEMENT SYSTEM AND PROJECT QUALITY PLAN
...................................................................................................................................................... 15
7.2 INTERFACE MANAGEMENT ..................................................................................................... 15
7.3 CHANGE MANAGEMENT .......................................................................................................... 16
7.4 MANAGEMENT REVIEW ........................................................................................................... 16
7.5 QUALITY AUDITS ...................................................................................................................... 16
8.0 SUBMITTALS ................................................................................................................................. 17
8.1 FILING OF SUBMITTALS ........................................................................................................... 17
8.2 SUBMITTAL REGISTER ............................................................................................................. 17
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
8.3 QUALITY CONTROL MANAGER REVIEW AND APPROVAL.................................................... 17
9.0 INSPECTION SYSTEM.................................................................................................................... 17
9.1 PREPARATORY INSPECTIONS ................................................................................................. 18
9.2 INITIAL INSPECTIONS .............................................................................................................. 18
9.3 FOLLOW-UP INSPECTIONS ...................................................................................................... 19
9.4 Documentation and Control ..................................................................................................... 19
9.5 COMPLETION INSPECTION ...................................................................................................... 19
9.5.1 PUNCH-OUT INSPECTION: ................................................................................................ 19
9.5.2 PRE-FINAL INSPECTION.................................................................................................... 19
9.5.3 FINAL ACCEPTANCE INSPECTION ................................................................................... 20
10.0 TESTING ....................................................................................................................................... 20
11.0 DOCUMENTS AND RECORDS.................................................................................................. 20
11.1 DOCUMENT IDENTIFICATION ............................................................................................... 20
11.1.1 DOCUMENT NUMBERING ............................................................................................... 20
11.1.2 DOCUMENT STAMPS ....................................................................................................... 24
11.2 (DESIGN) DOCUMENTS .......................................................................................................... 25
11.3 MATERIALS AND EQUIPMENT CERTIFICATION ................................................................. 26
11.4 DATA SHEETS .......................................................................................................................... 26
11.5 EQUIPMENT DRAWINGS ........................................................................................................ 26
12.0 CONTROL OF NONCONFORMANCES ..................................................................................... 26
12.1 REWORK PROCEDURES ......................................................................................................... 26
13.0 DOCUMENTATION ...................................................................................................................... 27
14.0 WORKMANSHIP .......................................................................................................................... 28
15.0 QUALITY ACTIVITIES / MATRIX ................................................................................................ 29
16.0 ATTACHMENTS ........................................................................................................................... 33
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
0.0 PURPOSE
The purpose of this project quality plan is to define the structure and content for Project and Quality
Management to be used by Bridgsite Nigeria Limited in order to meet project specific requirements
for Onshore Routine Construction and Installation Frame Contract.
This project quality plan is designed to achieve the following objectives:
Define responsibilities and general principles for managing the relationships between
Bridgsite Nigeria Limited, Client (TEPNG), and Bridgsite suppliers (internal or external) to
projects of equipment, services, consultancy.
Set a basis for quality assessments of the procedures employed by Bridgsite Nigeria
Limited to fulfil their contractual obligations to TEPNG.
This project quality plan logically displays quality actions and activities necessary to achieve a specific
level of quality. The performance of work in coating, fabrication and installation will be controlled by
specific procedures collected in construction procedures. These procedures will be specifically
adopted for this project and approved by CLIENT Project Engineer. They will give clear, complete and
up to date document instructions. The assigned QA Engineer supported by the General Manager,
Project Manager and the Construction Manager will prepare above mentioned procedures.
1.0 SCOPE
The scope of work to be carried out under this CONTRACT include all WORK specified in this section
in conformity with the applicable drawings, guidelines and scope of works described or/and presented
for on job request by CLIENT.
2.0 REFERENCES
ISO 9001:2008. Quality Management System Requirements
ISO 10005:2005 Quality Management Systems Guidelines for Quality Plans;
Total General Specifications 2014 Edition
Total General Specifications referenced codes and standards
3.0 DEFINITIONS
3.1 SPECIFIC DEFINITIONS
Contractors, Sub - Contractors or Suppliers Any commercial entity contracted directly either
by BRIDGSITE NIGERIA LTD or by the Client to carry
out part of the work activities.
Personnel on the distribution list will receive the update of the Project Quality Plan. In case of change
of the contents, complete page(s) will be distributed. The pages will be send undercover of a
transmittal, on which instruction concerning updating are specified. The recipient will return a signed
copy of the transmittal. The Quality Engineer is responsible for the distribution and filing of these
updates.
These Quality Objectives will support the specific Project Objectives of:
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
The objective of QA/QC of BRIDGSITE is to provide quality services in a manner that conforms
to Contractual and Regulatory Requirements, using qualified, trained and experienced
personnel.
To fulfill the above objectives, BRIDGSITE has decided to adopt the "QUALITY MANAGEMENT
SYSTEM" as outlined in this manual.
The Quality Assurance / Quality Control (QA/QC) Manager has the full support of BRIDGSITEs
Management to implement the measures outlined in the "QUALITY MANUAL" and in specific
Projects Quality Plans.
The QAlQC Department acts independently from other departments with the QAlQC Manager
as the head and reporting directly to the top management of BRIDGSITE
Therefore, it is mandatory for all BRIDGSITE personnel to adhere' strictly to the Quality
requirements as outlined in the Quality Manual and other related Quality Procedures and
Plans.
CHILAKA UGORJI
Managing Director
05/01/2017
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Quality Management and Responsibilities Bridgsite Nigeria Limited fully integrates its quality
management system into the organizational structure and performance management systems for
each project. We:
Maintain a documented quality system consisting of a quality manual with policies and
procedures.
Tightly control exceptions to the quality system so company standards are applied uniformly
to every project.
Systematically maintains quality system documents and records.
Quality Control Personnel - Bridgsite Nigeria Limited fully integrates its quality management system
into the organizational structure and performance management systems for each project. We:
Appoint a Quality Manager, Superintendent, and Project Manager to each project, each with
well-defined quality responsibilities and the authority to carry them out.
Have well-defined quality responsibilities for every employee with specific quality
responsibilities for key job positions.
Plan project quality records and documentation that will be maintained.
Tightly control exceptions to the quality system so company standards are applied uniformly
to every project.
Enforce policies that monitor work conditions before and during work so that quality results
are assured.
Project Quality Coordination and Communication Bridgsite Nigeria Limited tightly controls the
construction process to ensure quality results. We:
Quality Assurance Surveillance Bridgsite Nigeria Limited audits the quality system to assure it is
operating effectively. We:
Schedule monthly, quarterly and annual audit dates in the project plan depending on the
project progress.
Appoint the Quality Manager, QA Staff and Project team to confirm that the quality control
framework is appropriate and being properly implemented.
Ensure timely reviews of the results of any audit conducted on a project activity.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
FIGURE 1.1, BRIDGSITE PROJECT QUALITY CONTROL ORGANIZATION CHART, presents the QC organization for
the performance and support of remedial action at site, including the lines of authority and interface
with other members of the project team. Each member of the project team, including subcontractors,
shall be responsible for the quality of their work. The duties and responsibilities of the project QC
organization are described in this section.
Responsibilities
The Construction Manager is responsible for ensuring that all aspects of the construction
works are carried out in accordance with the contract documents within budget and schedule.
The Construction Manager will also ensure that all construction works are carried out in
accordance with current environmental and Health & Safety legislation.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
The Construction Manager reports to the Managing Director and will liaise on an on-going
basis with all other Project Team staff members and Client Representative to ensure the
requirements of the Contract are being fulfilled.
Prior to award of any procurement package related to third-party construction/installation,
the Construction Manager will assess the bidders competency to perform the Work.
The actual supervision of construction activities on site shall be managed by the Project
Manager who acts as the Site Manager and shall report to the Construction Manager.
Responsibilities
The Project Manager is responsible to ensure that all activities are performed in accordance
with the approved procedures, applicable Drawings and Specifications.
The Project Manager is responsible for establishing a planning, forecasting and reporting
system for the overall project. The main tool for achieving these objectives would be through
regular review, updating of forecasts and regular reporting of the monitored activities.
The Project Manager and his staff of Superintendents will be responsible for ensuring
protection to permanent works. Any completed or permanent works are suitably protected
from potential damage until the Project hand-over is complete.
The Project Manager reviews regularly and causes to be maintained all site diaries of the
appropriate supervisory staff, including Superintendents and Construction Representatives,
to record overall progress on the construction of the works.
Approves the following Project Plans: Project Execution, HS&E and Quality
Responsibilities
The QAQC Manager is responsible for coordinating all project testing, inspections and
reporting matters directly to the Construction Manager.
The QAQC Manager has the authority to intercede directly and stop unsatisfactory work and
control further processing, delivery or installation of non-conforming material.
Preparation, approval and implementation of the Project Quality Plan
Verification of supplied and procured materials as per project plans and specifications
Development of means and methods to store and protect materials
Reviewing and Developing supporting quality control procedures
Maintain documentation of inspection status of materials
Maintain documentation for material and administrative approvals
Ensure that all materials and construction are in accordance with the requirements for the
completeness, accuracy and constructability in accordance with applicable building codes
Carry out and participate in weekly progress and QC meetings
Maintain documentation of inspection of work executed by subcontractors
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
PROCUREMENT / PURCHASING MANAGER: (Key Personnel)
Responsibilities
The Procurement Manager is responsible for procuring qualified Consultants, Vendors and
Subcontractors for the procurement packages required for the Works.
The Procurement Manager shall also be responsible for preparing the list of proposed bidders
for each package and to manage the regular evaluation of Consultants, Vendors and
Subcontractors performance for future use.
The Procurement Manager shall ensure that all clarification of queries for packages during
procurement is processed through the procurement department. Prior to award of any
procurement package, the Procurement Manager is responsible for assessing the bid, along
with the Construction Manager and Quality Assurance Manager. He shall then provide this
information to the General Manager for review and final approval.
After award of the procurement package, the Procurement Manager shall prepare all
documentation for issue to Design and/or Construction Management and to
Consultant/Vendor/Subcontractor.
Responsibilities
The Health and Safety Manager shall monitor the Project Health and Safety Plan. The Health
and Safety Manager shall ensure that all elements of the works comply with the current Health
and Safety Plan, laws, and regulations and shall promote the principals and objectives for
managing Health and Safety in relation to the work being performed during each stage of
production.
The Health and Safety Manager shall provide training, ensure compliance with statutory
requirements and give appropriate advice to management.
The Health and Safety Manager shall monitor health and safety performance and standards
on the project.
The Health and Safety Manager shall be available for inspections conducted by regulatory
agencies, governmental entities, and the Developer.
The Health and Safety Manager shall liaise with all personnel including subcontractors and
suppliers to perform the following duties:
Plan and review specific work-risk assessments
Address work permitting requirements
Emergency Planning/First Aid Measures
Incident reporting
Responsibilities
Oversight and verification that the project is being conducted in accordance with applicable
quality criteria, as specified in the contract documents, federal, state, or local requirements.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
QA staff will perform the monitoring, inspection, and testing activities of this Quality Plan as
directed by the QAQC Manager.
Provide documentation and access to specialist information. Members of expert groups and
technical committees have to provide all documentation and information necessary for the
project within acceptable time-scale.
Ensure attendance at meetings to provide expert input. Members of expert groups and
technical committees have to be available to attend those meetings that require their
presence in furthering the projects progress.
The Project Manager is responsible for verifying that all project personnel are properly trained,
qualified, and where required, certified to the appropriate level for the work being performed.
Training records will be maintained in accordance with project records requirements to establish and
document the training requirements for project and management personnel.
When required, the qualifications and certifications of the QAQC Manager and subcontractor
personnel will be submitted to Client for review and acceptance prior to the performance of any
functions by an individual. The submittal of a subcontractors qualifications will be required only in
the instance when the subcontractor is solely responsible for QC. The ultimate responsibility for QC
resides with the Contractor.
The framework of the Project Quality Management System will align itself as appropriate with the
requirements of ISO 9001:2008. Within this framework the projects selection process for Sub-
contractors, Suppliers and Services requires that they have an effective quality management system
in place. They will also be required to meet the requirements of ISO 9001:2008.
The QMS to be implemented by the Project is intended to identify the processes that control and
improve the standard of work. The system is documented and consists of plans, processes and
procedures, all of which are utilized to control, record and demonstrate that specific requirements
have been met.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
7.1.2. RELATIONSHIPS BETWEEN MANAGEMENT SYSTEM AND PROJECT QUALITY PLAN
The Project Quality Management System is a suite of strategies, plans and procedures that provide a
systematic way of working at all levels to ensure that all activities are suitably managed to achieve the
Project objectives. The Plan describes how, using the QMS, the Project management will:
Define the quality policy and commitments and the overall Project objectives,
Communicate the necessary responsibilities and authorities,
Review how well the QMS is working and communicate its effectiveness,
Demonstrate management buy-in and commitment.
The Project Quality Plan also describes how the Project organization will:
Identify the processes and the application of processes to achieve the project objectives,
Indicate the sequence and interaction of the processes,
Define how these processes are operated and controlled,
Ensure that resources are available to implement the processes,
Implement continuous improvement, including monitoring, measurement, analysis and
improvement processes.
All work performed by the project team in the implementation of the Project activities shall be in
accordance with the QMS.
identify all interfaces and nominate an individual in the project team to be responsible for
each;
set up the interface by preparing annotated or special drawings, defining the party responsible
for providing each item of information and agreeing a schedule for its provision;
control the interface by expediting information, recording agreed data, adjudicating in the
case of a need to change agreed details and sponsoring changes through the project Change
Control system if there are technical integrity/cost/schedule implications, maintaining the
master copy of all interface data sheets, drawings etc.
Disciplines; - structures;
Sub-contractors; - modules;
Operations; - projects.
A Document Distribution Matrix is to be prepared early in the project, to ensure that drawings,
specifications etc. are distributed to the correct people as they are prepared for review and, if
necessary, approval. This ensures that interfacing disciplines receive the necessary information in time
for proper review and prevents operational staff from being confronted with batches of drawings or
completed designs at a late stage in the project.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Changes on the Project Management Level affecting goals and scope of the project (e.g.
requirements, budget, release date etc.)
Changes on the Execution Layer not affecting goals and scope of the project (e.g. design, code,
etc.)
Typically a special Change Control Board comprising of stakeholder members in the project team is
established for each level of changes. However the same change procedure can be applied to both
levels.
Change requests are used to track changes to baselines. Any stakeholder can submit change requests.
Change requests can describe identified defects or demands to change goals and scope of the project.
The authorized Change Control Board has to accept a change request before work on it is initiated,
and also accept all resulting changes before a new baseline is created. Approved changes are
communicated directly after the Change Control Board decision to the affected stakeholders and in
the project meetings to the whole development team.
The results of the Management Reviews will be fed back into the continuous improvement process.
The objective of the audits will be to establish compliance and measure the effectiveness of the
management systems, procedures and quality assurance activities implemented by the Company,
Project Team and the Sub-Contractors. Project team participation will be utilized as appropriate.
The QA/QC Manager will hold the latest revision of the audit and review plan.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Audit requirements will be identified, executed, reported and tracked in accordance with the Project
Audit Procedure. Audit action items will be entered into an action tracking register for follow up and
completion.
8.0 SUBMITTALS
All submittals are scheduled, reviewed, certified and managed to include submittals from
subcontractors, offsite fabricators, suppliers, purchasing agents, designers, consultants and engineers.
All submittals shall be reviewed, certified and managed by the Quality Control Manager. Copies of the
manufacturers data (material, equipment, etc.), including catalogue cut-sheets showing dimensions,
performance characteristics, capacities, wiring diagrams, schedules, operation and maintenance
manuals and any other relevant information are reviewed by the QA/QC Manager. The QA/QC
Manager is an authorized submittal reviewer and testing lab report reviewer. One (1) copy of the
submittal remains with the Contractor and one (1) copy is retained by Companys Document Control.
Incoming materials are inspected by QA/QC Inspectors to ensure they meet requirements before use
and as a means of monitoring on-going Supplier quality.
Inspection consists of Preparatory, Initial and Follow-up Inspections and applicable records for each
Inspection.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Review requirements for quality control and/or performance testing during this phase of
work. Emphasize testing methods and frequency. Establish who will be doing the testing and
verify that testing personnel will be present as needed.
Review the contract drawings and specifications for this phase of work in detail. Discuss the
construction procedures, tolerances, workmanship standards and repetitive deficiencies.
Review the requirement for special items and verify all samples have been submitted and
approved.
Verify all mobile construction equipment has been inspected for safety.
Verify all preliminary work required to start this phase of construction has been completed
and the work to be built upon has no deficiencies.
Verify all required materials and equipment are onsite, as specified, submitted and approved
and properly stored.
Verify all required submittals have been approved (review them as required).
Verify MSDS for all material to be used are readily available on the jobsite.
Record The Results Of This Inspection On Separate Sheets And Attach Them To The Daily Report.
Record the exact location where the initial inspection was held for future reference and
comparison during follow-up inspections.
Review the records of the preparatory inspection and verify that all action items have been
completed.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Verify all required quality control inspections and test are being performed.
Verify that the work being performed is in full compliance with contract requirements,
including acceptable level of workmanship. Compare with approved samples as appropriate.
Record The Results Of This Inspection On Separate Sheets And Attach Them To The Daily Report.
Records of the Follow-up Inspection will be submitted to the Client/Inspector not more than
one (1) working day after the inspection.
Review Noncompliance Tracking Log and ensure all deficiencies have been corrected or are
being scheduled for corrective action.
All reports for inspection and applicable records will be electronically maintained by the
Construction Superintendent in a document management program.
Inspections will be conducted, controlled and tracked for each definable feature of work and
sub-element identified herein using a project management program.
10.0 TESTING
The Testing Plan for this project is as follows:
Test reports will be attached to the Daily Report by the QA/QC Manager
Test reports will include the date, time and type of test to be performed, test name,
specification paragraph requiring testing, feature of work to be tested, test frequency and
person responsible for each test. (Laboratory facilities will be approved by the Purchasing.)
The QA/QC Manager will notify the Client/Inspector twenty-four (24) hours in advance of any
scheduled test.
Control, verification and acceptance testing procedures for each specific test will include the test
name, specification paragraph requiring test, feature of work to be tested, test frequency and person
responsible for each test. Client-directed laboratory facilities will be used when specified by Contract.
Project Title:
Contract No.
XXXXXXXXXXXXXXX
Each document for the project will be identified with a unique identification, the format is as
follows:
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
For Project Specific Procedures / Documents
BNL-A(B)-ZYYY(i)(I)(f)(t)
A - Correspondent company
A Administration
L Logistics
J Project Services
C Construction
M Material
QM QA/QC
HSE HSES
MT Maintenance
YYY in ZYYY represents serial No.: 001, 002, 003 --- etc.
i: internal memos
l: Letters
f: Fax messages
t: Transmittal
XX KK H NNN
H: Discipline Code
The designation is represented by two or more letters to define the main type of document as
follows:
CODE DOCUMENT
AA Procedure
AC Calculations
AE Equipment List
AS Engineering Schedule
BL Bid List
BM Bill of Material
CS Construction Schedule
DR Document Register
DW Drawing
EC Cost Estimate
MA Manuals
MO Monthly Report
OR Organization chart
PE Purchase enquiry
PL Plans
PO Purchase order
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
RA Audit Report including Technical Audits,
Design Review, Safety Review & HAZOP
Report
RC Conceptual Report
RD Design Report
RF Feasibility Report
RP Progress Report
RX Inspection Report
SC Sub-Contract (Tender
Documents)
SD Design Specification
SE Standard form
SK Sketches
ST Study/ Philosophy
TN Technical Notes
TR Technical Reports
VL Vendor document
(Requirements) List
EL Equipment Log
Discipline Code
CODE DISCIPLINE
D Drilling
E Electrical
F Project services
G Project general
H HVAC
J Instrumentation (including
K Pipelines
L Piping
M Mechanical
N Construction
P Process
R Rotating Machinery
S Civil/ Structural
T Telecommunications
U Commissioning
X HSES
All stamps are provided with date and space for signature
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
1. FOR INFORMATION ONLY: This will be used on documents which contain no crucial but
additional information. Documents with this stamp have no jurisdiction whatsoever
2. FOR COMMENT: Documents with this stamp are submitted to the CLIENT project Engineer
for comment, on return the comments will be processed.
3. FOR APPROVAL: After processing the comments the documents will be submitted for
approval. The outgoing documents carry the FOR APPROVAL stamp.
4. APPROVED FOR CONSTRUCTION: After implementation of the comments of design review,
the document will be submitted to the CLIENT Project Engineer for approval for
construction. The outgoing documents carry the stamp; APPROVED FOR CONSTRUCTION
only documents which are approved by CLIENT Project Engineer will be used for
construction purposes.
5. AS-BUILT: After construction, the approved for construction documents will be adapted to
the actual construction data. After adapting and approved by CLIENT Project Engineer, this
documents will be stamped AS BUILT. The submission of the number of electronic and
hard copies of the AS-BUILT package to the CLIENT Project Engineer shall be as per contract
requirements.
6. MASTER: For internal use, set of master documents of the CLIENT Approved for
Construction package will be compiled: The documents (Drawing, Procedures etc.) carry the
stamp MASTER. All changes which are necessary to adapt CLIENTS standard Design
drawings to site-specifics will be marked up on the master documents.
7. VOID: Documents will be void when they are either replaced by later revision or when they
are rejected by the CLIENT Project Engineer or Bridgsite, completely. All documents which
are no longer valid, will be mark with the stamp VOID and signed by CLIENT Project
Engineer, and will not be used any more for extracting information to all concerned.
Project name
Contract No.
Document number
Title
Dimension
Scale
Draftsmans name
Revision / approval
The design documents will be distributed to all concern. The receiver of such documents is
responsible for appropriate filling, storing, and treatment of the documents. The Project Manager is
responsible for recording a distribution list. He is also responsible for temporary distribution.
For external distribution, the drawings will be done by the CLIENT Project Engineer, however the
internal checking of correctness before submitting to the CLIENT Project Engineer will be done by a
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
person other than the draftsman, with at least the same experience and level of education as the
draftsman.
The drawing will be stamped issued for comment and will be signed for checking by the project
manager or the head engineering. The same procedure shall be followed for up-dating.
Only documents which are Approved for Construction will be used for construction purposes. The
BNL project manager and the CLIENT Project Engineer are releasing the documents.
A narrative will be provided describing the construction deficiency, its proposed corrective action,
time frame for correction, required testing and follow-up inspections to be taken.
The construction deficiency will be noted on the Daily Report and tracked daily until corrective action
has been completed. The QA/QC Manager will insure corrective action is accomplished according to
the contract Plans and Specifications with approval of the Construction Manager.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
The Noncompliance Program will be maintained throughout the life of the project. Copies of all
noncompliance reports will be available for review by the Client/Inspector as well as any
Subcontractor involved in the deficiency.
The Noncompliance Log will be updated monthly or as requested by the Construction Manager.
13.0 DOCUMENTATION
Procedure
All submittals of records will be maintained at the job site field office.
Test Reports will be attached to the Daily Report as they are received by the QA/QC Manager.
The QA/QC Manager will submit all Inspection Reports not more than one (1) working day after each
inspection.
As-Built Drawings
Daily Report
Modifications
Safety Plan
Submittal Data
14.0 WORKMANSHIP
The Company plans and carries out construction activities that include workmanship requirements
for:
Construction work instructions or procedures that identify all necessary work steps
(flowcharts, travelers, tickets).
Designation of unapproved equipment, utilities and supplies with proper signage to prevent
use.
Documented work instructions where the lack of such instructions would affect conformity to
requirements.
Engineering documents for all construction characteristics (drawings, part lists, materials and
specifications)
16.0 ATTACHMENTS
Report Number: Page 1 of 2
QUALITY CONTROL REPORT (QCR)
WEEKLY LOG OF CONSTRUCTION Date:
Contractor: Weather:
4 Activities in process:
Response:
5 General comments:
Response:
7 Prep/Initial Dates (Preparatory and initial dates held and advance notice)
Response:
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Activity Start/Finish:
QC Requirements:
Contractors/Visitors on Site:
On behalf of the contractor, I certify that this report is complete and correct and all
Contractor
equipment and material used and work performed during this reporting period are in
Certification compliance with the contract, plans and specifications, to the best of my knowledge, except
as noted above.
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Non-Conformance Report
<Project Name> <Project Number>
Non-Conforming Condition:
Disposition:
Completed by Accepted by
Item
Description Construction Quality Control
No.
(Sign/Date) (Sign/Date)
ONSHORE ROUTINE CONSTRUCTION AND INSTALLATION FRAME
CONTRACT
16333495/ECP/17
Attendees
Client Contractor Subcontractors Other
Review submittals and/or submittal register. Have all submittals been approved? YES NO
If no, what items have not been submitted?
Check approved submittals against delivered material. (This should be done as material arrives)
Comments:
When required?
Worksheets:
WORKSHEETS