All instrument device need to be zeroing in duration has been set to maintain its accuracy and precision.

Figure 1 : Zeroing Transmitter


Power Test

Rosemount Transmitter

Hart Communicator

STUDENT INDUSTRIAL PROJECT REPORT


MUHAMMAD FAIRUZ BIN ZAILI 19169
PROCEDURE TO ZEROING TRANSMITTER
1. Fisrtly, open equalizer (Green).
2. Wait a few seconds to make sure the reading is stable/constant.
3. Close isolate (Blue)
4. Then connect the Hart Communicator to the transmitter like Figure 1.
5. On Hart Communicator, select Communicator, Hart, Supply : Off,
04XXXXXXXXXX (Device KKS CODE), Online, Configure, Guided Setup,
Zero.
6. Normalize all and observe the reading of transmitter