Title Procedure for CW Pump Startup & Changeover
1. OBJECTIVE
To standardize the procedure for CW Pump Startup &
changeover in 1x76MW CDQ Power plant.
1.1 FUNCTION/PURPOSE
2. SCOPE
3. RESPONSIBILITY
Shift in charge
Desk engineer
Field engineer
4. PROCEDURE
TECHNICAL DATA
Installed: 3nos
Working: 2no-running & 1no-standby
Capacity: 7200CMH
Head : 20 mtr
Motor capacity: 550 kw
Motor Speed: 741 rpm
Full load current: 63 Amps
Volts : 6.6 kv
Page 1 of 6
Projects Limited, Vijayanagar Works, P.O Vidyanagar, Toranagallu,,
Dist. Bellary.
D.C.N CDQ ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
PP-TG OPRN- 14001 : 2004 (4.4.7) / BS OHSAS Rev. No. - Date
SOP-3 18001 : 2007 (4.4.7) 1/1 16/09/2014
Title Procedure for CW Pump Startup & Changeover
ANNEXURE-1
ANNEXURE 2
4.2.1 Log and monitor the datas in log book-Field/Control room &
ensure that
Parameters are within norms as per given in annexure-1.
4.2.2 Check any abnormalities in local and inform shift in-charge for
trouble shooting.
4.2.3 During change over if discharge valve of started pump is not
Page 2 of 6
Projects Limited, Vijayanagar Works, P.O Vidyanagar, Toranagallu,,
Dist. Bellary.
D.C.N CDQ ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
PP-TG OPRN- 14001 : 2004 (4.4.7) / BS OHSAS Rev. No. - Date
SOP-3 18001 : 2007 (4.4.7) 1/1 16/09/2014
Title Procedure for CW Pump Startup & Changeover
ANNEXURE 3
Startup Procedure
Page 3 of 6
Projects Limited, Vijayanagar Works, P.O Vidyanagar, Toranagallu,,
Dist. Bellary.
D.C.N CDQ ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
PP-TG OPRN- 14001 : 2004 (4.4.7) / BS OHSAS Rev. No. - Date
SOP-3 18001 : 2007 (4.4.7) 1/1 16/09/2014
Title Procedure for CW Pump Startup & Changeover
ANNEXURE 4
4.5.1 Ensure local and DCS checks before starting the pump.
4.5.2 Start the standby pump & ensure discharge valve MOV is
opening in auto.
4.5.3 Ensure discharge pressure is adequate (2.1 to 2.4 KSC), if not
adjust riser valve to
Maintain pump discharge pressure.
4.5.4 Ensure that vibration & current is normal.
4.5.5 Stop the running pump & keep in auto standby.
4.5.6 Ensure discharge MOV is closing after stopping the pump.
ANNEXURE 5
4.6.1 Ensure the standby pump mode selection to be made non stand
by.
4.6.2 Pump suction MIV & discharge MOV to be closed 100%.
4.6.3 CW Pump 6.6KV circuit breaker to be rack-out & Control power
supply made off.
4.6.4 Discharge MOV module to be made off.
4.6.5 Motor EPB to be pressed.
Page 4 of 6
Projects Limited, Vijayanagar Works, P.O Vidyanagar, Toranagallu,,
Dist. Bellary.
D.C.N CDQ ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
PP-TG OPRN- 14001 : 2004 (4.4.7) / BS OHSAS Rev. No. - Date
SOP-3 18001 : 2007 (4.4.7) 1/1 16/09/2014
Title Procedure for CW Pump Startup & Changeover
5. SAFETY MEASURES
6. REFERENCE DOCUMENTS
6.1 PID Name & No: Condenser & Auxiliary cooling water system &
TCE.6186A-613-FD-
1046 R0
6.2 Control room & Field engineer log book.
Page 5 of 6
Projects Limited, Vijayanagar Works, P.O Vidyanagar, Toranagallu,,
Dist. Bellary.
D.C.N CDQ ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
PP-TG OPRN- 14001 : 2004 (4.4.7) / BS OHSAS Rev. No. - Date
SOP-3 18001 : 2007 (4.4.7) 1/1 16/09/2014
Title Procedure for CW Pump Startup & Changeover
Page 6 of 6