DISTANCE PROTECTION
DISTANCE PROTECTION Vk = If (1+X/R)(Rct +2Rl+Rb) FOR PHASE TO EARTH
FAULTS.
FAULTS.
Rb = relay burden
CT Vk CALCULATION FOR A 100KM LONG 220KV LINE.(Distance Proection)
A B
BUS FAULT LEVEL AT END A = 2000MVA (ASSUMED)
220*10/3*56.2 =2260 A
CT Ratio= 600/1Amp.
= 3.77(1+5) (Rct+0.5*2+0)
= 3.77*6 (Rct+1)
The required knee point voltage must be calculated for the three phase
fault current at the zone-1 reach and also for the earth fault current at the
zone-1 reach. The higher of the two calculated knee point voltages is
used.