You are on page 1of 6

feature

Debottlenecking and
Optimisation of Oil and
Gas Facilities
by En. Mustafa bin Mahmood and Mr. Youxin Chng

The HYSYS process simulation are based on limited initial well test the original design cases, such as ad-
program is an established oil and gas data). The variations in operating data ditional production from satellite tie-
industry software used for generating compared with the initial design data ins which were not considered during
heat and mass (H&M) balances and may be: the design phase, will then impact the
performing process simulations of higher or lower gas oil ratio existing facilities and potentially cre-
various offshore facilities. Using the (GOR) ate bottlenecks in the production sys-
data from the H&M balances (and higher or lower operating tems which limit production or limit
properties from the process streams), pressures/temperatures/oil or increasing production.
designs for facilities are developed gas flowrates Identifying the bottlenecks can be
from conceptual phase engineering higher watercuts and produced a problem since, normally, a number
to Front End Engineering Design water rates of bottlenecks need to be addressed at
(FEED). changes in compositions, wax, the same time and then prioritised for
More often than not, the design data asphaltenes content, pour point, a particular production case. For ex-
used in the engineering phase differs gel point, etc. ample, a higher GOR would result in
significantly from actual operating contaminants difficult to identify more gas production than originally
conditions for offshore facilities. This from well tests, i.e. H2S content, designed for, assuming the design oil
may be due to a number of reasons, mercury, other trace metals rate is to be maintained. Therefore, the
but mostly due to the oil or gas capacities of the gas processing equip-
reservoir not behaving as predicted The aforementioned variations to de- ment would need to be checked and
(since reservoir behaviour predictions sign data or even planned changes to this could include compressors, heat

Demand (Required Capacity)


Utilisation Factor = x 100%
Capacity (Equipment Design Capacity)

Figure 1: Meascap modelling structure

18 Jurutera March 2009


feature

exchangers, separators, dehydration items has often been a task designated cility that has 15 pieces of equipment
units, control valves (PCVs) and other to process engineers. During the design and the operator wishes to consider
equipment depending on the com- phase, the capacity of equipment items the implications of two different GORs
plexity of the gas processing system. is determined and specified in process (higher GORs) on its processing ca-
The whole gas process should datasheets (PDS) for certain design pacity. This could result in 30 capacity
be evaluated for bottlenecks, and cases. The design cases considered checks being performed. To consider
assessing only certain individual are normally limited to two or three an additional sensitivity for two inlet
items for their capacities should be cases, which provide an envelope pressures would then double the ca-
avoided since an item that is not for all normal operating scenarios pacity checks to 60.
checked may actually prove to be a with some margin. It should be noted Poyry has developed a software
bottleneck. Certain gas processing that these design cases are based on tool called Meascap, which can eas-
equipment may have been designed certain operating conditions which are ily identify potential bottlenecks and
with different design margins (design fixed in order to develop the design perform capacity checks by compar-
factors of 10% or 20%), which would of a particular facility, i.e. perform ing the required capacity (Demand)
allow it to accommodate higher gas HYSYS simulations and generate the of an equipment item with its design
flowrates and still remain within its necessary H&M balances. capacity (Capacity). By making this
design capacity. When a facility actually goes into comparison, it is possible to identify
This could apply to the PCVs or production mode, it may not operate how close certain pieces of equipment
heat exchangers, but not necessarily as per design conditions as the pa- operate to their design limits for a
the separators or the compressors. rameters may change. These param- given production case, thus highlight-
Therefore, the capacities of the eters could be pressure, temperature, ing potential bottlenecks within the
separators and compressors could flow, compositions, etc. The operator process. Multiple cases can be run si-
have exceeded before exceeding the then adjusts the operating conditions multaneously and, therefore, different
design capacities of PCVs or heat in order to accommodate any small production profiles or operating cases
exchangers. changes in P, T, flow, etc. However, can easily be evaluated.
Performing capacity checks for sometimes, these changes are signifi- Meascap is a simple Excel-based
individual processing equipment cantly different from those considered spreadsheet tool which extracts the
during the design process data generated by a HYSYS
phase. Therefore, simulation and uses it to calculate
in performing ca- the actual design capacity (Capac-
pacity checks on ity) and required capacity (Demand)
existing equip- of the equipment items using Capac-
ment, the engineer ity Models. The capacity models are
also has to take worksheets which are automatically
into consideration generated by Meascap based on the
the actual oper- equipment simulated in HYSYS, i.e.
ating conditions each separator, heat exchanger, com-
and not only those pressor, pump, valve, etc, will have
considered during its own capacity model. The capacity
the design phase models are used to specify the design
(PDS). capacity for each piece of equipment.
C a p a c i t y Different capacity checks for
checks are not al- the same piece of equipment can
ways easily per- be specified such as duty, tubeside
formed. If you pressure drop and gas capacity
have a complex checks for a heat exchanger. A list of
process or a large capacity checks available in Meascap
number of items for various types of equipment is
to check, this can presented in Table 1. Meascap then
be time consum- uses these design capacity (Capacity)
ing, particularly if results and compares them with the
a number of oper- actual required capacities (Demand)
ating scenarios are as determined from the data extracted
to be considered. from the HYSYS simulation. A
Take, for example, Utilisation Factor is then calculated for
an offshore gas fa- each piece of equipment to indicate, in

20 Jurutera March 2009


feature

Table 1: List of capacity checks performed by Meascap

percentage, how close the equipment tabular and graphical formats (refer to
is required to operate compared to its Figure 2).
design capacity. Refer to Figure 1 for Obviously, if the Utilisation Factor
the Meascap modelling structure. exceeds 100%, a design constraint
Meascap presents the results of the for that piece of equipment has been
utilisation factors for each item in both exceeded. Data filters are available

Jurutera March 2009 21


feature

and can be used to filter results so as to profiles is relatively easy once the One oil processing facility
only identify an equipment of interest initial model has been calibrated One CO2 removal platform
which exceeds a certain value (i.e. only in HYSYS and the design capacity
present results for equipment with worksheets (capacity models) have The fully integrated HYSYS model
a utilisation factor greater than 90% been completed. It should be noted included a CO2 removal membrane
or greater than 100%). At the same that very low utilization factors system, two hydrocyclone systems
time, Meascap also identifies how should also be checked since some for produced water treatment and a
much capacity is available for each process equipment efficiencies are propane refrigerant system along with
equipment item. significantly affected below a certain the usual process equipment such
This type of capacity approach turndown limit. as separators, compressors, pumps,
makes Meascap an ideal tool for use heat exchangers, valves, etc. The total
on Enhanced Oil Recovery (EOR) Case Study number of equipment items simulated
projects and for debottlenecking/ A debottlenecking study was in HYSYS was 220 while 80 well
optimisation studies for maturing performed using Meascap for a large production streams were defined in
offshore facilities. It could also be offshore complex in Southeast Asia. terms of compositions (GOR), pressure,
used by new facilities to check the An integrated HYSYS model was temperature and flow. Dummy wells
robustness of the design using the developed (refer to Figure 3) and were also included to incorporate future
latest operating conditions and calibrated against actual operating data production scenarios. A total of 660
production data in order to plan for and included the following facilities: capacity calculations were performed
future operating conditions and where Production from five wellhead for a given case.
potential bottlenecks could occur. platforms (WHP) Since the HYSYS simulation and
Running multiple cases for different One central processing platform the Meascap evaluation is based on
operating conditions or production (CPP) steady state operating conditions,

Launching in 2009

A Guide to Certified Engineering


Companies & Products
Calling all ISO-compliant or ISO-certified companies. Here is a chance to showcase your
accomplishments to the engineering fraternity in the country via our brand new publication
entitled, A Guide to Certified Engineering Companies & Products in Malaysia.

For just RM2,125 per page for a full-page-full-colour advertisement in this publication, you can
increase awareness and market recognition of your products and get in-depth coverage of
your companys business and services.

Do not miss out on this opportunity to highlight your ISO success!

For more information, please contact Dimension Publishing at 03-8070 9949.

DIMENSION PUBLISHING SDN. BHD. (449732-T)


Suite 29, 3A Floor, IOI Business Park, 1 Persiaran Puchong Jaya Selatan,
Bandar Puchong Jaya, 47100 Puchong, Selangor, Malaysia.
Tel : +603-8070 9949 Fax : +603-8070 0047 Website : www.dimensionpublishing.com

22 Jurutera March 2009


feature

Figure 2: Utilisation factor results

Figure 3: Case study-integrated HYSYS model

Jurutera March 2009 23


feature

the control set points was fixed in A total of 30 items were identified
the HYSYS simulation by specifying as potential bottlenecks since their
the temperature, pressure, flow or utilisation factors were greater than
composition of a particular stream. 100%. These included the following:
However, these can be changed in
Meascap for different operating Separator gas capacities and liquid
scenarios since they are process residence times and vane pack
variables. For example, if the operating capacities
pressure for a vessel is controlled by Control valve liquid capacities and
a PCV, the inlet stream pressure to Cvs
the vessel could be specified at the Heat exchanger duties and shell
control value, and the same goes for side pressure drop
temperature control where the process Pump discharge head
stream temperature is specified to Compressor discharge head
be the temperature control set point
value. A further 45 items were identified as
In Meascap, the evaluation of the having exceeded design constraint,
heating medium and cooling medium but these were soft design constraints
systems was limited to calculating such as inlet nozzle momentum limits
individual heat exchanger duty and gas capacities based on assumed k
requirements and comparing them values for separators and vane packs. It
with their design duties, so these is at the operators discretion whether
systems were not modelled in HYSYS. exceeding the soft design constraints
However, the total duty for the heating such as inlet nozzle momentum is
medium and cooling medium system acceptable.
was calculated in HYSYS in order As part of the development of
to compare with the utility systems the fully integrated HYSYS model,
design duty. inter field pipelines were modelled
Only if the system design duty is in HYSYS using a PIPESIM Link,
exceeded (i.e. sum of the individual which then incorporates the pipeline
heating or cooling duties) should a pressure drop and pipeline heat loss
separate HYSYS and Meascap model be results into the HYSYS simulation.
developed to identify any bottlenecks The design data and operating data
within the utility system itself. for all the items identified as being
Depending on the clients preference, potential bottlenecks is to be checked
the cooling and heating mediums can again, and the client is to review the
be modelled and simulated. A propane design data and operating data used
refrigerant system was modelled to produce the previous findings. Once
for this case study rather than just this review is complete, the operator
comparing the cooling duty for the intends to perform Meascap evaluations
primary and secondary chillers with as part of its EOR program.
their design duties. Therefore, Meascap is an ideal tool
The debottlenecking study was for both projects group and operations
conducted over a six-month period and group for operating companies looking
was split into three distinct phases: either to increase production using
their existing facilities or optimise
(i) Develop a HYSYS fully integrated production on maturing facilities.
facilities model and calibrate Meascap identifies potential bottlenecks
against actual operating conditions within a process and helps prioritise
(30%). the bottlenecks in terms of equipment
(ii) Collate design data for input into capacity (utilisation factor). Once the
Meascap Capacity models (55%) bottlenecks have been identified, and
(iii) Checking Meascap results and with the aid of cost benefit analysis,
input data particularly for items a value can be put on any changes
with a Utilisation Factor > 100% necessary to improve or increase
(15%) production. n

Jurutera March 2009 25

You might also like