Professional Documents
Culture Documents
EXERCISE BOOK
EXERCISES
01 - MV substation architectures
02 - MV substation architectures
03 - Industrial C13-200 MV substation
04 - Max. distance between surge arrester and MV equipment
05 - Calculation of MV cable cross-section
06 - Calculation of Isc
07 - CTs for MV metering
08 - CTs for MV protection
09 - Earth-fault relay settings
10 - Capacitors
Define:
1. Type of LV or MV metering
2. Architecture and choice of cubicles
3. Type and rating of fuse that protects the transformer
Define:
1. Type of LV or MV metering
2. Architecture and choice of cubicles
An industrial MV consumer is supplied directly with 20kV (24KV, 125kV impulse; Isc = 12.5kA)
The power distribution system is a loop. In case of interruption, a radial feeder powers the entire
installation (the system must automatically switch back to the loop if power is restored to the loop)
The plant includes
1 B1 2000kVA non-priority loop supplying different substations
1 T1 250kVA non-priority transformer
1 B2 2000kVA priority loop
1 T2 800kVA priority transformer
The plant also has a 380V/20kV diesel genset to back up priority loads.
D in m
Verification
Isc
S = t
k
Isc = in Amperes
t = in seconds
k = factor for type of cable
S = cross-section in mm2
Data
Power supply: 63kV
Short-circuit power: 2000MVA
Network impedance 63kV (can be calculated directly for 10kV)
Network configuration:
The network includes 2 transformers and 1 AC generator in parallel
Each of the satellite substations includes 2 transformers, but a single transformer is sufficient to
power the loads
We find the Isc from the network upstream with the 2 transformers in parallel and add the Isc
from the AC generator
The (PR)ALU cables are buried directly in dry calcareous ground at 20C, with nothing nearby
For substation B, provision should be made for 2 cables in parallel
Schneider Electric - Division - Name Date 9
Upstream network 63kV calculation of Isc
Short-circuit power 2000 MVA
T1 T2 G1
15 MVA
15 MVA
Usc =10%
20 MVA
Usc =10%
G Usc Sub =15%
Usc Trans= 20%
CB1 D2 CB3
10KV busbar
10KV busbar 10KV busbar
CB4
Substation A
CB5 CB6 CB7
T4 T5 In each substation
1 single transformer
in operation
0.5
0.5 km
km
15 MVA 15 MVA Substation
Substation C
C
Usc=10% Usc=10%
11 km
km
CB18 CB19 Substation
Substation B
B CB10 CB11
T8 T9
5 MVA 5 MVA
3KV Usc=8% Usc=8%
CB8 CB9
T6 T7 CB16 CB17
10 MVA 10 MVA
Usc=8% Usc=8%
3KV
CB12 CB13
3KV
Schneider Electric - Division - Name Date 10
Location or observation point R X Z Isc BC MC = BC*2.5
Upstream network, downstream view
15 MVA TR
20 MVA TR
2 TRs and 15 MVA genset in parallel
TRs in series with network
15 MVA genset in subtransient
15 MVA genset in transient
Values at busbar in transient
Values at busbar in subtransient
Cable of substation B
Busbar input, substation B, transient
Busbar input, substation B, subtrans.
Upstream, downstream view,
substation B, subtransient
10 MVA TR substation B
Series upstream network + TR10 sub.
Series upstream network + TR10 trans.
Reminders:
Resistivity of copper: = 22.510-3 . mm2 /m
Resistivity of aluminium: = 3610-3 .
mm2 /m
Schneider Electric - Division - Name Date 11
Calculation of short-circuit currents
T1 T2
Impedance of 2 transfos in // + network in series
CB1 CB2
Substation A
T1 T2 G1
15 MVA
15 MVA 20 MVA G Usc Sub =15%
Usc =10% Usc =10% Usc Trans= 20%
CB1 CB2 D3
Impedance of network + 2 TR in //
CB1 CB2
Ik3 of network + TR in //
Substation A
Impedance of network + T1
Impedance of network + T2
Isc GE transient
Isc GE subtransient
Substation B: 1 km
Substation B
Operational current Ir:
CB16 CB17
cables to substation C: per phase
3KV
CB6
CB8 CB9
Calculation of impedance in substation B, subtransient. T6 T7
10 MVA 10 MVA
Usc=8% Usc=8%
CB12 CB13
3KV
CB7
0.5 km
Substation C
3KV
- Transient
CB6
- Subtransient:
1 km
Application of relative impedance formula: Substation B
U 2 (secondary)
R (downstream) = R (upstream)
U 2 (primary) CB8 CB9
T6 T7
3KV
Isc and breaking capacity of CB12 and CB13
- Subtransient:
0.5 km
Substation
C
Application of relative impedance formula:
CB10 CB11
U2 (secondary) T8 T9
R (downstream) = R (upstream) 5 MVA
5 MVA
U2 (primary) Usc=8%
Usc=8%
1) Impedance, Ik3 and breaking capacity in transient CB16 CB17
3KV
Impedance of transformer
U= 5.5 KV
Predicted active power P = 760 KW
p.f. = 0.93
Isc 8.5 KA
Power consumed by meter 2.5 VA
Meter input 5A
CT line < > meter = 20m (total 2 ways) in 6mm
Definition of CTs?
U= 6 KV
Large motor feeder 2500 KW p.f. 0.9 efficiency 0.94
Starting current 6 x In
Isc 8.5 KA
Power consumed by protection relay 1.8 VA
Relay input 5A
Line 42m (total 2 ways) in 6mm
3.1. To what should IL be limited by the earth fault resistance in order to protect 90% of the star winding of the
motor or motors?
3.3. what is the continuous permissible current for the earth fault resistance (zero-sequence generator) ?
TOTAL
Operating voltage U=5.5 kV
L = length of trunking in km
n = number of cables in // per phase
V = ph-to-neutral voltage in V
C = linear capacity of cable in F/km
= pulsation in rad/s
Schneider Electric - Division - Name Date 29
Earth-fault relay settings
G
Gh
1 X X X X
2 RGh
3
4 5 X X X 8
6 7 X 9
X X 9.2
9.1
M M M M M
There is a plan to double the installation and this will call for additional active power P2: 250 kW with
p.f. = 0.75.
QUESTIONS:
1) Without power factor correction, determine the apparent power at the transformer terminals.
What do you notice?
2) Calculate the maximum reactive power that the 630 kVA transformer can supply for this project.
3) Calculate the total active power to be supplied to the load before power factor correction.
6) A decision is made to raise the p.f. to 0.92. What is the minimum power of the capacitor bank to be installed?