MMC - GAMUDA JV
ELECTRIFIED DOUBLE TRACK PROJECT - IPOH TO PADANG BESAR
JOB RISK ASSESSMENT FORM Ref No. AS/JRA-055
Project : Electrified Double Track Project (EDTP) Description of Work : CONSTRUCTION OF SG. CHUPING Prepared by : MOHD HANAFIAH B ABD RASIP Revision No.
Location :CH 136208 (N1-RB2) Type of activities : Routine/ Non Routine Approved by : CHIEW HWA AIK
Hazard Risk
No Sequence of Basic Job Steps Potential Hazards Current Controls Sev. Pro. Significant (Y/N) Hierarchy of Control New Control Measures By Whom
Groups Level
person
Site Engineer
2 Pre-construction work
Survey Works
(refer to JRA No.AS-JRA-018 on
Survey Works)
Site Clearing
3 Piling work
Bored Pile)
4 Construction Of RC Abutment
Bridge)
Appendix B to DTP-MMCG(HQ)-QP-OP-026
MMC - GAMUDA JV
ELECTRIFIED DOUBLE TRACK PROJECT - IPOH TO PADANG BESAR
JOB RISK ASSESSMENT FORM Ref No. AS/JRA-055
Project : Electrified Double Track Project (EDTP) Description of Work : CONSTRUCTION OF SG. CHUPING Prepared by : MOHD HANAFIAH B ABD RASIP Revision No.
Location :CH 136208 (N1-RB2) Type of activities : Routine/ Non Routine Approved by : CHIEW HWA AIK
Hazard Risk
No Sequence of Basic Job Steps Potential Hazards Current Controls Sev. Pro. Significant (Y/N) Hierarchy of Control New Control Measures By Whom
Groups Level
5 Erection Of Scaffolding 1 Fall from high Nil 3 4 12 Y 5 * workers shall attend training on Subcontractors
compulsory
by competent person
competent person
6 Construciton of Pre-tension
beam
MMC - GAMUDA JV
ELECTRIFIED DOUBLE TRACK PROJECT - IPOH TO PADANG BESAR
JOB RISK ASSESSMENT FORM Ref No. AS/JRA-055
Project : Electrified Double Track Project (EDTP) Description of Work : CONSTRUCTION OF SG. CHUPING Prepared by : MOHD HANAFIAH B ABD RASIP Revision No.
Location :CH 136208 (N1-RB2) Type of activities : Routine/ Non Routine Approved by : CHIEW HWA AIK
Hazard Risk
No Sequence of Basic Job Steps Potential Hazards Current Controls Sev. Pro. Significant (Y/N) Hierarchy of Control New Control Measures By Whom
Groups Level
beam person
adequate
compulsory
competent person.
safety reprsentative.
Appendix B to DTP-MMCG(HQ)-QP-OP-026
MMC - GAMUDA JV
ELECTRIFIED DOUBLE TRACK PROJECT - IPOH TO PADANG BESAR
JOB RISK ASSESSMENT FORM Ref No. AS/JRA-055
Project : Electrified Double Track Project (EDTP) Description of Work : CONSTRUCTION OF SG. CHUPING Prepared by : MOHD HANAFIAH B ABD RASIP Revision No.
Location :CH 136208 (N1-RB2) Type of activities : Routine/ Non Routine Approved by : CHIEW HWA AIK
Hazard Risk
No Sequence of Basic Job Steps Potential Hazards Current Controls Sev. Pro. Significant (Y/N) Hierarchy of Control New Control Measures By Whom
Groups Level
8 Construction of RC Diaphragm
Beam
10 Construction of RC Approach
Slab
1. Risk Assessment Code (RAC) RAC No. 1 (1-5) Acceptable(Low) RAC No II (6-12) Moderate (Medium) RAC No. III (13-25) Not Acceptable (High) Significant Risk = Risk level more than 6 (Medium & High)
2. Risk = Severity rate x Probability
Sev Explanation Prob. Explanation
5 Fatality or paralysed 5 Almost Certain - happen frequently
4 Permanent disability (including occupational diseases) 4 Very likely - could happen frequently
3 Temporary disablement, Lost Time Accident (LTA)more than 3 days 3 Likely - could happen occasionally
2 Minor injury, LTA with up to 3 lost days 2 Unlikely - could happen rarely
1 First aid injury, non LTA 1 Very unlikely - probably will not happen
3. Hierarchy of Control
1 Elimination
2 Substitution
3 Isolation
4 Engineering Controls
5 Administration Controls
6 Personal Protective Equipment
7 Others :____________________________
4. Hazard Group & Example
Radiation, noise, struck by object,1struck
Physical
against, extreme temperature, vibration, pressure, fall from height, fall from same level, poor illumination, electric shock, short circuit, fire, etc.
2 Chemical Irritant, harmful, corrosive, toxic, very toxic, flammable, explosive.
3 Biological Blood patogen, infection, viruses, harm from animal (eg. Snake)
4 Mechanical Drawing in, entanglement, punching, crushing, cut, ejection, cutting, etc.
5 Psychological Stress, time pressure, violence, etc.
6 Ergonomic
Manual handling, repetitive movement, awkward posture or movement, poor work station design