Professional Documents
Culture Documents
Process Costing - Reviewer
Process Costing - Reviewer
Villaluz, CPA
Problem 1:
Double Click Manufacturing Co. uses process costing in the manufacture of its sole product. The following
production data are presented to you:
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 2:
Double Click Manufacturing Co. uses process costing in the manufacture of its sole product. The following
production data are presented to you:
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 3:
Double Click Manufacturing Co. uses process costing in the manufacture of its sole product. The following
production data are presented to you:
Forty percent of materials is added when the processing is halfway completed; balance when 80%
completed. Beginning inventory, if any, need 3/5 to be completed.
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 4:
Double Click Manufacturing Co. uses process costing in the manufacture of its sole product. The following
production data are presented to you:
1
Prepared by: Brian Christian S. Villaluz, CPA
20% of materials is added when the units are 25% completed; remaining materials are added when the
units are 90% converted.
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 5:
Monique Textile Inc., produces sophisticated fabrics that are being supplied to 5-star hotels and to high-
end condominiums that require components to be integrated in various points of the production. At the
beginning of the month, 4,000 units were in process. These were 20% converted.
For the current month, Monique started to produce 16,000 units. Only 12,000 of these were completed.
The remainder was behind 25% from completion.
Due to the complexity of this textile, materials are added at various points in the production. To sum up:
Direct materials:
40% are put into production at the beginning
50% are placed when the fabrics are 55% completed
10% are placed when the fabrics are 99% done
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 6:
Cherry Manufacturing Co. uses process costing in the manufacture of its sole product. The following
production data are presented to you:
All materials are added at the start of the process. Cherry inspects goods at 75% completion as to
conversion.
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 7:
The following information is available for BGC Company for the current period:
2
Prepared by: Brian Christian S. Villaluz, CPA
1. Using average costing, compute for the EUP for materials and conversion.
2. Using FIFO, compute for the EUP for materials and conversion.
Problem 8:
Cherry Manufacturing Co. uses process costing in the manufacture of its sole product. The following
information is available for the current year:
Current cost
Material 690,000
Conversion 471,150
All materials are added at the start of the process. Cherry inspects goods at 75% completion as to
conversion.
Using FIFO
1. Compute for the EUP for materials and conversion.
2. Compute for the cost per EUP for materials and conversion.
3. Compute for the cost assigned to units completed.
4. Compute for the cost assigned to the ending inventory.
5. Compute for the cost of abnormal lost units.
Problem 9:
Cherry Manufacturing Co. uses process costing in the manufacture of its sole product. The following
information is available for the current year:
3
Prepared by: Brian Christian S. Villaluz, CPA
Current cost
Material 690,000
Conversion 471,150
All materials are added at the start of the process. Cherry inspects goods at 75% completion as to
conversion.
Using FIFO
1. Compute for the EUP for materials and conversion.
2. Compute for the cost per EUP for materials and conversion.
3. Compute for the cost assigned to units completed.
4. Compute for the cost assigned to the ending inventory.
Problem 10:
Cherry Manufacturing Co. uses process costing in the manufacture of its sole product. The following
information is available for the current year:
Current cost
Material 690,000
Conversion 471,150
All materials are added at the start of the process. Cherry inspects goods at 75% completion as to
conversion.
Using FIFO
1. Compute for the EUP for materials and conversion.
2. Compute for the cost per EUP for materials and conversion.
3. Compute for the cost assigned to units completed.
4. Compute for the cost assigned to the ending inventory.
4
Prepared by: Brian Christian S. Villaluz, CPA
ASSEMBLY DEPARTMENT
Units: Cost:
January 1, 2016 100,000 units 40% complete as to conversion Direct materials P3,000,000
Direct labor P5,000,000
Factory overhead P2,000,000
December 31, 2016 150,000 units 80% complete as to conversion ???
Units started during 2016 400,000 units Direct materials P12,000,000
Direct labor P15,000,000
Factory overhead P13,000,000
FINISHING DEPARTMENT
Units: Cost:
January 1, 2016 50,000 units 70% incomplete as to conversion Transferred In P10,000,000
Direct materials P6,000,000
Direct labor P1,000,000
Factory overhead P3,000,000
December 31, 2016 30,000 units 10% incomplete as to conversion ???
Units started during 2016 ??? Transferred In ???
Direct materials P30,000,000
Direct labor P40,000,000
Factory overhead P10,000,000
Additional information:
(a) It is the companys policy to add conversion cost evenly throughout the period in the two
departments.
(b) It is the companys policy to add all direct materials in the assembly department at the start of the
process while all direct materials in the finishing department are added at the end of the process.
(c) There is no spoilage in both departments.
5
Prepared by: Brian Christian S. Villaluz, CPA
inspection. In both departments, units are inspected at the end of processing. Department 1 uses FIFO
while Department 2 uses average costing. The following production data for August show:
Department 1 Department 2
QUANTITY SCHEDULE
Beg. WIP 6,000 4,000
Stage of completion 1/3 4/5
Ending WIP 9,000 7,000
Stage of completion 2/3 5/7
Put into process 44,000 -
Normal loss 1,200 1,000
Abnormal loss 800 500
COST DATA
Beg. WIP
Transferred in - P3,710
Materials P9,000 -
Conversion costs 6,500 4,000
Current period costs
Materials 88,000 62,100
Conversion costs 67,500 49,300
Transferred in - ???
DEPARTMENT 1
1. What is the EUP for materials and conversion?
2. How much is the cost per EUP for materials and conversion?
3. What is the cost of goods manufactured or cost assigned to units completed for the
year ended December 31, 2016?
4. What is the cost assigned to December 31, 2016 work-in-process inventory?
DEPARTMENT 2
5. What is the EUP for transferred in, materials, and conversion?
6. How much is the cost per EUP for materials and conversion?
7. What is the cost of goods manufactured or cost assigned to units completed for the
year ended December 31, 2016?
8. What is the cost assigned to December 31, 2016 work-in-process inventory?
END
-BCSV-
6
Prepared by: Brian Christian S. Villaluz, CPA
ANSWERS:
PROBLEM 1: PROBLEM 7:
1. DM 85,000; CC 77,000 1. DM 84,500; CC 78,100
2. DM 75,000; CC 73,000 2. DM 70,000; CC 67,225
PROBLEM 2: PROBLEM 8:
1. DM 65,000; CC 73,000 1. DM 100,000; CC 106,525
2. DM 65,000; CC 67,000 2. 6.90; 4.42
3. 1,264,853
4. 144,913
5. 51,075
6. DM 120,000; CC 113,525
7. 6.50; 6.00
8. 1,251,000
9. 155,150
10. 55,000
PROBLEM 3: PROBLEM 9:
1. DM 165,000; CC 159,375 1. DM 100,000; CC 107,975
2. DM 165,000; CC 153,375 2. 6.90; 4.36
3. 1,254,161
4. 155,760
5. DM 120,000; CC 114,975
6. 6.50; 5.92
7. 1,238,412
8. 167,540
PROBLEM 5: Part IV
1. DM 19,600; CC 19,000 1. DM - 400,000; CC - 430,000
2. DM 18,000; CC 18,200 2. 30; 65.12
3. 37,687,200
4. 12,314,400
5. TI 350,000; DM 370,000; CC 382,000
6. 107.68; 81.08; 130.89
7. 130,923,150
8. 6,764,430
PROBLEM 6: Part V
1. DM 120,000; CC 113,525 1. DM 44,000; CC 45,000
2. DM 100,000; CC 106,525 2. 2.00; 1.50
3. 141,200
4. 27,000
5. 43,000; 34,500; 41,000
6. 3.37; 1.80; 1.30
7. 227,885
8. 30,090