NEED TO FOLLOW THE FOLLOWING INSTRUCTION BEFORE TO TEST THE BATTERY BANKS

CHECK ALL THE CONNECTION BETWEEN


BREAKERS TO BATTERY BANKS AND CELL
TO CELL ,CHECK RATING OF INSTALLED
BRAKERS ,CHECK LLVD AND BLVD
BREAKERS AND STATUS OF
CCONNECTIONS .

OF

CHECK RECTIFIER MODE CHANGER


SWITCH WHICH SHOULD BE ON 0 MODE
OR NORMAL MODE

CHECK BATTERY TEST MODE SETTING ,


LLVD AND BLVD AND CHANGE
ACCORDING TO GIVEN REQUIREMENT
AND STANDARD

BATTERY TEST MODE SETTINGS

TEST END VOLTAGE :45.2

TEST TIME:120 MINS

LLVD AND BLVD SETTINGS

LLVD: 44 V

BLVD: 43.2 V

AFTER ABOVE STEPS PUT RECTIFIER ON


TEST MODE AND CONTINUE THE TEST ON
TERMINAL SITES FOR 60 MINS AND 80
MINS FOR HUBS IN BETWEEN REGISTER
THE READING OF EACH CELL AND BANK
AFTER EVERY 15 MINS AND SORT THE
FAULTY CELLS IF FOUND ANY

STOP THE TEST AND


UPLOAD ALL REQUIRED
PHOTOS DURING TEST