Shooting Schedule

Date and Location Scene Who is needed Equipment


Time needed
25th Michelles Memories of the All of cast Camera, tripod,
October House couple together, glidecam,
watching TV, spending lighting, micv
time together
25th Stockwood Memory of them on a All of cast Camera, tripod,
October Park walk together glidecam,
lighting, mic

3rd B Block, Opening scene when All of cast Camera, tripod,


November Manshead the couple meets. glidecam,
School lighting, mic
3rd Room D2, Room scenes Only character Camera, tripod,
November Manshead 1 and glidecam,
School production gorilla pod,
team lighting, mic

Daylight

Date and Location Consideration


Time
25th MichellesTo shoot this scene we need daylight which is why we have
October House chosen the 25th as it is when everyone is available and in
halfterm so we can shoot in the day time
25th Stockwood To shoot this scene we need daylight which is why we have
October Park chosen the 25th as it is when everyone is available and in
halfterm so we can shoot in the day time

3rd B Block, This scene will need daylight so we have chosen a school day so
November Manshead we are able to shoot in the day time.
School
3 rd D2, This scene will not require daylight as the room does not have
November Manshead any external windows and can be artificially lit
School

Weather
Date and Location Consideration
Time
25th Michelles For this scene the weather will not impact the shooting,
October House however it would be helpful if it was dry
25th Stockwood For this scene we need the weather to be dry and preferably
October Park sunny so we have good lighting for the scene

3rd B Block, Weather will not hinder this scene


November Manshead
School
3 rd D2, Weather will not hinder this scene
November Manshead
School

Availability of actors/crew

Date and Location Consideration


Time
25th Michelles We have chosen the 25th as all actors and crew and available
October House
25th Stockwood We have chosen the 25th as all actors and crew and available
October Park

3rd B Block, We have chosen the 3rd as all actors and crew and available
November Manshead
School
3rd D2, We have chosen the 3rd as all actors and crew and available
November Manshead
School

Availability of equipment

Date and Location Consideration


Time
25th Michelles All equipment we are using is owned by me so there is no
October House availability issues
25th Stockwood All equipment we are using is owned by me so there is no
October Park availability issues

3rd B Block, All equipment we are using is owned by me so there is no


November Manshead availability issues
School
3 rd D2, All equipment we are using is owned by me so there is no
November Manshead availability issues
School
Use of locations
Date and Location Consideration
Time
25th Michelles This is a good location to use because it is close to other
October House locations we are using, it is easy for cast and crew to get to
25th Stockwood The location provides us with everything we needed for the
October Park scene, it is a public space so we have no issues with filming
there

3rd B Block, The scene requires this location as we need the lockers, as it is
November Manshead at school there is no issues with the use of the location
School
3 rd D2, Again this is at school so there is no issues with use of the
November Manshead location
School

Transport

Date and Location Consideration


Time
25th MichellesChris will be able to drive himself and I to the location
October House Michelle will already be there as it is her house
The actors will make their own way
25th Stockwood As Michelles house is near Stockwood we will all be able to
October Park walk round to the park

3rd B Block, Michelle, Chris and I will already be there


November Manshead Actors will make their own way
School
3 rd D2, Michelle, Chris and I will already be there
November Manshead Actors will make their own way