SITE DIARY
Date: 31/12/2015 Name : Situge S.M.J.M.T
Location
L03 at grid 23A-29/A-B1 concrete pouring inspection was done in day and night
L04 at grid 2-5/A-D Reinforcement beams fabrication work are inspected
Defects Noted/
Verbal instruction given to contractor
regarding defects
Collected information