You are on page 1of 222

PEKERJAAN PERLINTASAN PIPA MELALUI SUNGAI

JEMBATAN PIPA

172 Item Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. TIPE D
Paket :
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.44
3 Urugan tanah kembali m3 2.04
4 Pemadatan tanah perlapis 25 cm m3 2.04
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan batu kosong m3 0.40
7 Pasangan Batu, Spesi 1 : 4. m3 3.75
8 Plesteran Spesi 1 : 2, tebal 15 mm. m2 5.70

Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Pipa dan Accessories
1 Pipa Steel ND. 300 mm m 16.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Loose Flange ND. 300 mm, steel bh 8.00
4 Bend 45 all flange ND. 300 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Tee all flange ND. 300 x 100 mm, CI bh 1.00
7 Flange adaptor ND. 300 mm, CI bh 2.00
8 Flange socket ND. 300 mm, PVC RRJ bh 2.00
9 Flange socket ND. 100 mm, PVC RRJ bh 1.00
10 Gate Valve ND. 300 mm all flange, CI. bh 1.00
11 Gate Valve ND. 100 mm all flange, CI. bh 1.00
12 Air Valve ND. 25 mm all flange, CI bh 1.00
13 Street box Inside dia. 100 mm, CI. bh 2.00
14 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total II
III Pekerjaan lain-lain.
1 Pengecatan pipa ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

173 Item Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m.


Paket s Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kampung Cibacang, Patok 32.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.47
3 Urugan tanah kembali m3 2.74
4 Pemadatan tanah perlapis 25 cm m3 2.74
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 2.74
7 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.38
camp. 1:2:3 baja U.24, 160 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.340 kg 882.00
dimodifikasi dari bahan profil baja IWF. 250.175.7.11
3 Gelagar melintang, IWF.100.100.6.8. kg 91.74
3 Ikatan angin, baja siku L.50.50.5. kg 42.73
4 Plat penegar prol HC, tebal 10 mm kg 56.95
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 73.70
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 41.88
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 16.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 7.00
4 Bend 45 all flange ND. 300 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Loose Flange ND. 300 mm, steel bh 8.00
7 Tee all flange ND. 300 x 100 mm, CI bh 1.00
8 Flange adaptor ND. 300 mm, CI bh 2.00
9 Flange socket ND. 100 mm, PVC RRJ bh 1.00
10 Gate Valve ND. 300 mm all flange, CI. bh 1.00
11 Street box Inside dia. 100 mm, CI. bh 2.00
12 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV
174 Item Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m.
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kampung Cibacang, Patok 32.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.44
3 Urugan tanah kembali m3 2.04
4 Pemadatan tanah perlapis 25 cm m3 2.04
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 3.75
7 Plesteran Spesi 1 : 2, tebal 15 mm. m3 5.70

Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.340 kg 1,234.00
dimodifikasi dari bahan profil baja IWF. 250.175.7.11
3 Gelagar melintang, IWF.100.100.6.8. kg 128.50
3 Ikatan angin, baja siku L.50.50.5. kg 59.20
4 Plat penegar prol HC, tebal 10 mm kg 80.20
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 117.92
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 67.00
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 20.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 11.00
4 Bend 45 all flange ND. 300 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Loose Flange ND. 300 mm, steel bh 8.00
7 Tee all flange ND. 300 x 100 mm, CI bh 1.00
8 Flange adaptor ND. 300 mm, CI bh 2.00
9 Flange socket ND. 100 mm, PVC RRJ bh 1.00
10 Gate Valve ND. 300 mm all flange, CI. bh 1.00
11 Street box Inside dia. 100 mm, CI. bh 2.00
12 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

175 Item Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kampung Cibacang, Patok 32.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.44
3 Urugan tanah kembali m3 2.04
4 Pemadatan tanah perlapis 25 cm m3 2.04
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 3.75
7 Plesteran Spesi 1 : 2, tebal 15 mm. m3 5.70

Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.340 kg 1,411.20
dimodifikasi dari bahan profil baja IWF. 250.175.7.11
3 Gelagar melintang, IWF.100.100.6.8. kg 146.78
3 Ikatan angin, baja siku L.50.50.5. kg 68.36
4 Plat penegar prol HC, tebal 10 mm kg 91.12
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 117.92
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 67.00
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 22.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 11.00
4 Bend 45 all flange ND. 300 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Loose Flange ND. 300 mm, steel bh 8.00
7 Tee all flange ND. 300 x 100 mm, CI bh 1.00
8 Flange adaptor ND. 300 mm, CI bh 2.00
9 Flange socket ND. 100 mm, PVC RRJ bh 1.00
10 Gate Valve ND. 300 mm all flange, CI. bh 1.00
11 Street box Inside dia. 100 mm, CI. bh 2.00
12 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

176 Item Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kampung Cibacang, Patok 32.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.47
3 Urugan tanah kembali m3 2.74
4 Pemadatan tanah perlapis 25 cm m3 2.74
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 2.74
7 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.38
camp. 1:2:3 baja U.24, 160 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.340 kg 1,587.60
dimodifikasi dari bahan profil baja IWF. 250.175.7.11
3 Gelagar melintang, IWF.100.100.6.8. kg 165.12
3 Ikatan angin, baja siku L.50.50.5. kg 76.91
4 Plat penegar prol HC, tebal 10 mm kg 102.50
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 132.66
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 75.36
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 24.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 12.00
4 Bend 45 all flange ND. 300 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6
Loose Flange ND. 300 mm, steel bh 8.00
7
Tee all flange ND. 300 x 100 mm, CI bh 1.00
8
Flange adaptor ND. 300 mm, CI bh 2.00
9
Flange socket ND. 100 mm, PVC RRJ bh 1.00
10
Gate Valve ND. 300 mm all flange, CI. bh 1.00
11
Street box Inside dia. 100 mm, CI. bh 2.00
12
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

177 Item Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Desa Jatiwangi, Patok 172.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.47
3 Urugan tanah kembali m3 2.74
4 Pemadatan tanah perlapis 25 cm m3 2.74
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 2.74
7 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.38
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 1,764.22
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Gelagar melintang, IWF.100.100.6.8. kg 183.54
3 Ikatan angin, baja siku L.50.50.5. kg 85.44
4 Plat penegar prol HC, tebal 10 mm kg 113.88
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 147.38
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 83.72
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 26.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 14.00
4
Bend 45 all flange ND. 300 mm, steel bh 4.00
5
Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6
Loose Flange ND. 300 mm, Steel bh 8.00
7
Tee all flange ND. 300 x 100 mm, CI bh 1.00
8
Flange adaptor ND. 300 mm, CI bh 2.00
9
Gate Valve ND. 300 mm all flange, CI. bh 1.00
10
Gate Valve ND. 100 mm all flange, CI. bh 1.00
11
Flange socket ND. 100 mm, PVC RRJ bh 1.00
12
Street box Inside dia. 100 mm, CI. bh 2.00
13
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

178 Item Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Jembatan Balenyengked, Patok 172.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 19.24
3 Urugan tanah kembali m3 1.10
4 Pemadatan tanah perlapis 25 cm m3 1.10
5 Buangan tanah disekitar lokasi m3 18.14
6 Bongkaran beton masif dan pasangan batu. m3 9.15
7 Pasangan Batu kosong m3 3.15
8 Pasangan Batu, Spesi 1 : 4. m3 11.50
9 Urugan pasir dipadatkan m3 1.57
10 Plesteran Spesi 1 : 2, tebal 15 mm. m3 17.48
11 Beton Bertulang K225, Pilar Jembatan 50/50. m3 8.00
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 1,908.40
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Baja Canal C.160.60.7,6. 10,5 kg 391.04
3 Ikatan angin, baja siku L.60.60.6. kg 302.98
4 Plat penegar Gelagar induk, tebal 10 mm kg 255.30
5 Plat sambung gelagar induk (3 titik smb) kg 60.32
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 36.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 14.00
termasuk bantalan kayu 8/15 cm
4 Bend 11 1/4 all flange ND. 300 mm, steel bh 2.00
5 Bend 45 all flange ND. 300 mm, steel bh 2.00
6 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
7 Loose Flange ND. 300 mm, Steel bh 10.00
8 Tee all flange ND. 300 x 100 mm, CI bh 1.00
9 Flange adaptor ND. 300 mm, CI bh 4.00
10 Flange spigot ND. 300 mm, PVC bh 1.00
11 Gate Valve ND. 300 mm all flange, CI. bh 1.00
12 Gate Valve ND. 100 mm all flange, CI. bh 1.00
13 Air Valve (Double) ND. 50 mm all flange, CI bh 1.00
14 Loose Flange ND. 100 mm, Steel bh 1.00
15 Flange socket ND. 100 mm, PVC RRJ bh 1.00
16 Street box Inside dia. 100 mm, CI. bh 2.00
17 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

179 Item Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kp. Lempar, Desa Cijambe, Patok 40.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 15.59
3 Urugan tanah kembali m3 1.10
4 Pemadatan tanah perlapis 25 cm m3 1.10
5 Buangan tanah disekitar lokasi m3 -
6 Pasangan Batu kosong m3 2.64
7 Pasangan Batu, Spesi 1 : 4. m3 12.20
8 Urugan pasir dipadatkan m3 1.32
9 Plesteran Spesi 1 : 2, tebal 15 mm. m3 14.00
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 1,908.40
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Baja Canal C.160.60.7,6. 10,5 kg 391.04
3 Ikatan angin, baja siku L.60.60.6. kg 302.98
4 Plat penegar Gelagar induk, tebal 10 mm kg 255.30
5 Plat sambung gelagar induk (3 titik smb) kg 60.32
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 36.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 14.00
termasuk bantalan kayu 8/15 cm
4 Bend 11 1/4 all flange ND. 300 mm, steel bh 2.00
5 Bend 45 all flange ND. 300 mm, steel bh 2.00
6 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
7 Loose Flange ND. 300 mm, Steel bh 10.00
8 Tee all flange ND. 300 x 100 mm, CI bh 1.00
9 Flange adaptor ND. 300 mm, CI bh 4.00
10 Flange spigot ND. 300 mm, PVC bh 1.00
11 Gate Valve ND. 300 mm all flange, CI. bh 1.00
12 Gate Valve ND. 100 mm all flange, CI. bh 1.00
13 Air Valve (Double) ND. 50 mm all flange, CI bh 1.00
14 Loose Flange ND. 100 mm, Steel bh 1.00
15 Flange socket ND. 100 mm, PVC RRJ bh 1.00
16 Street box Inside dia. 100 mm, CI. bh 2.00
17 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

180 Item Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus).
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kp. Lempar, Desa Cijambe, Patok 40.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 15.59
3 Urugan tanah kembali m3 1.10
4 Pemadatan tanah perlapis 25 cm m3 1.10
5 Buangan tanah disekitar lokasi m3 -
6 Bongkaran beton masif dan pasangan batu. m3 9.15
7 Pasangan Batu kosong m3 2.64
8 Pasangan Batu, Spesi 1 : 4. m3 16.50
9 Urugan pasir dipadatkan m3 1.32
10 Plesteran Spesi 1 : 2, tebal 15 mm. m3 17.00
11 Beton Bertulang K225, Pilar Jembatan 50/50. m3 9.52
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 1,908.40
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Baja Canal C.160.60.7,6. 10,5 kg 391.04
3 Ikatan angin, baja siku L.60.60.6. kg 302.98
4 Plat penegar Gelagar induk, tebal 10 mm kg 255.30
5 Plat sambung gelagar induk (3 titik smb) kg 60.32
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 36.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 14.00
termasuk bantalan kayu 8/15 cm
4 Bend 11 1/4 all flange ND. 300 mm, steel bh 2.00
5 Bend 45 all flange ND. 300 mm, steel bh 2.00
6 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
7 Loose Flange ND. 300 mm, Steel bh 10.00
8 Tee all flange ND. 300 x 100 mm, CI bh 1.00
9 Flange adaptor ND. 300 mm, CI bh 4.00
10 Flange spigot ND. 300 mm, PVC bh 1.00
11 Gate Valve ND. 300 mm all flange, CI. bh 1.00
12 Gate Valve ND. 100 mm all flange, CI. bh 1.00
13 Air Valve (Double) ND. 50 mm all flange, CI bh 1.00
14 Loose Flange ND. 100 mm, Steel bh 1.00
15 Flange socket ND. 100 mm, PVC RRJ bh 1.00
16 Street box Inside dia. 100 mm, CI. bh 2.00
17 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

181 Item Jembatan Pipa, ND. 250 mm, Bentang = 50,00 m


Paket :
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 26.87
3 Urugan tanah kembali m3 8.06
4 Pemadatan tanah perlapis 25 cm m3 8.06
5 Buangan tanah disekitar lokasi m3 18.81
6 Bongkaran beton masif dan pasangan batu. m3 9.15
7 Pasangan Batu kosong m3 2.64
8 Pasangan Batu, Spesi 1 : 4. m3 20.70
9 Urugan pasir dipadatkan m3 1.32
10 Plesteran Spesi 1 : 2, tebal 15 mm. m3 36.00
11 Beton Bertulang K225, Pilar Jembatan 50/50. m3 17.46
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 8.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 6,250.00
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Baja Canal C.160.60.7,6. 10,5 kg 1,002.00
3 Ikatan angin, baja siku L.60.60.6. kg 582.50
4 Plat penegar Gelagar induk, tebal 10 mm kg 491.00
5 Plat sambung gelagar induk (3 titik smb) kg 125.00
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 250 mm m 67.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 35.00
3 Klem pipa ND. 250 mm, plat baja 3 x 50 mm + baut mur. bh 58.00
termasuk bantalan kayu 8/15 cm
4 Bend 45 all flange ND. 250 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Loose Flange ND. 250 mm, Steel bh 16.00
7 Tee all flange ND. 250 x 100 mm, CI bh 1.00
8 Flange adaptor ND. 250 mm, CI bh 4.00
9 Flange spigot ND. 250 mm, PVC bh 1.00
10 Gate Valve ND. 250 mm all flange, CI. bh 1.00
11 Gate Valve ND. 100 mm all flange, CI. bh 1.00
12
Air Valve (Double) ND. 50 mm all flange, CI bh 1.00
13
Loose Flange ND. 100 mm, Steel bh 1.00
14
Flange socket ND. 100 mm, PVC RRJ bh 1.00
15
Street box Inside dia. 100 mm, CI. bh 2.00
16
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

182 Item Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Desa Jatiwangi, Patok 172.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 3.80
3 Bongkaran beton masif dan pasangan batu. m3 5.40
4 Urugan tanah kembali m3 2.74
5 Pemadatan tanah perlapis 25 cm m3 2.74
6 Buangan tanah disekitar lokasi m3 3.40
7 Pasangan Batu, Spesi 1 : 4. m3 4.94
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.38
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 8.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.400 kg 2,930.00
dimodifikasi dari bahan profil baja IWF. 300.200.9.14
3 Gelagar melintang, IWF.100.100.6.8. kg 215.76
3 Ikatan angin, baja siku L.50.50.5. kg 100.46
4 Plat penegar prol HC, tebal 10 mm kg 133.96
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 148.59
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 84.40
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 300 mm m 33.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 14.00
4 Bend 45 all flange ND. 300 mm, Steel bh 4.00
5
Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6
Loose Flange ND. 300 mm, Steel bh 6.00
7
Tee all flange ND. 300 x 100 mm, CI bh 1.00
8
Flange adaptor ND. 300 mm, CI bh 2.00
9
Gate Valve ND. 300 mm all flange, CI. bh 1.00
10
Gate Valve ND. 100 mm all flange, CI. bh 1.00
11
Flange socket ND. 100 mm, PVC RRJ bh 1.00
12
Street box Inside dia. 100 mm, CI. bh 2.00
13
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

183 Item Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m.


Paket :
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.44
3 Urugan tanah kembali m3 2.04
4 Pemadatan tanah perlapis 25 cm m3 2.04
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan batu kosong m3 0.40
7 Pasangan Batu, Spesi 1 : 4. m3 3.75
8 Plesteran Spesi 1 : 2, tebal 15 mm. m2 5.70

Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Pipa dan Accessories
1 Pipa Steel ND. 250 mm m 16.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Loose Flange ND. 250 mm, steel bh 8.00
4 Bend 45 all flange ND. 250 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Tee all flange ND. 250 x 100 mm, CI bh 1.00
7 Flange adaptor ND. 250 mm, CI bh 2.00
8 Flange socket ND. 250 mm, PVC RRJ bh 2.00
9 Flange socket ND. 100 mm, PVC RRJ bh 1.00
10 Gate Valve ND. 250 mm all flange, CI. bh 1.00
11 Gate Valve ND. 100 mm all flange, CI. bh 1.00
12 Air Valve ND. 25 mm all flange, CI bh 1.00
13 Street box Inside dia. 100 mm, CI. bh 2.00
14 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total II
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

184 Item Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Kampung Cibacang, Patok 32.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.47
3 Urugan tanah kembali m3 2.74
4 Pemadatan tanah perlapis 25 cm m3 2.74
5 Buangan tanah disekitar lokasi m3 3.40
6 Pasangan Batu, Spesi 1 : 4. m3 2.74
7 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.38
camp. 1:2:3 baja U.24, 160 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk, Profil baja Honey Comb, HC.340 kg 882.00
dimodifikasi dari bahan profil baja IWF. 250.175.7.11
3 Gelagar melintang, IWF.100.100.6.8. kg 91.74
3 Ikatan angin, baja siku L.50.50.5. kg 42.73
4 Plat penegar prol HC, tebal 10 mm kg 56.95
5 Plat sambung gelagar induk HC.340 (2 titik smb) kg 73.70
6 Plat penutup HC, 2 x (150 x 32) tebal 10 mm. kg 41.88
7 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa GS. ND. 200 mm m 16.00
2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 200 mm, plat baja 3 x 50 mm + baut mur. bh 7.00
4 Bend 45 all flange ND. 200 mm, steel bh 4.00
5 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ bh 2.00
6 Loose Flange ND. 200 mm, steel bh 8.00
7 Tee all flange ND. 200 x 100 mm, CI bh 1.00
8 Flange adaptor ND. 200 mm, CI bh 2.00
9
Flange socket ND. 100 mm, PVC RRJ bh 1.00
10
Gate Valve ND. 200 mm all flange, CI. bh 1.00
11
Street box Inside dia. 100 mm, CI. bh 2.00
12
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 200 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

185 Item Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m.


Paket :
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 15.48
3 Urugan tanah kembali m3 1.10
4 Pemadatan tanah perlapis 25 cm m3 1.10
5 Buangan tanah disekitar lokasi m3 14.37
6 Pasangan Batu, Spesi 1 : 4. m3 16.50
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 36.96
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 12.91
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 8.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF250.125.6.9. kg 1,805.60
3 Gelagar melintang, Canal 165.65.7,5.10 kg 394.80
3 Ikatan angin, baja siku L.50.50.5. kg 344.60
4 Plat penegar profil IWF kg 38.30
5 Plat sambung gelagar t = 9 mm kg 282.60
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 150 mm ASTM A120, t = 7 mm m 33.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur. bh 15.00
4 Bend 11 1/4 all flange ND. 150 mm, steel bh 4.00
5 Bend 22,5 all flange ND. 150 mm, steel bh 2.00
6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 2.00
7 Loose Flange ND. 150 mm, Steel bh 10.00
8
Tee all flange ND. 150 x 100 mm, CI bh 1.00
9
Flange adaptor ND. 150 mm, CI bh 2.00
10
Gate Valve ND. 150 mm all flange, CI. bh 1.00
11
Gate Valve ND. 75 mm all flange, CI. bh 1.00
12
Air Valve ND. 25 mm all flange, CI bh 1.00
13
Flange socket ND. 150 mm, PVC RRJ bh 1.00
14
Flange socket ND. 75 mm, PVC RRJ bh 1.00
15
Street box Inside dia. 100 mm, CI. bh 2.00
16
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

186 Item Jembatan Pipa, ND. 150 mm, Bentang = 15,00 m.


Paket :
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 8.00
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 4.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF250.125.6.9. kg 444.00
3 Plat dudukan pipa kg 34.50
4 Plat penegar profil IWF kg 58.50
5 Plat sambung gelagar t = 9 mm kg 37.50
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 150 mm ASTM A120, t = 7 mm m 20.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
5
Loose Flange ND. 150 mm, Steel bh 6.00
6
Tee all socket ND. 150x75 mm, CI bh 1.00
7
Flange adaptor ND. 150 mm, CI bh 2.00
8
Gate Valve ND. 150 mm all flange, CI. bh 1.00
9
Gate Valve ND. 75 mm all flange, CI. bh 1.00
10
Air Valve ND. 25 mm all flange, CI bh 1.00
11
Flange socket ND. 150 mm, PVC RRJ bh 1.00
12
Flange socket ND. 75 mm, PVC RRJ bh 1.00
13
Flange spigot ND. 150 mm, PVC bh 1.00
14
Flange spigot ND. 75 mm, PVC bh 1.00
15
Street box Inside dia. 100 mm, CI. bh 2.00
16
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

187 Item Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi Desa Jatiwangi, Patok 172.

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 4.80
3 Urugan tanah kembali m3 1.60
4 Pemadatan tanah perlapis 25 cm m3 1.60
5 Buangan tanah disekitar lokasi m3 3.20
6 Pasangan Batu, Spesi 1 : 4. m3 3.89
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 4.70
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 -
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 150 mm ASTM A120, t = 7 mm m 16.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Loose Flange ND. 150 mm, Steel bh 4.00
4 Bend 45 all flange ND. 150 mm, steel bh 2.00
5 Bend 45 flange spigot ND. 150 mm, steel bh 2.00
6 Bend 90 all socket ND. 75 mm, PVC bh 1.00
7 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
8 Tee all socket ND. 150x75 mm, CI bh 1.00
9 Flange adaptor ND. 150 mm, CI bh 1.00
10
Flange socket ND. 150 mm, PVC RRJ bh 1.00
11
Flange socket ND. 75 mm, PVC RRJ bh 1.00
12
Flange spigot ND. 150 mm, PVC bh 1.00
13
Flange spigot ND. 75 mm, PVC bh 1.00
14
Gate Valve ND. 150 mm all flange, CI. bh 1.00
15
Gate Valve ND. 75 mm all flange, CI. bh 1.00
16
Air Valve ND. 25 mm all flange, CI bh 1.00
17
Street Box Inside Dia. 150 mm, CI. bh 2.00
18
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

188 Item Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 4.80
3 Urugan tanah kembali m3 1.60
4 Pemadatan tanah perlapis 25 cm m3 1.60
5 Buangan tanah disekitar lokasi m3 3.20
6 Pasangan Batu, Spesi 1 : 4. m3 3.89
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 4.70
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 -
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 150 mm ASTM A120, t = 7 mm m 10.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Loose Flange ND. 150 mm, Steel bh 4.00
4 Bend 45 all flange ND. 150 mm, steel bh 2.00
5 Bend 45 flange spigot ND. 150 mm, steel bh 2.00
6 Bend 90 all socket ND. 75 mm, PVC bh 1.00
7 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
8 Tee all socket ND. 150x75 mm, CI bh 1.00
9 Flange adaptor ND. 150 mm, CI bh 1.00
10 Flange socket ND. 150 mm, PVC RRJ bh 1.00
11 Flange socket ND. 75 mm, PVC RRJ bh 1.00
12 Flange spigot ND. 150 mm, PVC bh 1.00
13 Flange spigot ND. 75 mm, PVC bh 1.00
14
Gate Valve ND. 150 mm all flange, CI. bh 1.00
15
Gate Valve ND. 75 mm all flange, CI. bh 1.00
16
Air Valve ND. 25 mm all flange, CI bh 1.00
17
Street Box Inside Dia. 150 mm, CI. bh 2.00
18
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

189 Item Jembatan Pipa, ND. 100 mm, Bentang = 12,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 10.00
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 2.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF200.1005,5.8. kg 213.00
3 Plat dudukan pipa kg 22.00
4 Plat penegar profil IWF kg -
5 Plat sambung gelagar t = 9 mm kg 15.00
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 18.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4 Bend 45 all flange ND. 100 mm, steel bh 4.00
5 Bend 90 all socket ND. 75 mm, PVC bh 1.00
6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
7 Loose Flange ND. 100 mm, Steel bh 6.00
8
Tee all socket ND. 100x75 mm, CI bh 1.00
9
Flange adaptor ND. 100 mm, CI bh 2.00
10
Gate Valve ND. 100 mm all flange, CI. bh 1.00
11
Gate Valve ND. 75 mm all flange, CI. bh 1.00
12
Air Valve ND. 25 mm all flange, CI bh 1.00
13
Flange socket ND. 100 mm, PVC RRJ bh 1.00
14
Flange socket ND. 75 mm, PVC RRJ bh 1.00
15
Flange spigot ND. 100 mm, PVC bh 1.00
16
Flange spigot ND. 75 mm, PVC bh 1.00
17
Street box Inside dia. 100 mm, CI. bh 2.00
18
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

190 Item Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 -
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 2.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF200.1005,5.8. kg 170.40
3 Plat dudukan pipa kg 16.70
4 Plat penegar profil IWF kg -
5 Plat sambung gelagar t = 9 mm kg 10.50
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 16.00
2
Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3
Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4
Bend 45 all flange ND. 100 mm, steel bh 4.00
5
Bend 90 all socket ND. 75 mm, PVC bh 1.00
6
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
7
Loose Flange ND. 100 mm, Steel bh 6.00
8
Tee all socket ND. 100x75 mm, CI bh 1.00
9
Flange adaptor ND. 100 mm, CI bh 2.00
10
Gate Valve ND. 100 mm all flange, CI. bh 1.00
11
Gate Valve ND. 75 mm all flange, CI. bh 1.00
12
Air Valve ND. 25 mm all flange, CI bh 1.00
13
Flange socket ND. 100 mm, PVC RRJ bh 1.00
14
Flange socket ND. 75 mm, PVC RRJ bh 1.00
15
Flange spigot ND. 100 mm, PVC bh 1.00
16
Flange spigot ND. 75 mm, PVC bh 1.00
17
Street box Inside dia. 100 mm, CI. bh 2.00
18
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

191 Item Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 -
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 2.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF200.100.5,5.8. kg 149.20
3 Plat dudukan pipa kg 16.70
4 Plat penegar profil IWF kg -
5 Plat sambung gelagar t = 9 mm kg 10.50
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 15.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4 Bend 45 all flange ND. 100 mm, steel bh 4.00
5 Bend 90 all socket ND. 75 mm, PVC bh 1.00
6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
7 Loose Flange ND. 100 mm, Steel bh 6.00
8 Tee all socket ND. 100x75 mm, CI bh 1.00
9 Flange adaptor ND. 100 mm, CI bh 2.00
10 Gate Valve ND. 100 mm all flange, CI. bh 1.00
11 Gate Valve ND. 75 mm all flange, CI. bh 1.00
12 Air Valve ND. 25 mm all flange, CI bh 1.00
13 Flange socket ND. 100 mm, PVC RRJ bh 1.00
14 Flange socket ND. 75 mm, PVC RRJ bh 1.00
15 Flange spigot ND. 100 mm, PVC bh 1.00
16 Flange spigot ND. 75 mm, PVC bh 1.00
17 Street box Inside dia. 100 mm, CI. bh 2.00
18 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

192 Item Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 -
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 2.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF200.100.5,5.8. kg 127.80
3 Plat dudukan pipa kg 13.20
4 Plat penegar profil IWF kg -
5 Plat sambung gelagar t = 9 mm kg 10.50
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 14.00
2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4 Bend 45 all flange ND. 100 mm, steel bh 4.00
5 Bend 90 all socket ND. 75 mm, PVC bh 1.00
6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
7 Loose Flange ND. 100 mm, Steel bh 6.00
8 Tee all socket ND. 100x75 mm, CI bh 1.00
9 Flange adaptor ND. 100 mm, CI bh 2.00
10 Gate Valve ND. 100 mm all flange, CI. bh 1.00
11 Gate Valve ND. 75 mm all flange, CI. bh 1.00
12 Air Valve ND. 25 mm all flange, CI bh 1.00
13 Flange socket ND. 100 mm, PVC RRJ bh 1.00
14 Flange socket ND. 75 mm, PVC RRJ bh 1.00
15 Flange spigot ND. 100 mm, PVC bh 1.00
16 Flange spigot ND. 75 mm, PVC bh 1.00
17 Street box Inside dia. 100 mm, CI. bh 2.00
18 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV

193 Item Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 3.00
3 Urugan tanah kembali m3 1.20
4 Pemadatan tanah perlapis 25 cm m3 1.20
5 Buangan tanah disekitar lokasi m3 1.80
6 Pasangan Batu, Spesi 1 : 4. m3 2.20
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 2.80
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 -
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 11.00
2 Pipa PVC ND. 50 mm, S.12.5 (RRJ) m 6.00
Loose Flange ND. 100 mm, Steel bh 4.00
Bend 45 all flange ND. 100 mm, steel bh 2.00
Bend 45 flange spigot ND. 100 mm, steel bh 2.00
Bend 90 all socket ND 50 mm PVC bh 1.00
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
Tee all socket ND 100 mm x 50 mm PVC bh 1.00
Flange adaptor ND. 100 mm, CI bh 1.00
3 Flange socket ND. 100 mm, PVC RRJ bh 1.00
4 Flange socket ND. 50 mm, PVC RRJ bh 1.00
5 Flange spigot ND. 100 mm, PVC bh 1.00
6 Flange spigot ND. 50 mm, PVC bh 1.00
7 Gate Valve ND. 100 mm all flange, CI. bh 1.00
8 Gate Valve ND. 50 mm all flange, CI. bh 1.00
9 Air Valve ND. 25 mm all flange, CI bh 1.00
10 Street Box Inside Dia. 150 mm, CI. bh 2.00
11 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

194 Item Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 3.00
3 Urugan tanah kembali m3 1.20
4 Pemadatan tanah perlapis 25 cm m3 1.20
5 Buangan tanah disekitar lokasi m3 1.80
6 Pasangan Batu, Spesi 1 : 4. m3 2.20
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 2.80
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 -
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 10.00
2 Pipa PVC ND. 50 mm, S.12.5 (RRJ) m 6.00
Loose Flange ND. 100 mm, Steel bh 4.00
Bend 45 all flange ND. 100 mm, steel bh 2.00
Bend 45 all flange ND. 100 mm, steel bh 2.00
Bend 90 all socket ND 50 mm PVC bh 1.00
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
Tee all socket ND 100 mm x 50 mm PVC bh 1.00
Flange adaptor ND. 100 mm, CI bh 1.00
3 Flange socket ND. 100 mm, PVC RRJ bh 1.00
4 Flange socket ND. 50 mm, PVC RRJ bh 1.00
5 Flange spigot ND. 100 mm, PVC bh 1.00
6 Flange spigot ND. 50 mm, PVC bh 1.00
7 Gate Valve ND. 100 mm all flange, CI. bh 1.00
8 Gate Valve ND. 50 mm all flange, CI. bh 1.00
9 Air Valve ND. 25 mm all flange, CI bh 1.00
10 Street Box Inside Dia. 150 mm, CI. bh 2.00
11 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

195 Item Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1
Setting Out dan penyiapan lokasi. ls 1.00
2
Galian tanah biasa m3 3.00
3
Urugan tanah kembali m3 1.20
4
Pemadatan tanah perlapis 25 cm m3 1.20
5
Buangan tanah disekitar lokasi m3 1.80
6
Pasangan Batu, Spesi 1 : 4. m3 2.20
7
Plesteran Spesi 1 : 2, tebal 15 mm. m2 2.80
8
Beton Bertulang K225, Pilar Jembatan 50/50. m3 -
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm m 9.00
2
Pipa PVC ND. 50 mm, S.12.5 (RRJ) m 6.00
3
Loose Flange ND. 100 mm, Steel bh 4.00
4
Bend 45 all flange ND. 100 mm, steel bh 2.00
5
Bend 45 flange spigot ND. 100 mm, steel bh 2.00
Bend 90 all socket ND 50 mm PVC
6 bh 1.00
7
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ bh 1.00
Tee all socket ND 100 mm x 50 mm PVC
8 bh 1.00
9
Flange adaptor ND. 100 mm, CI bh 1.00
10
Flange socket ND. 100 mm, PVC RRJ bh 1.00
11
Flange socket ND. 50 mm, PVC RRJ bh 1.00
12
Flange spigot ND. 100 mm, PVC bh 1.00
13
Flange spigot ND. 50 mm, PVC bh 1.00
14
Gate Valve ND. 100 mm all flange, CI. bh 1.00
15
Gate Valve ND. 50 mm all flange, CI. bh 1.00
16
Air Valve ND. 25 mm all flange, CI bh 1.00
17
Street Box Inside Dia. 150 mm, CI. bh 2.00
18
Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
III Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total III
Total I + II + III

196 Item Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m.


Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :

NO URAIAN BAHAN Satuan Volume


I Pekerjaan Tanah dan pasangan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 2.60
3 Urugan tanah kembali m3 0.65
4 Pemadatan tanah perlapis 25 cm m3 0.65
5 Buangan tanah disekitar lokasi m3 2.20
6 Pasangan Batu, Spesi 1 : 4. m3 1.25
7 Plesteran Spesi 1 : 2, tebal 15 mm. m2 -
8 Beton Bertulang K225, Pilar Jembatan 50/50. m3 0.78
camp. 1:2:3 baja U.24, 125 kg/m3.
Sub Total I
II Pekerjaan Pengadaan dan Pemasangan
Konstruksi Rangka Baja.
1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. set 2.00
baut 40 cm (dilas pada plat), mur M.22.
2 Gelagar induk IWF200.200.8.12 kg 748.50
3 Plat dudukan pipa kg 13.00
4 Profil Siku 60.60.6 kg 173.40
5 Plat sambung gelagar t = 9 mm kg 12.90
6 Biaya Erection Konstruksi. ls 1.00
Sub Total II
III Pekerjaan Pengadaan dan Pemasangan Pipa
dan Accessories.
1 Pipa Steel ND. 75 mm ASTM A120, t = 7 mm m 24.00
2 Pipa PVC ND. 50 mm, S.12.5 (RRJ) m 6.00
3 Klem pipa Dia. 75 mm, plat baja 3 x 50 mm + baut mur. bh 5.00
4 Bend 45 all flange ND.75 mm, steel bh 4.00
5 Bend 90 all socket ND. 75 mm, PVC bh 1.00
6 Bend 90 Socket/spigot ND. 50 mm, PVC.RRJ bh 1.00
7 Loose Flange ND. 75 mm, Steel bh 6.00
8 Tee all socket ND. 75x75 mm, CI bh 1.00
9 Flange adaptor ND. 75 mm, CI bh 2.00
10 Gate Valve ND. 75 mm all flange, CI. bh 1.00
11 Gate Valve ND. 50 mm all flange, CI. bh 1.00
12 Air Valve ND. 25 mm all flange, CI bh 1.00
13 Flange socket ND. 75 mm, PVC RRJ bh 2.00
14 Flange spigot ND. 75 mm, PVC bh 1.00
15 Flange spigot ND. 50 mm, PVC bh 1.00
16 Street box Inside dia. 100 mm, CI. bh 2.00
17 Pemasangan pipa, fitting & accessories termasuk ls 1.00
pengadaan baut, mur, ring, paking dan thrusblock.
Sub Total III
IV Pekerjaan lain-lain.
1 Pengecatan pipa dan konstruksi baja ls 1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). unit 2.00
Sub Total IV
Total I + II + III + IV
MELALUI SUNGAI

36,437,560

Harga Satuan Jumlah


[Rp] [Rp]

75,000 75,000
19,680 107,059
8,620 17,585
12,300 25,092
7,875 26,775
145,690 58,276
480,990 1,803,713
27,200 155,040

2,268,540

625,000 10,000,000
34,000 204,000
360,000 2,880,000
1,300,000 5,200,000
85,100 170,200
839,000 839,000
753,260 1,506,520
792,700 1,585,400
90,000 90,000
8,100,000 8,100,000
1,700,000 1,700,000
475,500 475,500
127,700 255,400
650,000 650,000

33,656,020

100,000 100,000
206,500 413,000
513,000
36,437,560

46,112,329
Harga Satuan Jumlah
[Rp] [Rp]

100,000 100,000
19,680 107,650
8,620 23,619
12,300 33,702
7,875 26,775
480,990 1,317,913
3,238,083 1,230,472

2,840,130

261,800 1,047,200

6,559 5,785,299

5,756 528,064
5,756 245,958
5,756 327,809
5,756 424,224
5,756 241,065
1,350,000 1,350,000
9,949,619

625,000 10,000,000
34,000 204,000
87,780 614,460
1,300,000 5,200,000
85,100 170,200
360,000 2,880,000
839,000 839,000
753,260 1,506,520
90,000 90,000
8,100,000 8,100,000
127,700 255,400
2,800,000 2,800,000

32,659,580

250,000 250,000
206,500 413,000
663,000
46,112,329
52,046,808

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,059
8,620 17,585
12,300 25,092
7,875 26,775
480,990 1,803,713
27,200 155,040

2,235,264

261,800 1,047,200

6,559 8,094,171

5,756 739,658
5,756 340,761
5,756 461,638
5,756 678,758
5,756 385,658
1,890,000 1,890,000
13,637,844

625,000 12,500,000
34,000 204,000
87,780 965,580
1,300,000 5,200,000
85,100 170,200
360,000 2,880,000
839,000 839,000
753,260 1,506,520
90,000 90,000
8,100,000 8,100,000
127,700 255,400
2,800,000 2,800,000

35,510,700

250,000 250,000
206,500 413,000
663,000
52,046,808

54,949,919

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,059
8,620 17,585
12,300 25,092
7,875 26,775
480,990 1,803,713
27,200 155,040

2,235,264

261,800 1,047,200

6,559 9,256,478

5,756 844,879
5,756 393,486
5,756 524,495
5,756 678,758
5,756 385,658
2,160,000 2,160,000
15,290,955

625,000 13,750,000
34,000 204,000
87,780 965,580
1,300,000 5,200,000
85,100 170,200
360,000 2,880,000
839,000 839,000
753,260 1,506,520
90,000 90,000
8,100,000 8,100,000
127,700 255,400
2,800,000 2,800,000

36,760,700

250,000 250,000
206,500 413,000
663,000
54,949,919

56,442,794

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,650
8,620 23,619
12,300 33,702
7,875 26,775
480,990 1,317,913
3,238,083 1,230,472

2,840,130

261,800 1,047,200

6,559 10,413,538

5,756 950,446
- -
- -
- -
- -
2,430,000 2,430,000
14,841,184

625,000 15,000,000
34,000 204,000
87,780 1,053,360
1,300,000 5,200,000
85,100 170,200
360,000 2,880,000
839,000 839,000
753,260 1,506,520
90,000 90,000
8,100,000 8,100,000
127,700 255,400
2,800,000 2,800,000

38,098,480

250,000 250,000
206,500 413,000
663,000
56,442,794

63,630,420

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,650
8,620 23,619
12,300 33,702
7,875 26,775
480,990 1,317,913
3,238,083 1,230,472

2,840,130

261,800 1,047,200

6,559 11,572,041

5,756 1,056,473
5,756 491,800
5,756 655,504
5,756 848,333
5,756 481,900
2,700,000 2,700,000
18,853,251

625,000 16,250,000
34,000 204,000
87,780 1,228,920
1,300,000 5,200,000
85,100 170,200
360,000 2,880,000
839,000 839,000
753,260 1,506,520
8,100,000 8,100,000
1,700,000 1,700,000
90,000 90,000
127,700 255,400
2,800,000 2,800,000

41,224,040

300,000 300,000
206,500 413,000
713,000
63,630,420

107,669,431

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 378,643
8,620 9,482
12,300 13,530
7,875 142,853
88,700 811,605
145,690 458,924
480,990 5,531,385
101,830 159,873
27,200 475,456
3,238,083 25,914,381

33,996,131

261,800 1,047,200

6,559 12,517,760

5,756 2,250,862
5,756 1,743,980
5,756 1,469,530
5,756 347,207
3,240,000 3,240,000
22,616,540

625,000 22,500,000
34,000 204,000
87,780 1,228,920

585,600 1,171,200
1,300,000 2,600,000
85,100 170,200
360,000 3,600,000
839,000 839,000
753,260 3,013,040
699,000 699,000
8,100,000 8,100,000
1,700,000 1,700,000
1,250,000 1,250,000
123,000 123,000
90,000 90,000
127,700 255,400
2,800,000 2,800,000

50,343,760

300,000 300,000
206,500 413,000
713,000
107,669,431

81,141,038

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 306,811
8,620 9,482
12,300 13,530
7,875 -
145,690 384,622
480,990 5,868,078
101,830 134,416
27,200 380,800
7,197,738

261,800 1,047,200

6,559 12,517,760

5,756 2,250,862
5,756 1,743,980
5,756 1,469,530
5,756 347,207
3,510,000 3,510,000
22,886,540

625,000 22,500,000
34,000 204,000
87,780 1,228,920

585,600 1,171,200
1,300,000 2,600,000
85,100 170,200
360,000 3,600,000
839,000 839,000
753,260 3,013,040
699,000 699,000
8,100,000 8,100,000
1,700,000 1,700,000
1,250,000 1,250,000
123,000 123,000
90,000 90,000
127,700 255,400
2,800,000 2,800,000

50,343,760

300,000 300,000
206,500 413,000
713,000
81,141,038

114,929,054

Harga Satuan Jumlah


[Rp] [Rp]
100,000 100,000
19,680 306,811
8,620 9,482
12,300 13,530
7,875 -
88,700 811,605
145,690 384,622
480,990 7,936,335
101,830 134,416
27,200 462,400
3,238,083 30,826,553

40,985,754

261,800 1,047,200

6,559 12,517,760

5,756 2,250,862
5,756 1,743,980
5,756 1,469,530
5,756 347,207
3,510,000 3,510,000
22,886,540

625,000 22,500,000
34,000 204,000
87,780 1,228,920

585,600 1,171,200
1,300,000 2,600,000
85,100 170,200
360,000 3,600,000
839,000 839,000
753,260 3,013,040
699,000 699,000
8,100,000 8,100,000
1,700,000 1,700,000
1,250,000 1,250,000
123,000 123,000
90,000 90,000
127,700 255,400
2,800,000 2,800,000

50,343,760

300,000 300,000
206,500 413,000
713,000
114,929,054

196,169,306

Harga Satuan Jumlah


[Rp] [Rp]

450,000 450,000
19,680 528,802
8,620 69,486
12,300 99,150
7,875 148,121
88,700 811,605
145,690 384,622
480,990 9,956,493
101,830 134,416
27,200 979,200
3,238,083 56,536,935

70,098,829

261,800 2,094,400

6,559 40,995,599

5,756 5,767,603
5,756 3,352,923
5,756 2,826,241
5,756 719,511
5,000,000 5,000,000
60,756,277

550,000 36,850,000
34,000 1,190,000
22,500 1,305,000

685,000 2,740,000
85,100 170,200
310,000 4,960,000
520,500 520,500
595,000 2,380,000
430,100 430,100
6,800,000 6,800,000
1,700,000 1,700,000
1,250,000 1,250,000
123,000 123,000
90,000 90,000
127,700 255,400
3,750,000 3,750,000

64,514,200

350,000 350,000
150,000 450,000
800,000
196,169,306

78,961,988

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 74,784
88,700 478,980
8,620 23,619
12,300 33,702
7,875 26,775
480,990 2,376,091
3,238,083 1,230,472

4,344,422

261,800 2,094,400

6,559 19,218,737

5,756 1,241,934
5,756 578,257
5,756 771,086
5,756 855,298
5,756 485,814
3,780,000 3,780,000
29,025,526

625,000 20,625,000
34,000 204,000
87,780 1,228,920
1,300,000 5,200,000
85,100 170,200
360,000 2,160,000
839,000 839,000
753,260 1,506,520
8,100,000 8,100,000
1,700,000 1,700,000
90,000 90,000
127,700 255,400
2,800,000 2,800,000

44,879,040

300,000 300,000
206,500 413,000
713,000
78,961,988

30,699,740

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,059
8,620 17,585
12,300 25,092
7,875 26,775
145,690 58,276
480,990 1,803,713
27,200 155,040

2,293,540

550,000 8,800,000
34,000 204,000
310,000 2,480,000
685,000 2,740,000
85,100 170,200
520,500 520,500
595,000 1,190,000
483,800 967,600
90,000 90,000
6,800,000 6,800,000
1,700,000 1,700,000
475,500 475,500
127,700 255,400
1,350,000 1,350,000

27,743,200

250,000 250,000
206,500 413,000
663,000
30,699,740

33,008,763

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 107,650
8,620 23,619
12,300 33,702
7,875 26,775
480,990 1,317,913
3,238,083 1,230,472

2,840,130

261,800 1,047,200

6,559 5,785,299

5,756 528,064
5,756 245,958
5,756 327,809
5,756 424,224
5,756 241,065
1,350,000 1,350,000
9,949,619

472,500 7,560,000
34,000 204,000
79,002 553,014
305,000 1,220,000
85,100 170,200
225,000 1,800,000
426,000 426,000
368,200 736,400
90,000 90,000
4,250,000 4,250,000
127,700 255,400
2,500,000 2,500,000

19,765,014

250,000 250,000
102,000 204,000
454,000
33,008,763

98,179,223

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 304,646
8,620 9,482
12,300 13,530
7,875 113,164
480,990 7,936,335
27,200 1,005,312
3,238,083 41,803,656

51,286,125

261,800 2,094,400

6,559 11,843,465
5,756 2,272,505
5,756 1,983,549
5,756 220,458
5,756 1,626,671
4,500,000 4,500,000
24,541,048

244,000 8,052,000
28,000 168,000
20,250 303,750
262,600 1,050,400
285,000 570,000
41,200 82,400
190,000 1,900,000
488,000 488,000
255,600 511,200
2,150,000 2,150,000
970,000 970,000
475,500 475,500
198,300 198,300
94,100 94,100
127,700 255,400
4,320,000 4,320,000

21,589,050

350,000 350,000
206,500 413,000
763,000
98,179,223

24,069,481

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 217,600
3,238,083 2,525,705

3,526,633

261,800 1,047,200

6,559 2,912,327
5,756 198,585
5,756 336,731
5,756 215,853
1,400,000 1,400,000
6,110,697

244,000 4,880,000
28,000 168,000
20,250 101,250
41,200 41,200
190,000 1,140,000
286,000 286,000
255,600 511,200
2,150,000 2,150,000
970,000 970,000
475,500 475,500
198,300 198,300
94,100 94,100
175,600 175,600
85,600 85,600
127,700 255,400
2,350,000 2,350,000

13,882,150

350,000 250,000
150,000 300,000
550,000
24,069,481

16,048,227

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 94,464
8,620 13,792
12,300 19,680
7,875 25,200
480,990 1,871,051
27,200 127,840
3,238,083 -

2,252,027

244,000 3,904,000
28,000 168,000
190,000 760,000
167,000 334,000
225,600 451,200
36,500 36,500
41,200 41,200
286,000 286,000
255,600 255,600
198,300 198,300
94,100 94,100
175,600 175,600
85,600 85,600
2,150,000 2,150,000
970,000 970,000
475,500 475,500
148,800 297,600
2,350,000 2,350,000

13,033,200

350,000 350,000
206,500 413,000
763,000
16,048,227

14,584,227

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 94,464
8,620 13,792
12,300 19,680
7,875 25,200
480,990 1,871,051
27,200 127,840
3,238,083 -

2,252,027

244,000 2,440,000
28,000 168,000
190,000 760,000
167,000 334,000
225,600 451,200
36,500 36,500
41,200 41,200
286,000 286,000
255,600 255,600
198,300 198,300
94,100 94,100
175,600 175,600
85,600 85,600
2,150,000 2,150,000
970,000 970,000
475,500 475,500
148,800 297,600
2,350,000 2,350,000

11,569,200

350,000 350,000
206,500 413,000
763,000
14,584,227

18,552,748

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 272,000
3,238,083 2,525,705

3,581,033

261,800 523,600

6,559 1,397,130
5,756 126,634
5,756 -
5,756 86,341
1,850,000 1,850,000
3,983,705

139,000 2,502,000
28,000 168,000
71,102 355,509
75,000 300,000
36,500 36,500
41,200 41,200
123,000 738,000
215,300 215,300
220,000 440,000
1,700,000 1,700,000
970,000 970,000
475,500 475,500
90,000 90,000
94,100 94,100
107,900 107,900
85,600 85,600
127,700 255,400
1,750,000 1,750,000

10,325,009

250,000 250,000
206,500 413,000
663,000
18,552,748

18,216,912

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 -
3,238,083 2,525,705

3,309,033

261,800 523,600

6,559 1,117,704
5,756 96,127
5,756 -
5,756 60,439
1,850,000 1,850,000
3,647,870

139,000 2,224,000
28,000 168,000
71,102 355,509
75,000 300,000
36,500 36,500
41,200 41,200
123,000 738,000
215,300 215,300
220,000 440,000
1,700,000 1,700,000
970,000 970,000
475,500 475,500
90,000 90,000
94,100 94,100
107,900 107,900
85,600 85,600
127,700 255,400
2,200,000 2,200,000

10,497,009

350,000 350,000
206,500 413,000
763,000
18,216,912

18,088,855

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 -
3,238,083 2,525,705

3,309,033

261,800 523,600

6,559 978,647
5,756 96,127
5,756 -
5,756 60,439
2,000,000 2,000,000
3,658,813

139,000 2,085,000
28,000 168,000
71,102 355,509
75,000 300,000
36,500 36,500
41,200 41,200
123,000 738,000
215,300 215,300
220,000 440,000
1,700,000 1,700,000
970,000 970,000
475,500 475,500
90,000 90,000
94,100 94,100
107,900 107,900
85,600 85,600
127,700 255,400
2,200,000 2,200,000

10,358,009

350,000 350,000
206,500 413,000
763,000
18,088,855

17,489,340

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 -
3,238,083 2,525,705

3,309,033
261,800 523,600

6,559 838,278
5,756 75,980
5,756 -
5,756 60,439
1,850,000 1,850,000
3,348,297

139,000 1,946,000
28,000 168,000
71,102 355,509
75,000 300,000
36,500 36,500
41,200 41,200
123,000 738,000
215,300 215,300
220,000 440,000
1,700,000 1,700,000
970,000 970,000
475,500 475,500
90,000 90,000
94,100 94,100
107,900 107,900
85,600 85,600
127,700 255,400
2,200,000 2,200,000

10,219,009

200,000 200,000
206,500 413,000
613,000
17,489,340

10,395,657

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 59,040
8,620 10,344
12,300 14,760
7,875 14,175
480,990 1,058,178
27,200 76,160
3,238,083 -

1,332,657

139,000 1,529,000
12,000 72,000
123,000 492,000
75,000 150,000
198,600 397,200
8,200 8,200
41,200 41,200
12,800 12,800
220,000 220,000
90,000 90,000
68,200 68,200
107,900 107,900
62,400 62,400
1,700,000 1,700,000
526,000 526,000
475,500 475,500
148,800 297,600
2,200,000 2,200,000

8,450,000

200,000 200,000
206,500 413,000
613,000
10,395,657

10,009,457

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 59,040
8,620 10,344
12,300 14,760
7,875 14,175
480,990 1,058,178
27,200 76,160
3,238,083 -
1,332,657

139,000 1,390,000
12,000 72,000
123,000 492,000
75,000 150,000
75,000 150,000
8,200 8,200
41,200 41,200
12,800 12,800
220,000 220,000
90,000 90,000
68,200 68,200
107,900 107,900
62,400 62,400
1,700,000 1,700,000
526,000 526,000
475,500 475,500
148,800 297,600
2,200,000 2,200,000

8,063,800

200,000 200,000
206,500 413,000
613,000
10,009,457

10,117,657

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 59,040
8,620 10,344
12,300 14,760
7,875 14,175
480,990 1,058,178
27,200 76,160
3,238,083 -

1,332,657

139,000 1,251,000
12,000 72,000
123,000 492,000
75,000 150,000
198,600 397,200
8,200 8,200
41,200 41,200
12,800 12,800
220,000 220,000
90,000 90,000
68,200 68,200
107,900 107,900
62,400 62,400
1,700,000 1,700,000
526,000 526,000
475,500 475,500
148,800 297,600
2,200,000 2,200,000

8,172,000

200,000 200,000
206,500 413,000
613,000
10,117,657

21,084,755

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 51,168
8,620 5,603
12,300 7,995
7,875 17,325
480,990 601,238
27,200 -
3,238,083 2,525,705

3,309,033

261,800 523,600

6,559 4,909,633
5,756 74,829
5,756 998,106
5,756 74,254
2,025,000 2,025,000
8,605,422

98,000 2,352,000
12,000 72,000
16,500 82,500
126,800 507,200
36,500 36,500
19,000 19,000
97,000 582,000
98,000 98,000
147,500 295,000
970,000 970,000
526,000 526,000
475,500 475,500
94,100 188,200
85,600 85,600
62,400 62,400
127,700 255,400
2,000,000 2,000,000

8,607,300

150,000 150,000
206,500 413,000
563,000
21,084,755
HARGA SATUAN UPAH DAN BAHAN BANGUNAN

A. HARGA SATUAN UPAH


HARGA
NO URAIAN SATUAN
[Rp]
1 Pekerja Orang/Hari 25,000
2 Pekerja semi terampil Orang/Hari 33,300
3 Pekerja terampil Orang/Hari 37,500
4 Tukang batu semi terampil Orang/Hari 38,300
5 Tukang batu Orang/Hari 38,300
6 Kepala tukang batu Orang/Hari 41,700
7 Tukang kayu semi terampil Orang/Hari 41,700
8 Tukang kayu Orang/Hari 42,500
9 Kepala tukang kayu Orang/Hari 45,800
10 Tukang cat/pelitur semi terampil Orang/Hari 41,700
11 Tukang cat/pelitur Orang/Hari 42,500
12 Kepala tukang cat/pelitur Orang/Hari 45,800
13 Tukang besi beton semi terampil Orang/Hari 41,700
14 Tukang besi beton Orang/Hari 45,800
15 Kepala tukang besi beton Orang/Hari 50,000
16 Tukang besi profil semi terampil Orang/Hari 42,500
17 Tukang besi profil Orang/Hari 45,800
18 Kepala tukang besi profil Orang/Hari 50,000
19 Tukang las tidak bersertifikat Orang/Hari 41,700
20 Tukang las Orang/Hari 50,000
21 Tukang pipa Orang/Hari 37,500
22 Mandor Orang/Hari 37,500
23 Operator semi terampil Orang/Hari 45,800
24 Operator terampil Orang/Hari 50,000
25 Pembantu operator Orang/Hari 50,000
26 Sopir Orang/Hari 50,000
27 Pembantu sopir Orang/Hari 33,300
28 Penjaga Malam Orang/Hari 33,300

B. BIAYA OPERASI DAN KEPEMILIKAN ALAT


HARGA
NO URAIAN SATUAN
[Rp]
1 Air Compressor 150 M3 per jam 15,600
2 Concrete Mixer 0,25 M3 per jam 17,900
3 Concrete Vibrator per jam 7,300
4 Dump Truck 3,5 Ton per jam 47,900
5 Hydraulic Excavator 1,3 M3 per jam 109,300
6 Jack Hammer per jam 15,600
7 Pickup Truck per jam 47,900
8 Plat Bed Truck 4 Ton per jam 50,000
9 Plate Vibrator Tamper per jam 4,200
10 Pressure Pump 20 Bar per jam 10,400
11 Stone Crusher 20 Ton/Jam per jam 36,400
12 Tandem Roller 6 - 10 Ton per jam 47,900
13 Tree Wheel Roller 51 HP per jam 21,900
14 Vibro Roller 600 Kg per jam 15,600
15 Water Pump (Dia. 5 Cm) per jam 10,400
16 Water Tank Truck 5000 Ltr per jam 31,200
17 Welding Mechine 500A per jam 16,700
18 Biaya Anggkutan per m3 22,800

Perusahaan Daerah Air Minum Tirta Galuh Ciamis


Direktur Utama
Ir. Triani PD
C. HARGA SATUAN BAHAN BANGUNAN.
HARGA
NO URAIAN SATUAN
[Rp]
1 Abu batu/Filler m3 139,900
2 Angkur baut M16 bh 29,200
3 Anyaman bambu belah m2 10,800
4 Asbes Eternit 100 x 100 cm bh 10,000
5 Aspal kg 5,800
6 Bahan cairan spay uji las (2 tube) unit 149,900
7 Bata merah lokal bh 400
8 Batu belah 15/20 m3 95,800
9 Batu bronjong m3 95,800
10 Batu koral kali m3 87,500
11 Batu pecah 0,5 - 1 m3 108,300
12 Batu pecah 1 - 2 m3 136,600
13 Batu pecah 2 - 3 m3 136,600
14 Baut mur M12 bh 29,200
15 Besi Plat kg 11,500
16 Besi profil Ex DN (SII) kg 6,000
17 Besi siku kg 6,000
18 Besi strip 3 mm kg 6,000
19 Besi tulangan polos kg 6,200
20 Cat besi kg 40,800
21 Coltar primer anti karat kg 12,900
22 Genteng bubungan bh 5,700
23 Genteng Pres bh 3,900
24 Karbit kg 6,100
25 Kawat beton kg 12,500
26 Kawat bronjong 3 mm kg 20,000
27 Kawat las listrik kg 11,100
28 Kayu bakar m3 82,500
29 Kayu bekisting m3 1,457,800
30 Kayu Borneo m3 2,633,900
31 Kayu dolken dia. 8 cm 4 m btg 25,000
32 Kayu Kamper medan m3 3,956,800
33 Kayu Multiplek 4 mm (122 x 242 cm) lbr 45,600
34 Kayu Papan Multiplek 16 mm lbr 228,200
35 Keramik 20x20 kelas I m2 62,500
36 Kerikil sungai tersaring m3 79,100
37 Kerikil sungai tidak disaring m3 75,000
38 Kertas ampelas besi bh 5,400
39 Kuas bh 11,200
40 Lem kayu kg 25,000
41 Meni besi kg 12,900
42 Minyak bakar ltr 2,400
43 Minyak cat kg 3,200
44 Minyak tanah ltr 1,700
45 Mozaik 30x30 cm bh 8,000
46 Paku biasa kg 10,800
47 Pasir beton m3 133,300
48 Pasir pasang m3 116,600
49 Pasir urug m3 78,300
50 Paving block natural 8 cm m2 65,800
57 Tanah merah m3 33,700

HARGA
NO URAIAN SATUAN
[Rp]

51 Pelumas ltr 10,800


52 Pipa PVC D Dia. 4" m 56,900
53 Porselin 10x10 cm dos 49,100
54 Portland cement zak 48,300
55 Premium ltr 4,500
56 Solar ltr 4,300
58 Tangki Vibreglass kapasitas 0.6 m3. unit 1,041,300
59 Tangki Vibreglass kapasitas 1 m3. unit 1,249,500
60 Terpentin kg 3,200
61 Tiner kg 37,500

Perusahaan Daerah Air Minum Tirta Galuh Ciamis


Direktur Utama

Ir. Triani PD
HARGA SATUAN UPAH DAN BAHAN BANGUNAN
PIPA DAN ACCESSORIES

D. HARGA SATUAN PIPA FITTING DAN ACCESSORIES.


HARGA
NO URAIAN SATUAN
[Rp]

1 Air Valve (Double) ND. 50 mm all flange, CI bh 1,250,000


2 Air Valve ND. 25 mm all flange, CI bh 475,500
3 Bend 11 1/4 all flange ND. 150 mm, steel bh 262,600
4 Bend 11 1/4 all flange ND. 300 mm, steel bh 585,600
5 Bend 11 1/4 Socket/spigot ND. 75 mm, PVC.RRJ unit 26,400
6 Bend 11 1/4 Socket/spigot ND. 100 mm, PVC.RRJ unit 41,000
7 Bend 11 1/4 Socket/spigot ND. 150 mm, PVC.RRJ unit 114,900
8 Bend 11 1/4 Socket/spigot ND. 200 mm, PVC.RRJ unit 199,900
9 Bend 11 1/4 Socket/spigot ND. 250 mm, PVC.RRJ unit 351,000
10 Bend 11 1/4 Socket/spigot ND. 300 mm, PVC.RRJ unit 563,700
11 Bend 11 1/4 Socket/spigot ND. 400 mm, PVC.RRJ unit 1,180,000
12 Bend 22,5 all flange ND. 150 mm, steel bh 285,000
13 Bend 22,5 all flange ND. 250 mm, steel bh 395,000
14 Bend 22,5 all flange ND. 300 mm, steel bh 625,000
15 Bend 22,5 Socket/spigot ND. 75 mm, PVC.RRJ unit 29,800
16 Bend 22,5 Socket/spigot ND. 100 mm, PVC.RRJ unit 46,400
17 Bend 22,5 Socket/spigot ND. 150 mm, PVC.RRJ unit 134,700
18 Bend 22,5 Socket/spigot ND. 200 mm, PVC.RRJ unit 228,800
19 Bend 22,5 Socket/spigot ND. 250 mm, PVC.RRJ unit 393,500
20 Bend 22,5 Socket/spigot ND. 300 mm, PVC.RRJ unit 679,700
21 Bend 22,5 Socket/spigot ND. 400 mm, PVC.RRJ unit 1,230,000
22 Bend 45 all flange ND. 100 mm, steel bh 75,000
23 Bend 45 all flange ND. 150 mm, steel bh 167,000
24 Bend 45 all flange ND. 200 mm, steel bh 305,000
25 Bend 45 all flange ND. 250 mm, steel bh 685,000
26 Bend 45 all flange ND. 300 mm, steel bh 1,300,000
27 Bend 45 flange spigot ND. 100 mm, steel bh 198,600
28 Bend 45 flange spigot ND. 150 mm, steel bh 225,600
29 Bend 45 Socket/spigot ND. 150 mm, PVC.RRJ unit 160,200
30 Bend 45 Socket/spigot ND. 200 mm, PVC.RRJ unit 371,300
31 Bend 45 Socket/spigot ND. 300 mm, PVC.RRJ unit 838,900
32 Bend 45 Socket/spigot ND. 400 mm, PVC.RRJ unit 1,360,000
33 Bend 90 all flange ND. 100 mm, steel bh 85,000
34 Bend 90 all flange ND. 150 mm, steel bh 230,000
35 Bend 90 all flange ND. 200 mm, steel bh 375,000
36 Bend 90 all flange ND. 250 mm, Steel bh 765,000
37 Bend 90 all flange ND. 300 mm CI. bh 1,750,000
38 Bend 90 ND. 150 mm, GS. bh 268,000
39 Bend 90 ND. 250 mm, GS. bh 386,200
40 Bend 90 ND. 300 mm GS. bh 650,000
41 Bend 90 ND. 350 mm Steel. bh 715,000
42 Bend 90 Socket/spigot ND. 50 mm, PVC.RRJ unit 19,000
43 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ unit 41,200
44 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ unit 85,100
45 Bend 90 Socket/spigot ND. 200 mm, PVC.RRJ unit 491,600
46 Bend 90 Socket/spigot ND. 250 mm, PVC.RRJ unit 706,300
47 Bend 90 Socket/spigot ND. 300 mm, PVC.RRJ unit 1,270,000
48 Bend 90 Socket/spigot ND. 400 mm, PVC.RRJ unit 1,420,000
49 Bend 90 all socket ND. 75 mm, PVC unit 36,500
50 Blind flange ND. 50 mm, PVC bh 51,000
51 Blind flange ND. 75 mm, PVC bh 65,000
52 Blind flange ND. 100 mm, PVC bh 76,100
53 Blind flange ND. 250 mm, Steel bh 178,500
54 Blind flange ND. 300 mm, Steel bh 228,300
47 Blind flange ND. 400 mm, Steel bh 345,000
55 Dop ND. 50 mm, PVC RRJ bh 14,800
HARGA
NO URAIAN SATUAN
[Rp]
48 Dop ND. 75 mm, PVC RRJ bh 27,000
56 Dop ND. 100 mm, PVC RRJ bh 52,400
49 Flange adaptor ND. 50 mm, CI bh 80,000
57 Flange adaptor ND. 75 mm, CI bh 147,500
50 Flange adaptor ND. 100 mm, CI bh 220,000
51 Flange adaptor ND. 150 mm, CI bh 255,600
52 Flange adaptor ND. 200 mm, CI bh 368,200
53 Flange adaptor ND. 250 mm, CI bh 595,000
54 Flange adaptor ND. 300 mm, CI bh 753,260
55 Flange adaptor ND. 350 mm, CI bh 1,030,000
56 Flange adaptor ND. 400 mm, CI bh 1,265,000
57 Flange socket ND. 50 mm, PVC RRJ bh 68,200
58 Flange socket ND. 75 mm, PVC RRJ bh 94,100
59 Flange socket ND. 100 mm, PVC RRJ bh 90,000
60 Flange socket ND. 150 mm, PVC RRJ bh 198,300
61 Flange socket ND. 200 mm, PVC RRJ bh 294,000
62 Flange socket ND. 250 mm, PVC RRJ bh 483,800
HARGA
NO URAIAN SATUAN
[Rp]
63 Flange socket ND. 300 mm, PVC RRJ bh 792,700
64 Flange socket ND. 350 mm, PVC RRJ bh 820,000
64 Flange socket ND. 400 mm, PVC RRJ bh 980,000
65 Flange spigot ND. 50 mm, PVC bh 62,400
65 Flange spigot ND. 75 mm, PVC bh 85,600
66 Flange spigot ND. 100 mm, PVC bh 107,900
67 Flange spigot ND. 150 mm, PVC bh 175,600
68 Flange spigot ND. 200 mm, PVC bh 263,400
69 Flange spigot ND. 250 mm, PVC bh 430,100
70 Flange spigot ND. 300 mm, PVC bh 699,000
71 Flange spigot ND. 400 mm, CI. bh 865,000
72 Gate Valve ND. 50 mm all flange, CI. bh 526,000
73 Gate Valve ND. 75 mm all flange, CI. bh 970,000
74 Gate Valve ND. 100 mm all flange, CI. bh 1,700,000
75 Gate Valve ND. 150 mm all flange, CI. bh 2,150,000
76 Gate Valve ND. 200 mm all flange, CI. bh 4,250,000
77 Gate Valve ND. 250 mm all flange, CI. bh 6,800,000
78 Gate Valve ND. 300 mm all flange, CI. bh 8,100,000
79 Gate Valve ND. 350 mm all flange, CI. bh 15,600,000
80 Gate Valve ND. 400 mm all flange, CI. bh 20,225,000
81 Giboult Joint ND. 50 mm, CI bh 76,200
82 Giboult Joint ND. 75 mm, CI bh 120,000
83 Giboult Joint ND. 100 mm, CI bh 178,600
84 Giboult Joint ND. 150 mm, CI bh 215,000
85 Giboult Joint ND. 200 mm, CI bh 312,500
86 Giboult Joint ND. 250 mm, CI bh 475,600
87 Giboult Joint ND. 300 mm, CI bh 605,000
88 Giboult Joint ND. 400 mm, CI bh 1,265,000
89 Klem pipa ND. 400 mm, plat baja 3 x 50 mm + baut mur. bh 96,558
90 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. bh 87,780
91 Klem pipa ND. 250 mm, plat baja 3 x 50 mm + baut mur. bh 22,500
92 Klem pipa ND. 200 mm, plat baja 3 x 50 mm + baut mur. bh 79,002
93 Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur. bh 20,250
94 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. bh 71,102
95 Loose Flange ND. 75 mm, Steel bh 97,000
96 Loose Flange ND. 100 mm, Steel bh 123,000
97 Loose Flange ND. 150 mm, Steel bh 190,000
98 Loose Flange ND. 200 mm, Steel bh 225,000
99 Loose Flange ND. 250 mm, Steel bh 310,000
100 Loose Flange ND. 300 mm, Steel bh 360,000
101 Loose Flange ND. 350 mm, Steel bh 400,000
102 Loose Flange ND. 400 mm, Steel bh 480,000
103 Baut, mur dan ring , baja hitam mutu tinggi bh 4,000
104 Pipa GS. ND. 200 mm m 472,500
105 Pipa GS. ND. 250 mm m 532,800
106 Pipa GS. ND. 300 mm m 665,800
107 Pipa PVC ND. 50 mm, S.8 (RRJ) m
108 Pipa PVC ND. 75 mm, S.8 (RRJ) m
109 Pipa PVC ND. 100 mm, S.8 (RRJ) m
110 Pipa PVC ND. 150 mm, S.8 (RRJ) m
111 Pipa PVC ND. 200 mm, S.8 (RRJ) m
112 Pipa PVC ND. 250 mm, S.8 (RRJ) m
113 Pipa PVC ND. 300 mm, S.8 (RRJ) m 389,200
114 Pipa PVC ND. 400 mm, S.8 (RRJ) m
115 Pipa PVC ND. 50 mm, S.10 (RRJ) m 15,000
116 Pipa PVC ND. 75 mm, S.10 (RRJ) m 26,100
117 Pipa PVC ND. 100 mm, S.10 (RRJ) m 40,400
118 Pipa PVC ND. 150 mm, S.10 (RRJ) m 85,250
119 Pipa PVC ND. 200 mm, S.10 (RRJ) m 140,000
120 Pipa PVC ND. 250 mm, S.10 (RRJ) m 210,000
121 Pipa PVC ND. 300 mm, S.10 (RRJ) m 333,250
122 Pipa PVC ND. 400 mm, S.10 (RRJ) m 564,100
123 Pipa PVC ND. 50 mm, S.12.5 (RRJ) m 12,000
HARGA
NO URAIAN SATUAN
[Rp]
124 Pipa PVC ND. 75 mm, S.12.5 (RRJ) m 28,000
125 Pipa PVC ND. 100 mm, S.12.5 (RRJ) m 34,000
126 Pipa PVC ND. 150 mm, S.12.5 (RRJ) m 72,000
127 Pipa PVC ND. 200 mm, S.12.5 (RRJ) m 114,000
128 Pipa PVC ND. 250 mm, S.12.5 (RRJ) m 179,000
129 Pipa PVC ND. 300 mm, S.12.5 (RRJ) m 230,000
130 Pipa PVC ND. 400 mm, S.12.5 (RRJ) m 534,000
131 Pipa Steel ND. 50 mm m 47,000
132 Pipa Steel ND. 75 mm m 98,000
133 Pipa Steel ND. 100 mm m 139,000
134 Pipa Steel ND. 150 mm m 244,000
135 Pipa Steel ND. 200 mm m 268,000
136 Pipa Steel ND. 250 mm m 550,000
137 Pipa Steel ND. 300 mm m 625,000
138 Pipa Steel ND. 350 mm m 815,000
139 Pipa Steel ND. 400 mm m 1,079,000
HARGA
NO URAIAN SATUAN
[Rp]
140 Pudle flange ND. 100 mm, steel tebal 3 mm bh 34,200
141 Pudle flange ND. 150 mm, steel tebal 3 mm bh 44,900
142 Pudle flange ND. 250 mm, steel tebal 3 mm bh 64,200
143 Pudle flange ND. 300 mm, steel tebal 5 mm bh 127,150
144 Pudle flange ND. 350 mm, steel tebal 5 mm bh 149,250
145 Pudle flange ND. 400 mm, steel tebal 5 mm bh 173,100
146 Reducer all Flange ND. 150x100 mm, CI unit 243,800
147 Reducer all Flange ND. 300x250 mm, CI unit 630,000
148 Reducer all Flange ND. 350x250 mm, CI unit 740,500
149 Reducer all Flange ND. 350x300 mm, CI bh 965,000
150 Reducer all Flange ND. 400x300 mm, CI unit 1,354,000
151 Reducer all Socket ND. 400x350 mm, CI unit 1,468,000
152 Reducer all Socket ND. 75x50 mm, PVC.RRJ unit 30,700
153 Reducer all Socket ND. 100x50 mm, PVC.RRJ unit 43,700
154 Reducer all Socket ND. 100x75 mm, PVC.RRJ unit 45,000
155 Reducer all Socket ND. 150x100 mm, PVC.RRJ unit 84,000
156 Reducer all Socket ND. 150x75 mm, PVC.RRJ unit 80,200
157 Reducer all Socket ND. 200x100 mm, PVC.RRJ unit 130,800
158 Reducer all Socket ND. 200x150 mm, PVC.RRJ unit 134,200
159 Reducer all Socket ND. 250x150 mm, PVC.RRJ unit 223,400
160 Reducer all Socket ND. 250x200 mm, PVC.RRJ unit 234,900
161 Reducer all Socket ND. 300x200 mm, PVC.RRJ unit 377,400
162 Reducer all Socket ND. 300x250 mm, PVC.RRJ unit 386,800
163 Reducer all Socket ND. 350x250 mm, PVC.RRJ unit 510,000
164 Street box Inside dia. 100 mm, CI. bh 127,700
165 Street box Inside dia. 150 mm, CI. bh 148,800
166 Tee all flange ND. 100 x 100 mm, CI bh 136,300
167 Tee all flange ND. 150 x 75 mm, CI bh 320,000
168 Tee all flange ND. 150 x 100 mm, CI bh 488,000
169 Tee all flange ND. 150 x 150 mm, CI bh 424,500
170 Tee all flange ND. 200 x 100 mm, CI bh 426,000
171 Tee all flange ND. 200 x 150 mm, CI bh 595,000
172 Tee all flange ND. 250 x 100 mm, CI bh 520,500
173 Tee all flange ND. 250 x 250 mm, CI bh 815,000
174 Tee all flange ND. 300 x 100 mm, CI bh 839,000
175 Tee all flange ND. 300 x 150 mm, CI bh 866,000
176 Tee all flange ND. 300 x 300 mm CI. bh 912,500
177 Tee all flange ND. 350 x 250 mm CI. bh 910,000
178 Tee all flange ND. 350 x 350 mm CI. bh 965,000
179 Tee all socket ND. 75x75 mm, CI bh 98,000
180 Tee all socket ND. 100x75 mm, CI bh 215,300
181 Tee all socket ND. 150x75 mm, CI bh 286,000
182 Tee all socket ND. 200x100 mm, CI bh 326,800
183 Tee all socket ND. 300x100 mm, CI bh 564,000
184 Tee all socket ND. 300x50 mm, CI bh 386,000
185 Tee all socket ND. 400x400 mm, CI bh 768,000
186 Tee double socket and flange end ND. 100x100 mm, PVC bh 380,000
187 Tee double socket and flange end ND. 100x50 mm, PVC bh 260,000
188 Tee double socket and flange end ND. 100x75 mm, PVC bh 325,000
189 Tee double socket and flange end ND. 150x100 mm, PVC bh 426,000
190 Tee double socket and flange end ND. 150x75 mm, PVC bh 375,000
191 Tee double socket and flange end ND. 200x100 mm, PVC bh 510,000
192 Tee double socket and flange end ND. 250x250 mm, PVC bh 1,125,000
193 Tee double socket and flange end ND. 50x50 mm, PVC bh 76,000
194 Tee double socket and flange end ND. 75x50 mm, PVC bh 110,000
195 Tee double socket and flange end ND. 75x75 mm, PVC bh 146,000
196 Tee Y all flange ND. 300 x 300 mm CI. bh 1,145,000
197 Wall pipe all flange ND. 300 mm CI. bh 760,800
198 Wall pipe all flange ND. 350 mm CI. bh 895,600
199 Water meter 1/2" unit 145,750
200 Water meter induk ND. 50 mm unit 8,200,000
HARGA
NO URAIAN SATUAN
[Rp]
201 Water meter induk ND. 75 mm unit 9,750,000
202 Water meter induk ND. 100 mm unit 11,150,000
203 Water meter induk ND. 150 mm unit 19,800,000
204 Water meter induk ND. 200 mm unit 22,200,000
205 Water meter induk ND. 250 mm unit 38,400,000
206 Water meter induk ND. 300 mm unit 48,000,000
Item : TAPING POINT
Paket :
Lokasi :

Harga Satuan Jumlah


NO URAIAN BAHAN Satuan Volume
[Rp] [Rp]

Kebutuhan Accessories
- Tee all flange 250 x 250 bh 1.00 729,000.00 729,000.00
- Gate Valve dia 250 mm bh 3.00 8,022,000.00 24,066,000.00
- Pipa Steel dia 250 mm bh 18.00 385,000.00 6,930,000.00
- loose Flange dia 250 mm bh 5.00 520,000.00 2,600,000.00
- Flange Socket dia 250 mm bh 2.00 422,600.00 845,200.00

Jumlah 35,170,200.00
PEKERJAAN PERLINTASAN PIPA MELALAUI JALAN

CROSSING JALAN BOR HORIZONTAL

197 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 50,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 21.00
3 Urugan tanah kembali m3 19.95
4 Urugan pasir dipadatkan m3 18.95
5 Pemadatan tanah perlapis 25 cm m3 19.95
6 Pemasangan turap kayu pengaman galian 1.5 m m1 8.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 3.00
3 Biaya operasi Pompa Air jam 16.00
4 Tukang ahli bor oh 3.00
5 Tukang pipa oh 2.00
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 400 mm m 50.00
2 Loose flange ND. 400 mm, Steel bh 4.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

198 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 8.40
3 Urugan tanah kembali m3 7.98
4 Urugan pasir dipadatkan m3 7.58
5 Pemadatan tanah perlapis 25 cm m3 7.98
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00
II Pekerjaan Pengeboran Horisontal, L 2.5 m
1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 3.00
3 Biaya operasi Pompa Air jam 16.00
4 Tukang ahli bor oh 3.00
5 Tukang pipa oh 2.00
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 400 mm m 20.00
2 Loose flange ND. 400 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

199 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 8.40
3 Urugan tanah kembali m3 7.98
4 Urugan pasir dipadatkan m3 7.58
5 Pemadatan tanah perlapis 25 cm m3 7.98
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 300 mm m 15.00
2 Loose flange ND. 300 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV
200 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 18,00 m
Paket :
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 18.00
3 Urugan tanah kembali m3 17.10
4 Urugan pasir dipadatkan m3 16.25
5 Pemadatan tanah perlapis 25 cm m3 17.10
6 Pemasangan turap kayu pengaman galian 1.5 m m1 27.00

II Pekerjaan Pengeboran Horisontal


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) hari 20.00
3 Biaya Pengeboran meter 18.00
4 Biaya operasi Pompa Air jam 24.00
5 Tukang ahli bor oh 2.00
6 Tukang pipa oh 2.00
7 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 300 mm m 18.00
2 Loose flange ND. 300 mm, Steel bh 2.00
3 Pemasangan Thrusblock bh 2.00
4 Flange socket ND. 300 mm bh 2.00

IV Pek. Lain-lain.
Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

201 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m
Paket :
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 12.00
3 Urugan tanah kembali m3 8.40
4 Urugan pasir dipadatkan m3 4.20
5 Pemadatan tanah perlapis 25 cm m3 8.40
6 Pemasangan turap kayu pengaman galian 1.5 m m1 8.00

II Pekerjaan Pengeboran Horisontal


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) hari 20.00
3 Biaya Pengeboran meter 18.00
4 Biaya operasi Pompa Air jam 24.00
5 Tukang ahli bor oh 2.00
6 Tukang pipa oh 2.00
7 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 100 mm m 10.00
2 Loose flange ND. 100 mm, Steel bh 2.00
3 Pemasangan Thrusblock bh 2.00
4 Flange socket ND. 100 mm bh 2.00

IV Pek. Lain-lain.
Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

202 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 8.40
3 Urugan tanah kembali m3 7.98
4 Urugan pasir dipadatkan m3 7.58
5 Pemadatan tanah perlapis 25 cm m3 7.98
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 250 mm m 15.00
2 Loose flange ND. 250 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00
Total I + II + III + IV

203 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 250 mm m 12.00
2 Loose flange ND. 250 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

204 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 250 mm m 10.00
2 Loose flange ND. 250 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

205 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 8.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 200 mm m 15.00
2 Loose flange ND. 200 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

206 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 7.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m 10.00
2 Loose flange ND. 150 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

207 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 25,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 1.75
3 Urugan tanah kembali m3 1.66
4 Urugan pasir dipadatkan m3 1.58
5 Pemadatan tanah perlapis 25 cm m3 1.66
6 Pemasangan turap kayu pengaman galian 1.5 m m1 5.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 7.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m 25.00
2 Loose flange ND. 150 mm, Steel bh 6.00
3 Pemasangan Thrusblock m3 2.00

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

208 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 12.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 7.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m 10.00
2 Loose flange ND. 150 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

209 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 9.00
4 Tukang ahli bor oh 1.50
5 Tukang pipa oh 1.50
6 Pekerja oh 6.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m 7.00
2 Loose flange ND. 150 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

210 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 9.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 6.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 100 mm m 10.00
2 Loose flange ND. 100 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00
Total I + II + III + IV

211 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 9.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 6.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 100 mm m 7.00
2 Loose flange ND. 100 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

212 Item Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Galian tanah biasa m3 5.60
3 Urugan tanah kembali m3 5.32
4 Urugan pasir dipadatkan m3 5.05
5 Pemadatan tanah perlapis 25 cm m3 5.32
6 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pekerjaan Pengeboran Horisontal, L 2.5 m


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) ah 2.00
3 Biaya operasi Pompa Air jam 9.00
4 Tukang ahli bor oh 2.00
5 Tukang pipa oh 1.50
6 Pekerja oh 5.00

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 100 mm m 10.00
2 Loose flange ND. 100 mm, Steel bh 2.00
3 Pemasangan Thrusblock m3 0.20

IV Pengadaan Lain-lain.
2 Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00

Total I + II + III + IV

CROSSING BIASA

213 Item Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 7.20
3 Galian tanah biasa m3 8.64
4 Urugan tanah kembali m3 6.36
5 Urugan pasir dipadatkan m3 2.28
6 Pemadatan tanah perlapis 25 cm m3 6.36
7 Pemasangan turap kayu pengaman galian 1.5 m m1 3.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 300 mm m3 6.00
2 Bend 90 all flange ND. 300 mm CI. unit 2.00
3 Loose flange ND. 300 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 48.00
3 Perbersihan akhir ls 1.00
Total I + II + III + IV

214 Item Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 6.00
3 Galian tanah biasa m3 7.20
4 Urugan tanah kembali m3 5.30
5 Urugan pasir dipadatkan m3 1.90
6 Pemadatan tanah perlapis 25 cm m3 5.30
7 Pemasangan turap kayu pengaman galian 1.5 m m1 4.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 300 mm m3 5.00
2 Bend 90 all flange ND. 300 mm CI. unit 2.00
3 Loose flange ND. 300 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 48.00
3 Perbersihan akhir ls 1.00
Total I + II + III + IV

215 Item Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 6.00
3 Galian tanah biasa m3 5.76
4 Urugan tanah kembali m3 4.24
5 Urugan pasir dipadatkan m3 1.52
6 Pemadatan tanah perlapis 25 cm m3 4.24
7 Pemasangan turap kayu pengaman galian 1.5 m m1 2.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 300 mm m3 4.00
2 Bend 90 all flange ND. 300 mm CI. unit 2.00
3 Loose flange ND. 300 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 48.00
3 Perbersihan akhir ls 1.00
Total I + II + III + IV

216 Item Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 4.80
3 Galian tanah biasa m3 5.76
4 Urugan tanah kembali m3 3.86
5 Urugan pasir dipadatkan m3 1.90
6 Pemadatan tanah perlapis 25 cm m3 3.86
7 Pemasangan turap kayu pengaman galian 1.5 m m1 2.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 250 mm m3 4.00
2 Bend 90 ND. 250 mm, GS. unit 2.00
3 Flange adaptor ND. 250 mm, CI bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 48.00
3 Perbersihan akhir ls 1.00
Total I + II + III

217 Item Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 18.00
3 Galian tanah biasa m3 21.60
4 Urugan tanah kembali m3 19.70
5 Urugan pasir dipadatkan m3 1.90
6 Pemadatan tanah perlapis 25 cm m3 19.70
7 Pemasangan turap kayu pengaman galian 1.5 m m1 6.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m3 15.00
2 Bend 90 all flange ND. 150 mm, Steel unit 2.00
3 Loose flange ND. 250 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 48.00
3 Perbersihan akhir ls 1.00
Total I + II + III
218 Item Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 7.20
3 Galian tanah biasa m3 8.64
4 Urugan tanah kembali m3 6.36
5 Urugan pasir dipadatkan m3 2.28
6 Pemadatan tanah perlapis 25 cm m3 6.36
7 Pemasangan turap kayu pengaman galian 1.5 m m1 6.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 150 mm m3 6.00
2 Bend 90 all flange ND. 150 mm, Steel unit 2.00
3 Loose flange ND. 250 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 18.00
3 Perbersihan akhir ls 1.00
Total I + II + III

219 Item Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m
Paket Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi :
NO URAIAN BAHAN Satuan Volume
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00
2 Bongkaran perkerasan Jalan kelas III m2 4.20
3 Galian tanah biasa m3 7.92
4 Urugan tanah kembali m3 5.64
5 Urugan pasir dipadatkan m3 2.28
6 Pemadatan tanah perlapis 25 cm m3 5.64
7 Pemasangan turap kayu pengaman galian 1.5 m m1 2.00

II Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 50 mm m3 6.00
2 Bend 90 all flange ND. 50 mm, Steel unit 2.00
3 Loose flange ND. 250 mm, Steel bh 2.00
4 Pemasangan Thrusblock m3 0.20

III Pengadaan Lain-lain.


1 Transportasi alat ke lokasi pekerjaan. ls 1.00
2 Biaya operasi Pompa Air jam 18.00
3 Perbersihan akhir ls 1.00
Total I + II + III
ALAUI JALAN

64,996,555

Harga Satuan Jumlah


[Rp] [Rp]

250,000 250,000
19,680 413,280
8,620 171,969
101,830 1,929,933
12,300 245,385
50,670 405,360

1,500,000 1,500,000
350,000 1,050,000
10,400 166,400
25,000 75,000
37,500 75,000
25,000 200,000

1,079,000 53,950,000
480,000 1,920,000
721,137 144,227

2,500,000 2,500,000

64,996,555

24,981,864

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 165,312
8,620 68,788
101,830 771,973
12,300 98,154
50,670 152,010
100,000 100,000
50,000 150,000
10,400 166,400
25,000 75,000
37,500 75,000
25,000 200,000

1,079,000 21,580,000
480,000 960,000
721,137 144,227

250,000 250,000

24,981,864

12,351,514

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 165,312
8,620 68,788
101,830 771,973
12,300 98,154
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 200,000

625,000 9,375,000
360,000 720,000
721,137 144,227

200,000 200,000

12,351,514
31,514,290

Harga Satuan Jumlah


[Rp] [Rp]

250,000 250,000
19,680 354,240
8,620 147,402
101,830 1,654,228
12,300 210,330
50,670 1,368,090

1,500,000 1,500,000
260,000 5,200,000
350,000 6,300,000
10,400 249,600
25,000 50,000
37,500 75,000
25,000 200,000

625,000 11,250,000
360,000 720,000
75,000 150,000
792,700 1,585,400

250,000 250,000

31,514,290

6,785,534

Harga Satuan Jumlah


[Rp] [Rp]

250,000 250,000
19,680 236,160
8,620 72,408
101,830 427,686
12,300 103,320
50,670 405,360
500,000 500,000
50,000 1,000,000
65,000 1,170,000
10,400 249,600
25,000 50,000
37,500 75,000
25,000 200,000

139,000 1,390,000
123,000 246,000
65,000 130,000
90,000 180,000

100,000 100,000

6,785,534

11,176,514

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 165,312
8,620 68,788
101,830 771,973
12,300 98,154
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 200,000

550,000 8,250,000
310,000 620,000
721,137 144,227

250,000 250,000
11,176,514

9,108,439

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 200,000

550,000 6,600,000
310,000 620,000
721,137 144,227

200,000 200,000

9,108,439

8,058,439

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 200,000

550,000 5,500,000
310,000 620,000
721,137 144,227

250,000 250,000

8,058,439

6,358,439

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 200,000

268,000 4,020,000
225,000 450,000
721,137 144,227

200,000 200,000

6,358,439

4,683,439
Harga Satuan Jumlah
[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 175,000

244,000 2,440,000
190,000 380,000
721,137 144,227

200,000 200,000

4,683,439

13,521,722

Harga Satuan Jumlah


[Rp] [Rp]

250,000 250,000
19,680 34,440
8,620 14,331
101,830 160,828
12,300 20,449
50,670 253,350

750,000 750,000
1,250,000 2,500,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 175,000
244,000 6,100,000
190,000 1,140,000
721,137 1,442,274

450,000 450,000

13,521,722

4,633,439

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 124,800
25,000 50,000
37,500 56,250
25,000 175,000

244,000 2,440,000
190,000 380,000
721,137 144,227

150,000 150,000

4,633,439

3,932,739

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 93,600
25,000 37,500
37,500 56,250
25,000 150,000

244,000 1,708,000
190,000 380,000
721,137 144,227

250,000 250,000

3,932,739

3,393,239

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 93,600
25,000 50,000
37,500 56,250
25,000 150,000

139,000 1,390,000
123,000 246,000
721,137 144,227

150,000 150,000
3,393,239

3,076,239

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 93,600
25,000 50,000
37,500 56,250
25,000 150,000

139,000 973,000
123,000 246,000
721,137 144,227

250,000 250,000

3,076,239

3,468,239

Harga Satuan Jumlah


[Rp] [Rp]

25,000 25,000
19,680 110,208
8,620 45,858
101,830 514,649
12,300 65,436
50,670 152,010

100,000 100,000
50,000 100,000
10,400 93,600
25,000 50,000
37,500 56,250
25,000 125,000

139,000 1,390,000
123,000 246,000
721,137 144,227

250,000 250,000

3,468,239

9,792,392

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 141,696
19,680 170,035
8,620 54,823
101,830 232,172
12,300 78,228
50,670 152,010

625,000 3,750,000
1,750,000 3,500,000
360,000 720,000
721,137 144,227

150,000 150,000
10,400 499,200
100,000 100,000
9,792,392

9,105,236

Harga Satuan Jumlah


[Rp] [Rp]
100,000 100,000
19,680 118,080
19,680 141,696
8,620 45,686
101,830 193,477
12,300 65,190
50,670 202,680

625,000 3,125,000
1,750,000 3,500,000
360,000 720,000
721,137 144,227

150,000 150,000
10,400 499,200
100,000 100,000
9,105,236

8,289,687

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
19,680 118,080
19,680 113,357
8,620 36,549
101,830 154,782
12,300 52,152
50,670 101,340

625,000 2,500,000
1,750,000 3,500,000
360,000 720,000
721,137 144,227

150,000 150,000
10,400 499,200
100,000 100,000
8,289,687

5,739,216
Harga Satuan Jumlah
[Rp] [Rp]

100,000 100,000
19,680 94,464
19,680 113,357
8,620 33,273
101,830 193,477
12,300 47,478
50,670 101,340

550,000 2,200,000
386,200 772,400
595,000 1,190,000
721,137 144,227

150,000 150,000
10,400 499,200
100,000 100,000
5,739,216

8,664,736

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
88,700 1,596,600
19,680 425,088
8,620 169,814
101,830 193,477
12,300 242,310
50,670 304,020

244,000 3,660,000
230,000 460,000
310,000 620,000
721,137 144,227

150,000 150,000
10,400 499,200
100,000 100,000
8,664,736
4,703,346

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
88,700 638,640
19,680 170,035
8,620 54,823
101,830 232,172
12,300 78,228
50,670 304,020

244,000 1,464,000
230,000 460,000
310,000 620,000
721,137 144,227

150,000 150,000
10,400 187,200
100,000 100,000
4,703,346

2,527,334

Harga Satuan Jumlah


[Rp] [Rp]

100,000 100,000
88,700 372,540
19,680 155,866
8,620 48,617
101,830 232,172
12,300 69,372
50,670 101,340

47,000 282,000
32,000 64,000
310,000 620,000
721,137 144,227

75,000 75,000
10,400 187,200
75,000 75,000
2,527,334
Item Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m
Paket :
Lokasi :
Harga Satuan Jumlah
NO URAIAN BAHAN Satuan Volume
[Rp] [Rp]
I Pekerjaan Tanah dan Persiapan
1 Setting Out dan penyiapan lokasi. ls 1.00 250,000 250,000
2 Galian tanah biasa m3 12.00 19,680 236,160
3 Urugan tanah kembali m3 8.40 #N/A #N/A
4 Urugan pasir dipadatkan m3 4.20 #N/A #N/A
5 Pemadatan tanah perlapis 25 cm m3 8.40 #N/A #N/A
6 Pemasangan turap kayu pengaman galian 1.5 m m1 8.00 #N/A #N/A

II Pekerjaan Pengeboran Horisontal


1 Transportasi alat ke lokasi pekerjaan. ls 1.00 500,000 500,000
2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) hari 20.00 50,000 1,000,000
3 Biaya Pengeboran meter 18.00 65,000 1,170,000
4 Biaya operasi Pompa Air jam 24.00 5,729 137,492
5 Tukang ahli bor oh 2.00 25,000 50,000
6 Tukang pipa oh 2.00 #N/A #N/A
7 Pekerja oh 8.00 #N/A #N/A

III Pengadaan dan Pemasangan Pipa & Acc.


1 Pipa Steel ND. 100 mm m 10.00 139,000 1,390,000
2 Loose flange ND. 100 mm, Steel bh 2.00 123,000 246,000
3 Pemasangan Thrusblock bh 2.00 65,000 130,000
4 Flange socket ND. 100 mm bh 2.00 90,000 180,000

IV Pek. Lain-lain.
Perbaikan dan perbersihan saluran akibat pekerjaan. ls 1.00 100,000 100,000

Total I + II + III + IV #N/A


REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN


A Pekerjaan Persiapan, Tanah dan Bongkaran
1 Pembersihan lokasi secara manual 1M2
2 Mengukur dan memasang bouwplank 1M1
3 Galian tanah biasa 1M3
4 Galian tanah keras 1M3
5 Galian tanah berbatu 1M3
6 Galian dasar sungai berbatu 1M3
7 Urugan tanah kembali 1M3
8 Pemadatan tanah perlapis 25 cm 1M3
9 Urugan tanah didatangkan dipadatkan 1M3
10 Urugan pasir dipadatkan 1M3
11 Buangan tanah disekitar lokasi 1M3
12 Pemasangan turap kayu pengaman galian 1.5 m 1 M1
13 Bongkaran beton masif dan pasangan batu. 1 M3
14 Bongkaran perkerasan jalan kelas III (40 cm) 1 M2
15 Bongkaran perkerasan jalan kelas I (15 cm) 1 M2
16 Bongkaran perkerasan Paving Block tebal 8 cm. 1 M2

B Pekerjaan Pasangan.
17 Pasangan Batu kosong 1 M3
18 Pasangan Batu Bronjong. 1 m3
19 Pasangan Batu, Spesi 1 : 4. 1 m3
20 Pasangan Batu, Spesi 1 : 3. 1 m3
21 Pasangan Bata, Spesi 1 : 4. 1 m3
22 Plesteran Spesi 1 : 2, tebal 10 mm. 1 m2
23 Plesteran Spesi 1 : 2, tebal 15 mm. 1 m2
24 Siaran, Spesi 1 : 1, tebal 10 mm. 1 m2
25 Pasang Keramik 20x20 cm 1 m2
26 Pasang lantai Mozaik 30x30 cm 1 m2
27 Pasang Porselin 10x10 cm 1 m2

C Pekerjaan Beton
28 Adukan Beton, Campuran 1:2:2,5. (K225) 1 m3
29 Adukan Beton, Campuran 1:2:3. (K175) 1 m3
30 Adukan Beton, Campuran 1:2:5. (K125) 1 m3
31 Pembesian tulangan beton, mutu baja U24. 1 Kg.
32 Cetakan Beton (non eksposed). 1 M2
33 Cetakan Beton (eksposed). 1 M2
34 Perancah tinggi 3,00 m. 1 M2
35 Beton Bertulang K225, Pilar Jembatan 50/50. 1 M3
36 Beton Bertulang K225, Support pipa 30/30. 1 M3
37 Beton Bertulang K225, Kepala Pilar Jembatan 50/130. 1 M3
38 Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm) 1 M3
39 Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3. 1 M3
40 Plat lantai beton bertulang, K225 baja U24 (103 kg/m3) 1 M3
41 Plat lantai beton bertulang, K225 baja U24 (129 kg/m3) 1 M3
42 Plat lantai beton bertulang, K225 baja U24 (168 kg/m3) 1 M3
43 Plat lantai beton bertulang, K225 baja U24 (183 kg/m3) 1 M3
44 Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3) 1 M3
45 Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3) 1 M3
46 Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3) 1 M3
47 Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3) 1 M3
48 Kolom beton bertulang, K225 baja U24 (152 kg/m3) 1 M3
49 Balok beton bertulang, K225 baja U24 (165 kg/m3) 1 M3
50 Sloof beton bertulang, K225 baja U24 (174 kg/m3) 1 M3
51 Sloof beton bertulang, K175 baja U24 (148 kg/m3) 1 M3
52 Kolom/balok ringbalk, K175 baja U24 (148 kg/m3) 1 M3
53 Plat Atap beton bertulang, K225 baja U24 (90 kg/m3) 1 M3
54 Plat Atap beton bertulang, K225 baja U24 (189 kg/m3) 1 M3
55 Lisplank beton bertulang, K175 baja U24 (90 kg/m3) 1 M3

D Pekerjaan Konstruksi Baja

56 Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart) 1 M3
57 Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah). 1 M'
58 Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian). 1 M'
59 Pekerjaan pemotongan plat baja tebal 5 mm 1 M'
60 Pengecatan besi/pipa anti karat (exterior painting). 1 M2
61 Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m 1 kg
62 Pekerjaan konstruksi rangka baja 1 kg
63 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). 1 unit
64 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. 1 unit
65 Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur. 1 unit
66 Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5 1 unit

E Pekerjaan Kayu
67 Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm. 1 m'
68 Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15. 1 M3
69 Rangka kusen pintu dan jendela, Kayu Kamper medan 1 M3
70 Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3 1 M2
71 Penutup bubungan 1 M2
72 Lisplank, kayu borne 2x3/20 1 m1
73 Daun Pintu double triplek, rangka borneo 3/6 1 bh
74 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7 1 M3
75 Daun jendala kaca, kayu 3/10 dan profil 2/3. 1 M2

F Pekerjaan Pemasangan Pipa Baja


76 Pengangkutan pipa baja ke lokasi galian. 1 kg
77 Penyambungan Pipa Las Flange Pipa Dia. 250 mm 1 M'
78 Penyambungan Pipa Las Flange Pipa Dia. 300 mm 1 M'
79 Pemasangan Pipa GI ND. 250 mm, diatas tumpuan 1 M'
80 Pemasangan Pipa GI ND. 300 mm, diatas tumpuan 1 M'

81 Pemasangan GI Dia. 250 mm, Galian tanah biasa. 1 M'


82 Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. 1 M'
83 Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. 1 M'
84 Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. 1 M'
85 Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block. 1 M'

86 Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. 1 M'


87 Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. 1 M'
88 Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. 1 M'
89 Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. 1 M'
90 Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. 1 M'
91 Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. 1 M'
92 Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. 1 M'
93 Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm. 1 M'

G Pekerjaan Pemasangan Pipa PVC


94 Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm 1 M'
95 Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm 1 M'
96 Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm 1 M'
97 Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm 1 M'
98 Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm 1 M'
99 Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm 1 M'
100 Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm 1 M'
101 Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm 1 M'

102 Penyambungan pipa PVC Dia. 50 mm didalam galian 1 M'


103 Penyambungan pipa PVC Dia. 75 mm didalam galian 1 M'
104 Penyambungan pipa PVC Dia. 100 mm didalam galian 1 M'
105 Penyambungan pipa PVC Dia. 150 mm didalam galian 1 M'
106 Penyambungan pipa PVC Dia. 200 mm didalam galian 1 M'
107 Penyambungan pipa PVC Dia. 250 mm didalam galian 1 M'
108 Penyambungan pipa PVC Dia. 300 mm didalam galian 1 M'
109 Penyambungan pipa PVC Dia. 400 mm didalam galian 1 M'

110 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. 1 M'
111 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. 1 M'
112 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. 1 M'
113 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. 1 M'
114 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. 1 M'
115 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. 1 M'
116 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. 1 M'
117 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. 1 M'
118 Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa. 1 M'

119 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras 1 M'
120 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras 1 M'
121 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. 1 M'
122 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. 1 M'
123 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. 1 M'
124 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. 1 M'
125 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. 1 M'
126 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. 1 M'
127 Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras 1 M'
128 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu 1 M'
129 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu 1 M'
130 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. 1 M'
131 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. 1 M'
132 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. 1 M'
133 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. 1 M'
134 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. 1 M'
135 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu. 1 M'

136 Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. 1 M'
137 Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. 1 M'
138 Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. 1 M'
139 Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. 1 M'
140 Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. 1 M'
141 Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. 1 M'
142 Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. 1 M'
143 Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. 1 M'
144 Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. 1 M'
145 Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. 1 M'
146 Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. 1 M'
147 Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. 1 M'
148 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 1 M'
149 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 1 M'
150 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 1 M'
151 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 1 M'
152 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 1 M'
153 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 1 M'
154 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 1 M'
155 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 1 M'
H Pekerjaan Perkerasan Jalan.
156 Pemadatan tanah dasar menggunakan Stamper 1M2
157 Pemadatan standart Bina Marga menggunakan alat berat 1M2
158 Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2. 1 M2
159 Lapis Pondasi bawah Onderlaght, tebal 15 cm. 1 M2
160 Lapis Pondasi bawah onderlaght, tebal 30 cm. 1 M2
161 Lapis Pondasi Atas Steinslaght , tebal 7 cm. 1 M2
162 Lapis Perkerasan Macadam, tebal 5 cm. 1 M2
163 Lapis PENETRASI , tebal 3 cm. 1 M2
164 Perbaikan Perkerasan jalan kelas III 1 M2
165 Perbaikan Perkerasan jalan kelas I 1 M2
166 Pemasangan kembali Paving Block (30% rusak diganti baru) 1 M2
167 Perbaikan paving blok, pemasangan pipa dia. 400 mm 1 M2
168 Perbaikan paving blok, pemasangan pipa dia. 300 mm 1 M2
169 Perbaikan paving blok, pemasangan pipa dia. 250 mm 1 M2
170 Perbaikan paving blok, pemasangan pipa dia. 200 mm 1 M2
171 Jalan inspeksi, beton rabat tebal 10 cm 1 M2

H Pekerjaan Perlintasan Pipa


172 Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. TIPE D 1 unit
173 Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m. 1 unit
174 Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m. 1 unit
175 Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m. 1 unit
176 Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m. 1 unit
177 Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m. 1 unit
178 Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m. 1 unit
179 Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m. 1 unit
180 Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus). 1 unit
181 Jembatan Pipa, ND. 250 mm, Bentang = 50,00 m 1 unit
182 Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m. 1 unit
183 Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m. 1 unit
184 Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m. 1 unit
185 Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m. 1 unit
186 Jembatan Pipa, ND. 150 mm, Bentang = 15,00 m. 1 unit
187 Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m. 1 unit
188 Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m. 1 unit
189 Jembatan Pipa, ND. 100 mm, Bentang = 12,00 m. 1 unit
190 Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m. 1 unit
191 Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m. 1 unit
192 Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m. 1 unit
193 Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m. 1 unit
194 Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m. 1 unit
195 Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m. 1 unit
196 Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m. 1 unit

197 Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 50,00 m 1 unit
198 Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m 1 unit
199 Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m 1 unit
200 Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 18,00 m 1 unit
201 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m 1 unit
202 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m 1 unit
203 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m 1 unit
204 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m 1 unit
205 Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m 1 unit
206 Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m 1 unit
207 Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 25,00 m 1 unit
208 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m 1 unit
209 Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m 1 unit
210 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m 1 unit
211 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m 1 unit
212 Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m 1 unit
213 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m 1 unit
214 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m 1 unit
215 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m 1 unit
216 Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m 1 unit
217 Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m 1 unit
218 Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m 1 unit
219 Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m 1 unit
HARGA

780.00
9,450.00
19,680.00
26,870.00
39,370.00
71,250.00
8,620.00
12,300.00
83,410.00
101,830.00
7,875.00
50,670.00
88,700.00
22,640.00
24,840.00
4,310.00

145,690.00
296,210.00
480,990.00
514,950.00
560,760.00
25,420.00
27,200.00
27,380.00
104,290.00
132,060.00
95,070.00

780,210.00
648,570.00
594,330.00
15,470.17
63,403.59
146,161.86
195,772.69
3,238,083.33
2,938,126.54
3,532,016.56
721,137.18
657,733.59
2,410,177.97
2,812,402.39
3,415,739.02
3,647,791.57
4,323,509.54
4,335,366.86
4,443,658.05
5,588,450.63
5,128,956.59
5,478,275.74
4,232,862.63
4,967,069.96
3,673,636.78
4,123,847.88
5,655,394.71
5,883,438.00

200,435.00
102,847.50
143,997.00
46,378.75
46,234.56
9,375.87
8,926.64
206,500.00
261,800.00
87,780.00
788,720.00

96,313.47
3,979,820.00
6,167,540.00
178,770.00
62,230.00
58,240.00
537,350.00
111,340.00
140,100.00

170.00
49,468.75
56,535.71
60,200.00
68,900.00

106,600.00
124,100.00
133,300.00
131,500.00
119,000.00

165,800.00
120,400.00
137,300.00
136,700.00
144,000.00
133,000.00
2,590.00
2,820.00

330.00
363.00
396.00
462.00
561.00
693.00
858.00
1,023.00

750.00
787.50
937.50
1,312.50
1,500.00
1,800.00
2,062.50
2,250.00

26,900.00
29,000.00
34,300.00
40,300.00
41,000.00
44,800.00
54,500.00
57,000.00
62,100.00

35,700.00
37,900.00
44,800.00
52,000.00
53,000.00
59,400.00
72,700.00
76,200.00
85,700.00
34,000.00
36,300.00
42,300.00
48,300.00
51,000.00
58,200.00
69,200.00

36,800.00
40,600.00
53,800.00
63,600.00
69,300.00
78,300.00
63,000.00
66,900.00
83,500.00
64,900.00
72,300.00
83,200.00
1,640.00
1,650.00
2,020.00
2,100.00
2,410.00
2,660.00
2,790.00
3,210.00

5,643.75
1,050.30
5,193.02
20,970.00
36,369.00
23,985.49
33,558.13
24,101.38
54,528.13
69,056.87
30,675.11
30,675.11
27,607.60
24,540.09
21,472.58
101,374.24

36,437,559.50
46,112,328.53
52,046,807.69
54,949,918.57
56,442,793.52
63,630,420.21
107,669,431.04
81,141,038.27
114,929,053.55
196,169,305.96
78,961,987.60
30,699,739.50
33,008,762.53
98,179,222.73
24,069,480.73
16,048,227.10
14,584,227.10
18,552,747.88
18,216,912.19
18,088,855.11
17,489,339.86
10,395,657.00
10,009,457.00
10,117,657.00
21,084,755.38

64,996,555
24,981,864
12,351,514
31,514,290
6,785,534
11,176,514
9,108,439
8,058,439
6,358,439
4,683,439
13,521,722
4,633,439
3,932,739
3,393,239
3,076,239
3,468,239
9,792,392
9,105,236
8,289,687
5,739,216
8,664,736
4,703,346
2,527,334
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA


A Pekerjaan Persiapan, Tanah dan Bongkaran
1 Pembersihan lokasi secara manual 1M2 780.00
2 Mengukur dan memasang bouwplank 1M1 9,450.00
3 Galian tanah biasa 1M3 19,680.00
4 Galian tanah keras 1M3 26,870.00
5 Galian tanah berbatu 1M3 39,370.00
6 Galian dasar sungai berbatu 1M3 71,250.00
7 Urugan tanah kembali 1M3 8,620.00
8 Pemadatan tanah perlapis 25 cm 1M3 12,300.00
9 Urugan tanah didatangkan dipadatkan 1M3 83,410.00
10 Urugan pasir dipadatkan 1M3 101,830.00
11 Buangan tanah disekitar lokasi 1M3 7,875.00
12 Pemasangan turap kayu pengaman galian 1.5 m 1 M1 50,670.00
13 Bongkaran beton masif dan pasangan batu. 1 M3 88,700.00
14 Bongkaran perkerasan jalan kelas III (40 cm) 1 M2 22,640.00
15 Bongkaran perkerasan jalan kelas I (15 cm) 1 M2 24,840.00
16 Bongkaran perkerasan Paving Block tebal 8 cm. 1 M2 4,310.00
B Pekerjaan Pasangan.
17 Pasangan Batu kosong 1 M3 145,690.00
18 Pasangan Batu Bronjong. 1 m3 296,210.00
19 Pasangan Batu, Spesi 1 : 4. 1 m3 480,990.00
20 Pasangan Batu, Spesi 1 : 3. 1 m3 514,950.00
21 Pasangan Bata, Spesi 1 : 4. 1 m3 560,760.00
22 Plesteran Spesi 1 : 2, tebal 10 mm. 1 m2 25,420.00
23 Plesteran Spesi 1 : 2, tebal 15 mm. 1 m2 27,200.00
24 Siaran, Spesi 1 : 1, tebal 10 mm. 1 m2 27,380.00
25 Pasang Keramik 20x20 cm 1 m2 104,290.00
26 Pasang lantai Mozaik 30x30 cm 1 m2 132,060.00
27 Pasang Porselin 10x10 cm 1 m2 95,070.00

C Pekerjaan Beton
28 Adukan Beton, Campuran 1:2:2,5. (K225) 1 m3 780,210.00
29 Adukan Beton, Campuran 1:2:3. (K175) 1 m3 648,570.00
30 Adukan Beton, Campuran 1:2:5. (K125) 1 m3 594,330.00
31 Pembesian tulangan beton, mutu baja U24. 1 Kg. 15,470.17
32 Cetakan Beton (non eksposed). 1 M2 63,403.59
33 Cetakan Beton (eksposed). 1 M2 146,161.86
34 Perancah tinggi 3,00 m. 1 M2 195,772.69
35 Beton Bertulang K225, Pilar Jembatan 50/50. 1 M3 3,238,083.33
36 Beton Bertulang K225, Support pipa 30/30. 1 M3 2,938,126.54
37 Beton Bertulang K225, Kepala Pilar Jembatan 50/130. 1 M3 3,532,016.56
38 Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm) 1 M3 721,137.18
39 Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3. 1 M3 657,733.59
40 Plat lantai beton bertulang, K225 baja U24 (103 kg/m3) 1 M3 2,410,177.97
41 Plat lantai beton bertulang, K225 baja U24 (129 kg/m3) 1 M3 2,812,402.39
42 Plat lantai beton bertulang, K225 baja U24 (168 kg/m3) 1 M3 3,415,739.02
43 Plat lantai beton bertulang, K225 baja U24 (183 kg/m3) 1 M3 3,647,791.57
44 Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3) 1 M3 4,323,509.54
45 Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3) 1 M3 4,335,366.86
46 Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3) 1 M3 4,443,658.05
47 Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3) 1 M3 5,588,450.63
48 Kolom beton bertulang, K225 baja U24 (152 kg/m3) 1 M3 5,128,956.59
49 Balok beton bertulang, K225 baja U24 (165 kg/m3) 1 M3 5,478,275.74
50 Sloof beton bertulang, K225 baja U24 (174 kg/m3) 1 M3 4,232,862.63
51 Sloof beton bertulang, K175 baja U24 (148 kg/m3) 1 M3 4,967,069.96
52 Kolom/balok ringbalk, K175 baja U24 (148 kg/m3) 1 M3 3,673,636.78
53 Plat Atap beton bertulang, K225 baja U24 (90 kg/m3) 1 M3 4,123,847.88
54 Plat Atap beton bertulang, K225 baja U24 (189 kg/m3) 1 M3 5,655,394.71
55 Lisplank beton bertulang, K175 baja U24 (90 kg/m3) 1 M3 5,883,438.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA


D Pekerjaan Konstruksi Baja

56 Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart) 1 M3 200,435.00
57 Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah). 1 M' 102,847.50
58 Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian). 1 M' 143,997.00
59 Pekerjaan pemotongan plat baja tebal 5 mm 1 M' 46,378.75
60 Pengecatan besi/pipa anti karat (exterior painting). 1 M2 46,234.56
61 Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m 1 kg 9,375.87
62 Pekerjaan konstruksi rangka baja 1 kg 8,926.64
63 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). 1 unit 206,500.00
64 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. 1 unit 261,800.00
65 Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur. 1 unit 87,780.00
66 Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5 1 unit 788,720.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA

E Pekerjaan Kayu
67 Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm. 1 m' 96,313.47
68 Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15. 1 M3 3,979,820.00
69 Rangka kusen pintu dan jendela, Kayu Kamper medan 1 M3 6,167,540.00
70 Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3 1 M2 178,770.00
71 Penutup bubungan 1 M2 62,230.00
72 Lisplank, kayu borne 2x3/20 1 m1 58,240.00
73 Daun Pintu double triplek, rangka borneo 3/6 1 bh 537,350.00
74 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7 1 M3 111,340.00
75 Daun jendala kaca, kayu 3/10 dan profil 2/3. 1 M2 140,100.00

F Pekerjaan Pemasangan Pipa Baja


76 Pengangkutan pipa baja ke lokasi galian. 1 kg 170.00
77 Penyambungan Pipa Las Flange Pipa Dia. 250 mm 1 M' 49,468.75
78 Penyambungan Pipa Las Flange Pipa Dia. 300 mm 1 M' 56,535.71
79 Pemasangan Pipa GI ND. 250 mm, diatas tumpuan 1 M' 60,200.00
80 Pemasangan Pipa GI ND. 300 mm, diatas tumpuan 1 M' 68,900.00

81 Pemasangan GI Dia. 250 mm, Galian tanah biasa. 1 M' 106,600.00


82 Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. 1 M' 124,100.00
83 Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. 1 M' 133,300.00
84 Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. 1 M' 131,500.00
85 Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block. 1 M' 119,000.00

86 Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. 1 M' 165,800.00
87 Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. 1 M' 120,400.00
88 Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. 1 M' 137,300.00
89 Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. 1 M' 136,700.00
90 Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. 1 M' 144,000.00
91 Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. 1 M' 133,000.00
92 Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. 1 M' 2,590.00
93 Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm. 1 M' 2,820.00

G Pekerjaan Pemasangan Pipa PVC


94 Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm 1 M' 330.00
95 Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm 1 M' 363.00
96 Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm 1 M' 396.00
97 Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm 1 M' 462.00
98 Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm 1 M' 561.00
99 Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm 1 M' 693.00
100 Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm 1 M' 858.00
101 Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm 1 M' 1,023.00

102 Penyambungan pipa PVC Dia. 50 mm didalam galian 1 M' 750.00


103 Penyambungan pipa PVC Dia. 75 mm didalam galian 1 M' 787.50
104 Penyambungan pipa PVC Dia. 100 mm didalam galian 1 M' 937.50
105 Penyambungan pipa PVC Dia. 150 mm didalam galian 1 M' 1,312.50
106 Penyambungan pipa PVC Dia. 200 mm didalam galian 1 M' 1,500.00
107 Penyambungan pipa PVC Dia. 250 mm didalam galian 1 M' 1,800.00
108 Penyambungan pipa PVC Dia. 300 mm didalam galian 1 M' 2,062.50
109 Penyambungan pipa PVC Dia. 400 mm didalam galian 1 M' 2,250.00

110 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. 1 M' 26,900.00
111 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. 1 M' 29,000.00
112 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. 1 M' 34,300.00
113 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. 1 M' 40,300.00
114 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. 1 M' 41,000.00
115 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. 1 M' 44,800.00
116 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. 1 M' 54,500.00
117 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. 1 M' 57,000.00
118 Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa. 1 M' 62,100.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA

119 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras 1 M' 35,700.00
120 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras 1 M' 37,900.00
121 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. 1 M' 44,800.00
122 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. 1 M' 52,000.00
123 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. 1 M' 53,000.00
124 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. 1 M' 59,400.00
125 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. 1 M' 72,700.00
126 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. 1 M' 76,200.00
127 Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras 1 M' 85,700.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA

128 Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu 1 M' 34,000.00
129 Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu 1 M' 36,300.00
130 Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. 1 M' 42,300.00
131 Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. 1 M' 48,300.00
132 Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. 1 M' 51,000.00
133 Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. 1 M' 58,200.00
134 Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. 1 M' 69,200.00
135 Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu. 1 M'

136 Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. 1 M' 36,800.00
137 Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. 1 M' 40,600.00
138 Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. 1 M' 53,800.00
139 Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. 1 M' 63,600.00
140 Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. 1 M' 69,300.00
141 Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. 1 M' 78,300.00

142 Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. 1 M' 63,000.00
143 Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. 1 M' 66,900.00
144 Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. 1 M' 83,500.00

145 Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. 1 M' 64,900.00
146 Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. 1 M' 72,300.00
147 Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. 1 M' 83,200.00
148 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 1 M' 1,640.00
149 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 1 M' 1,650.00
150 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 1 M' 2,020.00
151 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 1 M' 2,100.00
152 Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 1 M' 2,410.00

H Pekerjaan Perkerasan Jalan.


153 #N/A #N/A #N/A
154 #N/A #N/A #N/A
155 #N/A #N/A #N/A
156 Pemadatan tanah dasar menggunakan Stamper 1M2 5,643.75
157 Pemadatan standart Bina Marga menggunakan alat berat 1M2 1,050.30
158 Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2. 1 M2 5,193.02
159 Lapis Pondasi bawah Onderlaght, tebal 15 cm. 1 M2 20,970.00
160 Lapis Pondasi bawah onderlaght, tebal 30 cm. 1 M2 36,369.00
161 Lapis Pondasi Atas Steinslaght , tebal 7 cm. 1 M2 23,985.49
162 Lapis Perkerasan Macadam, tebal 5 cm. 1 M2 33,558.13
163 Lapis PENETRASI , tebal 3 cm. 1 M2 24,101.38
164 Perbaikan Perkerasan jalan kelas III 1 M2 54,528.13
165 Perbaikan Perkerasan jalan kelas I 1 M2 69,056.87
166 Pemasangan kembali Paving Block (30% rusak diganti baru) 1 M2 30,675.11
167 Perbaikan paving blok, pemasangan pipa dia. 400 mm 1 M2 30,675.11
168 Perbaikan paving blok, pemasangan pipa dia. 300 mm 1 M2 27,607.60
169 Perbaikan paving blok, pemasangan pipa dia. 250 mm 1 M2 24,540.09
170 Perbaikan paving blok, pemasangan pipa dia. 200 mm 1 M2 21,472.58
171 Jalan inspeksi, beton rabat tebal 10 cm 1 M2 101,374.24
REKAP DAFTAR HARGA SATUAN PEKERJAAN
PENDUKUNG

NO URAIAN PEKERJAAN SATUAN HARGA


H Pekerjaan Perlintasan Pipa
172 Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. 1 unit 34,310,099
173 Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m. 1 unit 40,175,189
174 Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m. 1 unit 46,324,564
175 Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m. 1 unit 49,309,275
176 Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m. 1 unit 53,411,379
177 Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m. 1 unit 57,674,320
178 Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m. 1 unit 85,731,227
179 Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m. 1 unit 73,889,429
180 Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus). 1 unit 89,062,116
181 Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m. 1 unit 71,955,876
182 Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m. 1 unit 25,657,479
183 Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m. 1 unit 31,170,719
184 Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m. 1 unit 71,649,790
185 Jembatan Pipa, ND. 150 mm, Bentang = 10,00 m. 1 unit 21,960,837
186 Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m. 1 unit 17,276,014
187 Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m. 1 unit 15,224,014
188 Jembatan Pipa, ND. 100 mm, Bentang = 10,00 m. 1 unit 18,596,146
189 Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m. 1 unit 17,790,313
190 Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m. 1 unit 17,553,306
191 Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m. 1 unit 16,844,841
192 Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m. 1 unit 10,498,676
193 Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m. 1 unit 10,389,526
194 Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m. 1 unit 10,002,776
195 Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m. 1 unit 19,950,940

196 Syphon Pipa, ND. 300 mm, Bentang 1,50 m (Type A). 1 unit 1,963,728
197 Syphon Pipa, ND. 250 mm, Bentang 1,50 m (Type A). 1 unit 1,867,028
198 Syphon Pipa, ND. 200 mm, Bentang 1,50 m (Type A). 1 unit 1,721,028
199 Syphon Pipa, ND. 150 mm, Bentang 1,50 m (Type A). 1 unit 1,359,028
200 Syphon Pipa, ND. 100 mm, Bentang 1,50 m (Type A). 1 unit 1,063,928
201 Syphon Pipa, ND. 100 mm, Bentang 2,50 m (Type A). 1 unit 1,878,036
202 Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m 1 unit 21,944,585
203 Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m 1 unit 11,642,170
204 Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 6,00 m 1 unit 5,411,820
205 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m 1 unit 9,432,170
206 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m 1 unit 7,669,020
207 Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m 1 unit 6,669,020
208 Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m 1 unit 7,928,020

209 Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m 1 unit 4,637,020
210 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m 1 unit 6,297,020
211 Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m 1 unit 3,621,333
212 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m 1 unit 3,512,333
213 Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m 1 unit 2,868,483
214 Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m 1 unit 3,602,333
215 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m 1 unit 6,896,417
216 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m 1 unit 6,198,701
217 Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m 1 unit 5,444,716
218 Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m 1 unit 5,013,828
219 Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m 1 unit 7,690,963
220 Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m 1 unit 4,019,233
221 Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m 1 unit 1,710,507
ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan

Lokasi

No Uraian Pekerjaan Harga Satuan Jumlah

A PEKERJAAN TANAH DAN PERSIAPAN

1 1M2 Pembersihan lokasi secara manual


0.030 Oh Pekerja @ Rp. 25,000.00 = Rp. 750.00
0.001 Oh Mandor @ Rp. 37,500.00 = Rp. 37.50
Jumlah 787.50
Dibulatkan 780.00

2 1M1 Mengukur dan memasang bouwplank


0.006 Oh Kayu Bekisting @ Rp. 1,457,800.00 = Rp. 8,746.80
0.006 Oh Pekerja @ Rp. 25,000.00 = Rp. 150.00
0.015 Oh Mandor 37,500.00 = Rp. 562.50
Jumlah 9,459.30
Dibulatkan 9,450.00

3 1M3 Galian tanah biasa


0.750 oh Pekerja @ Rp. 25,000.00 = Rp. 18,750.00
0.025 oh Mandor @ Rp. 37,500.00 = Rp. 937.50
Jumlah 19,687.50
Dibulatkan 19,680.00

4 1M3 Galian tanah keras


1.000 oh Pekerja @ Rp. 25,000.00 = Rp. 25,000.00
0.050 oh Mandor @ Rp. 37,500.00 = Rp. 1,875.00
Jumlah 26,875.00
Dibulatkan 26,870.00

5 1M3 Galian tanah berbatu


1.500 oh Pekerja @ Rp. 25,000.00 = Rp. 37,500.00
0.050 oh Mandor @ Rp. 37,500.00 = Rp. 1,875.00
Jumlah 39,375.00
Dibulatkan 39,370.00

6 1M3 Galian dasar sungai berbatu


1.750 oh Pekerja @ Rp. 25,000.00 = Rp. 43,750.00
0.100 oh Mandor @ Rp. 37,500.00 = Rp. 3,750.00
0.050 oh Alat bantu (pompa, kisdam turap, dll) = Rp. 23,750.00
Jumlah 71,250.00
Dibulatkan 71,250.00

7 1M3 Urugan tanah kembali


0.330 oh Pekerja @ Rp. 25,000.00 = Rp. 8,250.00
0.010 oh Mandor @ Rp. 37,500.00 = Rp. 375.00
Jumlah 8,625.00
Dibulatkan 8,620.00

8 1M3 Pemadatan tanah perlapis 25 cm


0.160 jam Plate Vibrator Tamper @ Rp. 4,200.00 = Rp. 672.00
0.160 oh Operator semi terampil @ Rp. 45,800.00 = Rp. 7,328.00
0.160 oh Pekerja @ Rp. 25,000.00 = Rp. 4,000.00
0.008 oh Mandor @ Rp. 37,500.00 = Rp. 300.00
Jumlah 12,300.00
Dibulatkan = Rp. 12,300.00

9 1M3 Urugan tanah didatangkan dipadatkan


1.2 m3 Tanah merah @ Rp. 33,700.00 = Rp. 40,440.00
0.300 oh Pekerja @ Rp. 25,000.00 = Rp. 7,500.00
0.010 oh Mandor @ Rp. 37,500.00 = Rp. 375.00
1.000 M3 Pemadatan perlapis 25 cm @ Rp. 12,300.00 = Rp. 12,300.00
1.000 M3 Biaya Anggkutan @ Rp. 22,800.00 = Rp. 22,800.00
Jumlah 83,415.00
Dibulatkan = Rp. 83,410.00

10 1M3 Urugan pasir dipadatkan


No Uraian Pekerjaan Harga Satuan Jumlah

1.2 m3 Pasir urug @ Rp. 78,300.00 = Rp. 93,960.00


0.300 oh Pekerja @ Rp. 25,000.00 = Rp. 7,500.00
0.010 oh Mandor @ Rp. 37,500.00 = Rp. 375.00
Jumlah 101,835.00
Dibulatkan = Rp. 101,830.00

11 1M3 Buangan tanah disekitar lokasi


0.300 oh Pekerja @ Rp. 25,000.00 = Rp. 7,500.00
0.010 oh Mandor @ Rp. 37,500.00 = Rp. 375.00
Jumlah 7,875.00
Dibulatkan = Rp. 7,870.00
No Uraian Pekerjaan Harga Satuan Jumlah

12 1 M1 Pemasangan turap kayu pengaman galian 1.5 m


2.000 m2 Anyaman bambu belah @ Rp. 10,800.00 = Rp. 21,600.00
0.500 kg Paku biasa @ Rp. 10,800.00 = Rp. 5,400.00
0.500 oh Pekerja @ Rp. 25,000.00 = Rp. 12,500.00
0.250 oh Tukang kayu semi terampil @ Rp. 41,700.00 = Rp. 10,425.00
0.020 oh Mandor @ Rp. 37,500.00 = Rp. 750.00
Jumlah 50,675.00
Dibulatkan = Rp. 50,670.00

13 1 M3 Bongkaran beton masif dan pasangan batu.


2.000 oh Pekerja @ Rp. 25,000.00 = Rp. 50,000.00
0.200 oh Mandor @ Rp. 37,500.00 = Rp. 7,500.00
2.000 jam Jack Hammer @ Rp. 15,600.00 = Rp. 31,200.00
Jumlah 88,700.00
Dibulatkan 88,700.00

14 1 M2 Bongkaran perkerasan jalan kelas III (40 cm)


0.750 oh Pekerja @ Rp. 25,000.00 = Rp. 18,750.00
0.075 oh Mandor @ Rp. 37,500.00 = Rp. 2,812.50
Alat bantu = Rp. 1,078.13
Jumlah 22,640.63
Dibulatkan 22,640.00

15 1 M2 Bongkaran perkerasan jalan kelas I (15 cm)


0.500 oh Pekerja @ Rp. 25,000.00 = Rp. 12,500.00
0.100 oh Operator terampil @ Rp. 50,000.00 = Rp. 5,000.00
0.100 oh Pembantu operator @ Rp. 50,000.00 = Rp. 5,000.00
0.075 jam Jack Hammer @ Rp. 15,600.00 = Rp. 1,170.00
0.075 jam Air Compressor 150 M3 15,600.00 = Rp. 1,170.00
Jumlah 24,840.00
Dibulatkan 24,840.00

16 1 M2 Bongkaran perkerasan Paving Block tebal 8 cm.


0.150 oh Pekerja @ Rp. 25,000.00 = Rp. 3,750.00
0.015 oh Mandor @ Rp. 37,500.00 = Rp. 562.50
Jumlah 4,312.50
Dibulatkan 4,310.00

B PEKERJAAN PASANGAN DAN PLESTERAN

17 1 M3 Pasangan Batu kosong


1.100 m3 Batu belah 15/20 @ Rp. 95,800.00 = Rp. 105,380.00
1.500 oh Pekerja @ Rp. 25,000.00 = Rp. 37,500.00
0.075 oh Mandor @ Rp. 37,500.00 = Rp. 2,812.50
Jumlah 145,692.50
Dibulatkan 145,690.00

18 1 m3 Pasangan Batu Bronjong.


2.000 oh Pekerja @ Rp. 25,000.00 = Rp. 50,000.00
1.000 oh Pekerja terampil @ Rp. 37,500.00 = Rp. 37,500.00
0.100 oh Mandor @ Rp. 37,500.00 = Rp. 3,750.00
1.200 m3 Batu bronjong @ Rp. 95,800.00 = Rp. 114,960.00
4.500 Kg Kawat bronjong 3 mm @ Rp. 20,000.00 = Rp. 90,000.00
Jumlah 296,210.00
Dibulatkan 296,210.00

19 1 m3 Pasangan Batu, Spesi 1 : 4.


1.200 m3 Batu belah 15/20 @ Rp. 95,800.00 = Rp. 114,960.00
0.522 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 60,865.20
3.260 zak Portland Cement @ Rp. 48,300.00 = Rp. 157,458.00
3.600 oh Pekerja @ Rp. 25,000.00 = Rp. 90,000.00
1.200 oh Tukang Batu @ Rp. 38,300.00 = Rp. 45,960.00
0.120 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 5,004.00
0.180 oh Mandor @ Rp. 37,500.00 = Rp. 6,750.00
Jumlah 480,997.20
Dibulatkan 480,990.00

20 1 m3 Pasangan Batu, Spesi 1 : 3.


1.200 m3 Batu belah 15/20 @ Rp. 95,800.00 = Rp. 114,960.00
0.486 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 56,667.60
No Uraian Pekerjaan Harga Satuan Jumlah

4.050 zak Portland Cement @ Rp. 48,300.00 = Rp. 195,615.00


3.600 oh Pekerja @ Rp. 25,000.00 = Rp. 90,000.00
1.200 oh Tukang batu @ Rp. 38,300.00 = Rp. 45,960.00
0.120 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 5,004.00
0.180 oh Mandor @ Rp. 37,500.00 = Rp. 6,750.00
Jumlah 514,956.60
Dibulatkan 514,950.00
No Uraian Pekerjaan Harga Satuan Jumlah

21 1 m3 Pasangan Bata, Spesi 1 : 4.


450.000 m3 Bata merah lokal @ Rp. 400.00 = Rp. 180,000.00
0.378 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 44,074.80
3.148 zak Portland Cement @ Rp. 48,300.00 = Rp. 152,048.40
4.500 oh Pekerja @ Rp. 25,000.00 = Rp. 112,500.00
1.500 oh Tukang batu @ Rp. 38,300.00 = Rp. 57,450.00
0.150 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 6,255.00
0.225 oh Mandor @ Rp. 37,500.00 = Rp. 8,437.50
Jumlah 560,765.70
Dibulatkan 560,760.00

22 1 m2 Plesteran Spesi 1 : 2, tebal 10 mm.


0.012 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 1,399.20
0.143 zak Portland Cement @ Rp. 48,300.00 = Rp. 6,906.90
0.400 oh Pekerja @ Rp. 25,000.00 = Rp. 10,000.00
0.150 oh Tukang batu @ Rp. 38,300.00 = Rp. 5,745.00
0.015 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 625.50
0.020 oh Mandor @ Rp. 37,500.00 = Rp. 750.00
Jumlah 25,426.60
Dibulatkan 25,420.00

23 1 m2 Plesteran Spesi 1 : 2, tebal 15 mm.


0.019 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 2,215.40
0.163 zak Portland Cement @ Rp. 48,300.00 = Rp. 7,872.90
0.400 oh Pekerja @ Rp. 25,000.00 = Rp. 10,000.00
0.150 oh Tukang Batu @ Rp. 38,300.00 = Rp. 5,745.00
0.015 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 625.50
0.020 oh Mandor @ Rp. 37,500.00 = Rp. 750.00
Jumlah 27,208.80
Dibulatkan 27,200.00

24 1 m2 Siaran, Spesi 1 : 1, tebal 10 mm.


0.060 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 6,996.00
0.082 zak Portland Cement @ Rp. 48,300.00 = Rp. 3,960.60
0.150 oh Pekerja @ Rp. 25,000.00 = Rp. 3,750.00
0.300 oh Tukang batu semi terampil @ Rp. 38,300.00 = Rp. 11,490.00
0.015 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 625.50
0.015 oh Mandor @ Rp. 37,500.00 = Rp. 562.50
Jumlah 27,384.60
Dibulatkan 27,380.00

25 1 m2 Pasang Keramik 20x20 cm


1.000 m2 Keramik 20x20 kelas I @ Rp. 62,500.00 = Rp. 62,500.00
0.035 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 4,081.00
0.248 zak Portland Cement @ Rp. 48,300.00 = Rp. 11,978.40
0.500 oh Pekerja @ Rp. 25,000.00 = Rp. 12,500.00
0.250 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 10,425.00
0.075 oh Mandor @ Rp. 37,500.00 = Rp. 2,812.50
Jumlah 104,296.90
Dibulatkan 104,290.00

26 1 m2 Pasang lantai Mozaik 30x30 cm


11.000 bh Mozaik 30x30 cm @ Rp. 8,000.00 = Rp. 88,000.00
0.035 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 4,081.00
0.248 zak Portland Cement @ Rp. 48,300.00 = Rp. 11,978.40
0.500 oh Pekerja @ Rp. 25,000.00 = Rp. 12,500.00
0.300 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 12,510.00
0.080 oh Mandor @ Rp. 37,500.00 = Rp. 3,000.00
Jumlah 132,069.40
Dibulatkan 132,060.00

27 1 m2 Pasang Porselin 10x10 cm


1.000 dos Porselin 10x10 cm @ Rp. 49,100.00 = Rp. 49,100.00
0.035 m3 Pasir pasang @ Rp. 116,600.00 = Rp. 4,081.00
0.248 zak Portland Cement @ Rp. 48,300.00 = Rp. 11,978.40
0.250 oh Pekerja @ Rp. 25,000.00 = Rp. 6,250.00
0.500 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 20,850.00
0.075 oh Mandor @ Rp. 37,500.00 = Rp. 2,812.50
Jumlah 95,071.90
Dibulatkan 95,070.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah

C PEKERJAAN BETON
28 1 m3 Adukan Beton, Campuran 1:2:2,5. (K225)
6.000 oh Pekerja @ Rp. 25,000.00 = Rp. 150,000.00
0.600 oh Tukang Batu @ Rp. 38,300.00 = Rp. 22,980.00
0.050 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 2,085.00
0.300 oh Mandor @ Rp. 37,500.00 = Rp. 11,250.00
0.492 m3 Pasir beton @ Rp. 133,300.00 = Rp. 65,583.60
0.820 m3 Batu pecah 1 - 2 @ Rp. 136,600.00 = Rp. 112,012.00
8.200 zak Portland Cement @ Rp. 48,300.00 = Rp. 396,060.00
0.200 ah Concrete Mixer 0,25 m3 @ Rp. 17,900.00 = Rp. 3,580.00
0.200 ah Concrete Vibrator @ Rp. 7,300.00 = Rp. 1,460.00
1.000 ls Alat bantu = Rp. 15,199.41
Jumlah 780,210.01
Dibulatkan 780,210.00

29 1 m3 Adukan Beton, Campuran 1:2:3. (K175)


6.000 oh Pekerja @ Rp. 25,000.00 = Rp. 150,000.00
0.600 oh Tukang Batu @ Rp. 38,300.00 = Rp. 22,980.00
0.050 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 2,085.00
0.300 oh Mandor @ Rp. 37,500.00 = Rp. 11,250.00
0.522 m3 Pasir beton @ Rp. 133,300.00 = Rp. 69,582.60
0.836 m3 Batu pecah 1 - 2 @ Rp. 136,600.00 = Rp. 114,197.60
5.400 zak Portland Cement @ Rp. 48,300.00 = Rp. 260,820.00
0.200 ah Concrete Mixer 0,25 m3 @ Rp. 17,900.00 = Rp. 3,580.00
0.200 ah Concrete Vibrator @ Rp. 7,300.00 = Rp. 1,460.00
1.000 ls Alat bantu = Rp. 12,618.30
Jumlah 648,573.50
Dibulatkan 648,570.00

30 1 m3 Adukan Beton, Campuran 1:2:5. (K125)


6.000 oh Pekerja @ Rp. 25,000.00 = Rp. 150,000.00
0.600 oh Tukang Batu @ Rp. 38,300.00 = Rp. 22,980.00
0.050 oh Kepala Tukang Batu @ Rp. 41,700.00 = Rp. 2,085.00
0.300 oh Mandor @ Rp. 37,500.00 = Rp. 11,250.00
0.588 m3 Pasir beton @ Rp. 133,300.00 = Rp. 78,380.40
0.842 m3 Batu pecah 1 - 2 @ Rp. 136,600.00 = Rp. 115,017.20
4.100 zak Portland Cement @ Rp. 48,300.00 = Rp. 198,030.00
0.200 ah Concrete Mixer 0,25 m3 @ Rp. 17,900.00 = Rp. 3,580.00
0.200 ah Concrete Vibrator @ Rp. 7,300.00 = Rp. 1,460.00
1.000 ls Alat bantu = Rp. 11,554.85
Jumlah 594,337.45
Dibulatkan 594,330.00

31 1 Kg. Pembesian tulangan beton, mutu baja U24.


100 Kg. Pekerjaan pemotongan, pembengkokan dan pemasangan tulangan beton.
9.000 oh Pekerja @ Rp. 25,000.00 = Rp. 225,000.00
9.000 oh Tukang Besi Beton @ Rp. 45,800.00 = Rp. 412,200.00
3.000 oh Kepala tukang besi beton @ Rp. 50,000.00 = Rp. 150,000.00
1.000 oh Mandor @ Rp. 37,500.00 = Rp. 37,500.00
110.0 Kg Besi tulangan polos @ Rp. 6,200.00 = Rp. 682,000.00
2.000 Kg Kawat beton @ Rp. 12,500.00 = Rp. 25,000.00
1.000 ls Alat bantu = Rp. 15,317.00
Jumlah = Rp. 1,547,017.00
Harga Satuan per 1 kg = Rp. 15,470.17
No Uraian Pekerjaan Harga Satuan Jumlah

32 1 M2 Cetakan Beton (non eksposed).


100 M2 Cetakan Beton (non eksposed).
6.000 oh Pekerja @ Rp. 25,000.00 = Rp. 150,000.00
5.000 oh Tukang Kayu @ Rp. 42,500.00 = Rp. 212,500.00
0.500 oh Kepala tukang kayu @ Rp. 45,800.00 = Rp. 22,900.00
0.100 oh Mandor @ Rp. 37,500.00 = Rp. 3,750.00
3.960 m3 Kayu Bekisting @ Rp. 1,457,800.00 = Rp. 5,772,888.00
5.000 Kg Paku biasa @ Rp. 10,800.00 = Rp. 54,000.00
1.000 ls Alat bantu = Rp. 124,320.76
Jumlah = Rp. 6,340,358.76
Harga Satuan per 1 m2 = Rp. 63,403.59

33 1 M2 Cetakan Beton (eksposed).


100 M2 Cetakan Beton ( eksposed).
6.000 oh Pekerja @ Rp. 25,000.00 = Rp. 150,000.00
5.000 oh Tukang Kayu @ Rp. 42,500.00 = Rp. 212,500.00
0.500 oh Kepala tukang kayu @ Rp. 45,800.00 = Rp. 22,900.00
0.100 oh Mandor @ Rp. 37,500.00 = Rp. 3,750.00
36.960 m3 Kayu Papan Multiplek 16 mm @ Rp. 228,200.00 = Rp. 8,434,272.00
3.740 m3 Kayu Bekisting @ Rp. 1,457,800.00 = Rp. 5,452,172.00
5.000 Kg Paku biasa @ Rp. 10,800.00 = Rp. 54,000.00
1.000 ls Alat bantu = Rp. 286,591.88
Jumlah = Rp. 14,616,185.88
Harga Satuan per 1 m2 = Rp. 146,161.86

34 1 M2 Perancah tinggi 3,00 m.


100 M2 Perancah tinggi 3,00 m.
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
2.000 oh Tukang kayu semi terampil 41,700.00 = Rp. 83,400.00
0.100 oh Kepala Tukang kayu 45,800.00 = Rp. 4,580.00
0.100 oh Mandor 37,500.00 = Rp. 3,750.00
400 btg Kayu dolken dia. 8 cm 4 m 25,000.00 = Rp. 10,000,000.00
6.300 m3 Kayu bekisting 1,457,800.00 = Rp. 9,184,140.00
5.000 Kg Paku biasa 10,800.00 = Rp. 54,000.00
1.000 ls Alat bantu = Rp. 97,399.35
Jumlah = Rp. 19,577,269.35
Harga Satuan per 1 m2 = Rp. 195,772.69

35 1 M3 Beton Bertulang K225, Pilar Jembatan 50/50.


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
121.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,871,890.57
2.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 292,323.72
6.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 293,659.04
Jumlah = Rp. 3,238,083.33

36 1 M3 Beton Bertulang K225, Support pipa 30/30.


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
113.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,748,129.21
2.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 292,323.72
6.00 M2 Perancah tinggi 3 m (10% Analisa C5) 195,772.69 = Rp. 117,463.62
Jumlah = Rp. 2,938,126.54

37 1 M3 Beton Bertulang K225, Kepala Pilar Jembatan 50/130.


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
140.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,165,823.80
2.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 292,323.72
6.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 293,659.04
Jumlah = Rp. 3,532,016.56

38 1 M3 Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm)


1.00 m3 Adukan Beton K125, Analisa C-30. 594,330.00 = Rp. 594,330.00
2.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 126,807.18
Jumlah = Rp. 721,137.18

39 1 M3 Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3.


1.00 m3 Adukan Beton K125, Analisa C-30. 594,330.00 = Rp. 594,330.00
1.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 63,403.59
Jumlah = Rp. 657,733.59
No Uraian Pekerjaan Harga Satuan Jumlah

40 1 M3 Plat lantai beton bertulang, K225 baja U24 (103 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
103.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,593,427.51
0.25 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 36,540.46
Jumlah = Rp. 2,410,177.97

41 1 M3 Plat lantai beton bertulang, K225 baja U24 (129 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
129.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,995,651.93
0.25 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 36,540.46
Jumlah = Rp. 2,812,402.39

42 1 M3 Plat lantai beton bertulang, K225 baja U24 (168 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
168.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,598,988.56
0.25 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 36,540.46
Jumlah = Rp. 3,415,739.02

43 1 M3 Plat lantai beton bertulang, K225 baja U24 (183 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
183.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,831,041.11
0.25 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 36,540.46
Jumlah = Rp. 3,647,791.57

44 1 M3 Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
98.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,516,076.66
13.20 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,929,336.54
2.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 97,886.35
Jumlah = Rp. 4,323,509.54

45 1 M3 Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
129.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,995,651.93
10.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,461,618.59
2.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 97,886.35
Jumlah = Rp. 4,335,366.86

46 1 M3 Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
136.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,103,943.12
10.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,461,618.59
2.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 97,886.35
Jumlah = Rp. 4,443,658.05

47 1 M3 Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
210.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 3,248,735.70
10.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,461,618.59
2.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 97,886.35
Jumlah = Rp. 5,588,450.63

48 1 M3 Kolom beton bertulang, K225 baja U24 (152 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
152.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,351,465.84
13.33 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,948,337.58
1.00 M2 Perancah tinggi 3 m (25% Analisa C5) 195,772.69 = Rp. 48,943.17
Jumlah = Rp. 5,128,956.59

49 1 M3 Balok beton bertulang, K225 baja U24 (165 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
165.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,552,578.05
12.00 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 1,753,942.31
4.00 M2 Perancah tinggi 3 m (50% Analisa C5) 195,772.69 = Rp. 391,545.39
Jumlah = Rp. 5,478,275.74
No Uraian Pekerjaan Harga Satuan Jumlah

50 1 M3 Sloof beton bertulang, K225 baja U24 (174 kg/m3)


tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata.
1.00 m3 Adukan Beton K225, Analisa C-29. 780,210.00 = Rp. 780,210.00
12.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 760,843.05
174.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,691,809.58
Jumlah = Rp. 4,232,862.63

51 1 M3 Sloof beton bertulang, K175 baja U24 (148 kg/m3)


tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata.
1.00 m3 Adukan Beton K225, Analisa C-29. 648,570.00 = Rp. 648,570.00
32.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 2,028,914.80
148.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,289,585.16
Jumlah = Rp. 4,967,069.96

52 1 M3 Kolom/balok ringbalk, K175 baja U24 (148 kg/m3)


tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata.
1.00 m3 Adukan Beton K175, Analisa C-29. 648,570.00 = Rp. 648,570.00
11.60 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 735,481.62
148.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,289,585.16
Jumlah = Rp. 3,673,636.78

53 1 M3 Plat Atap beton bertulang, K225 baja U24 (90 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
90.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,392,315.30
6.66 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 973,437.98
6.66 M2 Perancah tinggi 3 m (75% Analisa C5) 195,772.69 = Rp. 977,884.60
Jumlah = Rp. 4,123,847.88

54 1 M3 Plat Atap beton bertulang, K225 baja U24 (189 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-28. 780,210.00 = Rp. 780,210.00
189.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 2,923,862.13
6.66 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 973,437.98
6.66 M2 Perancah tinggi 3 m (75% Analisa C5) 195,772.69 = Rp. 977,884.60
Jumlah = Rp. 5,655,394.71

55 1 M3 Lisplank beton bertulang, K175 baja U24 (90 kg/m3)


1.00 m3 Adukan Beton K225, Analisa C-29. 648,570.00 = Rp. 648,570.00
90.0 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 1,392,315.30
25.62 M2 Cetakan beton eksposed Analisa C29. 146,161.86 = Rp. 3,744,666.82
1.00 M2 Perancah tinggi 3 m (50% Analisa C5) 195,772.69 = Rp. 97,886.35
Jumlah = Rp. 5,883,438.00

56 1 M3 Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart)
0.06 m3 Adukan Beton K175, Analisa C-29. 648,570.00 = Rp. 37,617.06
6.4 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 99,525.62
0.58 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 36,774.08
0.03 m3 Cor dengan adukan Beton K125, Analisa C1. 594,330.00 = Rp. 19,018.56
1.00 ls Biaya pengangkutan, pemasangan dan tulisan cekung di cat = Rp. 7,500.00
Jumlah = Rp. 200,435.00
No Uraian Pekerjaan Harga Satuan Jumlah

D PEKERJAAN KONSTRUKSI BAJA

57 1 M' Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah).


1.500 kg Kawat Las Listrik 11,100.00 = Rp. 16,650.00
2.000 jam Welding Mechine 500A 16,700.00 = Rp. 33,400.00
0.500 oh Pekerja 25,000.00 = Rp. 12,500.00
0.250 oh Tukang las 50,000.00 = Rp. 12,500.00
0.250 oh Operator semi terampil 45,800.00 = Rp. 11,450.00
0.250 oh Tukang besi profil 45,800.00 = Rp. 11,450.00
1.000 ls Alat bantu = Rp. 4,897.50
Jumlah = Rp. 102,847.50

58 1 M' Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian).


1.500 kg Kawat Las Listrik 11,100.00 = Rp. 16,650.00
3.000 jam Welding Mechine 500A 16,700.00 = Rp. 50,100.00
0.750 oh Pekerja 25,000.00 = Rp. 18,750.00
0.300 oh Tukang las 50,000.00 = Rp. 15,000.00
0.500 oh Operator semi terampil 45,800.00 = Rp. 22,900.00
0.300 oh Tukang besi profil 45,800.00 = Rp. 13,740.00
1.000 ls Alat bantu = Rp. 6,857.00
Jumlah = Rp. 143,997.00

59 1 M' Pekerjaan pemotongan plat baja tebal 5 mm


3.000 kg Karbit 6,100.00 = Rp. 18,300.00
0.500 oh Pekerja 25,000.00 = Rp. 12,500.00
0.250 oh Tukang las tidak bersertifikat 41,700.00 = Rp. 10,425.00
0.025 oh Mandor 37,500.00 = Rp. 937.50
1.000 ls Alat bantu = Rp. 4,216.25
Jumlah = Rp. 46,378.75

60 1 M2 Pengecatan besi/pipa anti karat (exterior painting).


0.350 kg Cat besi 40,800.00 = Rp. 14,280.00
0.170 ltr Meni besi 12,900.00 = Rp. 2,193.00
0.150 ltr Minyak cat 3,200.00 = Rp. 480.00
0.500 lbr Kertas ampelas besi 5,400.00 = Rp. 2,700.00
0.100 lbr Kuas 11,200.00 = Rp. 1,120.00
0.150 oh Pekerja 25,000.00 = Rp. 3,750.00
0.225 oh Tukang cat/pelitur 42,500.00 = Rp. 9,562.50
0.225 oh Kepala tukang cat/pelitur 45,800.00 = Rp. 10,305.00
0.025 oh Mandor 37,500.00 = Rp. 937.50
1.000 ls Alat bantu = Rp. 906.56
Jumlah = Rp. 46,234.56

61 1 kg Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m


396.0 Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m
396.0 kg Besi profil Ex DN (SII) 6,000.00 = Rp. 2,376,000.00
16.20 m Pemotongan plat baja 46,378.75 = Rp. 751,335.75
4.050 m Pengelasan as badan HC 102,847.50 = Rp. 416,532.38
2.000 oh Pekerja 25,000.00 = Rp. 50,000.00
1.000 oh Tukang besi profil 45,800.00 = Rp. 45,800.00
0.010 oh Mandor 37,500.00 = Rp. 375.00
1.000 ls Alat bantu = Rp. 72,800.86
Jumlah = Rp. 3,712,843.99
Harga Satuan 1 kg Pembuatan Gelagar HC = Rp. 9,375.87

62 1 kg Pekerjaan konstruksi rangka baja


110.00 kg Besi siku 6,000.00 = Rp. 660,000.00
1.20 kg Pemotongan besi 46,378.75 = Rp. 55,654.50
2.40 bh Pengelasan rangka baja 102,847.50 = Rp. 246,834.00
1.00 ls Alat bantu = Rp. 19,437.29
Jumlah = Rp. 981,930.00
1 kg Pekerjaan konstruksi rangka baja = Rp. 8,926.64

63 1 unit Bar Matahari Pipa Dia. 300 mm (sesuai gambar).


18.00 kg Besi tulangan polos 6,200.00 = Rp. 111,600.00
1.50 kg Besi strip 3 mm 6,000.00 = Rp. 9,000.00
2.00 bh Baut mur M12 29,200.00 = Rp. 58,400.00
1.00 bh Karet packing = Rp. 5,000.00
1.00 ls Biaya pabrikasi 25,000.00 = Rp. 22,500.00
Jumlah = Rp. 206,500.00
Dibulatkan = Rp. 206,500.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah

64 1 unit Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur.


11.30 kg Besi plat 11,500.00 = Rp. 129,996.00
4.00 bh Angkur baut M16 29,200.00 = Rp. 116,800.00
1.00 ls Biaya pabrikasi 15,000.00 = Rp. 15,000.00
Jumlah = Rp. 261,796.00
Dibulatkan = Rp. 261,800.00

65 1 unit Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur.
1.25 kg Besi plat 11,500.00 = Rp. 14,380.81
2.00 bh Baut mur M12 29,200.00 = Rp. 58,400.00
1.00 bh Karet packing 1/2 diameter. = Rp. 5,000.00
1.00 ls Biaya pabrikasi 10,000.00 = Rp. 10,000.00
Jumlah = Rp. 87,780.81
Dibulatkan = Rp. 87,780.00

66 1 unit Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5
39.11 m Besi siku (Rangka tutup & rangka lubang) 3,000.00 = Rp. 117,342.00
39.25 kg Besi plat 11,500.00 = Rp. 451,375.00
2.00 bh Engsel baja 12,500.00 = Rp. 25,000.00
2.00 bh Handle, besi dia. 16 mm di las pada tutup 2,500.00 = Rp. 5,000.00
1.00 bh Kunci gembok 17,500.00 = Rp. 17,500.00
8.00 bh Angkur dia. 12 mm 2,500.00 = Rp. 20,000.00
1.00 bh Kait gembok dilas pada rangka 2,500.00 = Rp. 2,500.00
1.00 ls Biaya pengelasan/pabrikasi & pasang 150,000.00 = Rp. 150,000.00
Jumlah = Rp. 788,717.00
Dibulatkan = Rp. 788,720.00

67 1 m' Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm.


4.71 kg Besi plat 11,500.00 = Rp. 54,165.00
1.20 m 60% pekerjaan pemotong plat dengan las 27,827.25 = Rp. 33,392.70
1.00 ls Biaya pemasangan dan alat bantu = Rp. 8,755.77
Jumlah = Rp. 96,313.47
Dibulatkan = Rp. 96,310.00
E PEKERJAAN KAYU

68 1 M3 Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15.


1.100 kg Kayu borneo 2,633,900.00 = Rp. 2,897,290.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
12.000 oh Tukang Kayu 42,500.00 = Rp. 510,000.00
4.000 oh Tukang kayu semi terampil 41,700.00 = Rp. 166,800.00
1.200 oh Kepala tukang kayu 45,800.00 = Rp. 54,960.00
0.300 oh Mandor 37,500.00 = Rp. 11,250.00
1.000 ls Alat bantu = Rp. 189,515.00
Jumlah = Rp. 3,979,815.00
Dibulatkan = Rp. 3,979,820.00

69 1 M3 Rangka kusen pintu dan jendela, Kayu Kamper medan


1.100 kg Kayu kamper medan 3,956,800.00 = Rp. 4,352,480.00
12.000 oh Pekerja 25,000.00 = Rp. 300,000.00
20.000 oh Tukang Kayu 42,500.00 = Rp. 850,000.00
6.000 oh Tukang kayu semi terampil 41,700.00 = Rp. 250,200.00
2.400 oh Kepala tukang kayu 45,800.00 = Rp. 109,920.00
0.300 oh Mandor 37,500.00 = Rp. 11,250.00
1.000 ls Alat bantu = Rp. 293,692.50
Jumlah = Rp. 6,167,542.50
Dibulatkan = Rp. 6,167,540.00

70 1 M2 Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3
25 bh Genteng pres 3,900.00 = Rp. 97,500.00
0.013 m3 Kayu borneo 2,633,900.00 = Rp. 34,240.70
0.25 kg Paku biasa 10,800.00 = Rp. 2,700.00
0.400 oh Pekerja 25,000.00 = Rp. 10,000.00
0.600 oh Tukang Kayu 42,500.00 = Rp. 25,500.00
0.100 oh Kepala tukang kayu 45,800.00 = Rp. 4,580.00
0.010 oh Mandor 37,500.00 = Rp. 375.00
1.000 ls Alat bantu = Rp. 3,869.79
Jumlah = Rp. 178,765.49
Dibulatkan = Rp. 178,770.00

71 1 M2 Penutup bubungan
5.000 bh Genteng bubungan 5,700.00 = Rp. 28,500.00
No Uraian Pekerjaan Harga Satuan Jumlah

0.270 zak Portland cement 48,300.00 = Rp. 13,041.00


0.032 m3 Pasir pasang 116,600.00 = Rp. 3,731.20
0.300 oh Pekerja 25,000.00 = Rp. 7,500.00
0.150 oh Tukang batu semi terampil 38,300.00 = Rp. 5,745.00
0.020 oh Mandor 37,500.00 = Rp. 750.00
1.000 ls Alat bantu = Rp. 2,963.36
Jumlah = Rp. 62,230.56
Dibulatkan = Rp. 62,230.00
No Uraian Pekerjaan Harga Satuan Jumlah

72 1 m1 Lisplank, kayu borne 2x3/20


0.009 m3 Kayu borneo 2,633,900.00 = Rp. 23,178.32
0.1 kg Paku biasa 10,800.00 = Rp. 1,080.00
0.200 oh Pekerja 25,000.00 = Rp. 5,000.00
0.500 oh Tukang Kayu 42,500.00 = Rp. 21,250.00
0.100 oh Kepala tukang kayu 45,800.00 = Rp. 4,580.00
0.010 oh Mandor 37,500.00 = Rp. 375.00
1.000 ls Alat bantu = Rp. 2,773.17
Jumlah = Rp. 58,236.49
Dibulatkan = Rp. 58,240.00

73 1 bh Daun Pintu double triplek, rangka borneo 3/6


0.025 m3 Kayu kamper medan 3,956,800.00 = Rp. 96,941.60
0.711 lbr Kayu Multiplek 4 mm (122 x 242 cm) 45,600.00 = Rp. 32,434.63
0.250 kg Lem kayu 25,000.00 = Rp. 6,250.00
0.020 kg Paku biasa 10,800.00 = Rp. 216.00
2.250 oh Pekerja 25,000.00 = Rp. 56,250.00
6.750 oh Tukang Kayu 42,500.00 = Rp. 286,875.00
0.675 oh Kepala tukang kayu 45,800.00 = Rp. 30,915.00
0.050 oh Mandor 37,500.00 = Rp. 1,875.00
1.000 ls Alat bantu = Rp. 25,587.86
Jumlah = Rp. 537,345.09
Dibulatkan = Rp. 537,350.00

74 1 M3 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7


0.023 m3 Kayu borneo 2,633,900.00 = Rp. 60,579.70
0.023 m2 Asbes eternit 100 x 100 cm 10,000.00 = Rp. 230.00
0.280 oh Pekerja 25,000.00 = Rp. 7,000.00
0.800 oh Tukang Kayu 42,500.00 = Rp. 34,000.00
0.080 oh Kepala tukang kayu 45,800.00 = Rp. 3,664.00
0.015 oh Mandor 37,500.00 = Rp. 562.50
1.000 ls Alat bantu = Rp. 5,301.81
Jumlah = Rp. 111,338.01
Dibulatkan = Rp. 111,340.00

75 1 M2 Daun jendala kaca, kayu 3/10 dan profil 2/3.


0.014 kg Kayu Kamper medan 3,956,800.00 = Rp. 55,395.20
2.400 m profil 2/3 6,500.00 = Rp. 15,600.00
0.500 oh Pekerja 25,000.00 = Rp. 12,500.00
1.000 oh Tukang Kayu 42,500.00 = Rp. 42,500.00
0.150 oh Kepala tukang kayu 45,800.00 = Rp. 6,870.00
0.015 oh Mandor 37,500.00 = Rp. 562.50
1.000 ls Alat bantu = Rp. 6,671.39
Jumlah = Rp. 140,099.09
Dibulatkan = Rp. 140,100.00
ANALISA PEKERJAAN
No Uraian Pekerjaan Harga Satuan Jumlah

F PEKERJAAN PEMASANGAN PIPA BAJA

76 1 kg Pengangkutan pipa baja ke lokasi galian.


3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian.
2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km
4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp. 200,000.00
8.000 oh Pekerja 25,000.00 = Rp. 200,000.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00
1.000 ls Alat bantu = Rp. 48,330.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 531,600.00
Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp. 170.00

8 btg Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda.


15.000 kg Kawat Las Listrik 11,100.00 = Rp. 166,500.00
6.000 jam Welding Mechine 500A 16,700.00 = Rp. 100,200.00
1.000 unit Bahan cairan spay uji las (2 tube) 149,900.00 = Rp. 149,900.00
1.200 kg Coltar primer anti karat 12,900.00 = Rp. 15,480.00
96.00 bh Baut baja , Mur , Ring 4,000.00 = Rp. 384,000.00
8.00 bh Packing Loose Flange 7,500.00 = Rp. 60,000.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
6.000 oh Operator semi terampil 45,800.00 = Rp. 274,800.00
2.000 oh Tukang las 50,000.00 = Rp. 100,000.00
0.020 oh Mandor 37,500.00 = Rp. 750.00
1.000 ls Alat bantu = Rp. 143,913.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,583,000.00
1 Meter Penyambungan pipa GI dengan flange = Rp. 32,900.00

77 1 M' Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) = Rp. 49,468.75
78 1 M' Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg ) = Rp. 56,535.71

79 1 M' Pemasangan Pipa GI ND. 250 mm, diatas tumpuan


31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 5,473.88
Jumlah ( Dibulatkan dalam ratusan) = Rp. 60,200.00

80 1 M' Pemasangan Pipa GI ND. 300 mm, diatas tumpuan


36.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,120.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 6,265.57
Jumlah ( Dibulatkan dalam ratusan) = Rp. 68,900.00

81 1 M' Pemasangan GI Dia. 250 mm, Galian tanah biasa.


0.720 m3 Galian tanah biasa 19,680.00 = Rp. 14,169.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 9,694.91
Jumlah ( Dibulatkan dalam ratusan) = Rp. 106,600.00

82 1 M' Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu.


0.720 m3 Galian tanah berbatu 39,370.00 = Rp. 28,346.40
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
No Uraian Pekerjaan Harga Satuan Jumlah
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 13,001.73
Jumlah ( Dibulatkan dalam ratusan) = Rp. 124,100.00
No Uraian Pekerjaan Harga Satuan Jumlah
83 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III.
0.720 m2 Bongkaran perkerasan jalan kelas III (40 cm) 22,640.00 = Rp. 16,300.80
0.480 m3 Galian tanah berbatu 39,370.00 = Rp. 18,897.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 15,337.13
Jumlah ( Dibulatkan dalam ratusan) = Rp. 133,300.00

84 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I.


0.720 m2 Bongkaran perkerasan jalan kelas I (15 cm) 24,840.00 = Rp. 17,884.80
0.480 m3 Galian tanah berbatu 39,370.00 = Rp. 18,897.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 11,956.19
Jumlah ( Dibulatkan dalam ratusan) = Rp. 131,500.00

85 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block.


0.720 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 3,103.20
0.600 m3 Galian tanah berbatu 39,370.00 = Rp. 23,622.00
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.458 m3 Urugan kembali 8,620.00 = Rp. 3,943.65
0.458 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,627.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 10,824.95
Jumlah ( Dibulatkan dalam ratusan) = Rp. 119,000.00

86 1 M' Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu.


0.780 m3 Galian dasar sungai berbatu 71,250.00 = Rp. 55,575.00
0.70 m3 Pasangan batu kosong (bahan setempat) 28,300.00 = Rp. 19,810.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 27,642.14
Jumlah ( Dibulatkan dalam ratusan) = Rp. 165,800.00

87 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa.


0.780 m3 Galian tanah biasa 19,680.00 = Rp. 15,350.40
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.530 m3 Urugan kembali 8,620.00 = Rp. 4,568.60
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,519.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 10,948.91
Jumlah ( Dibulatkan dalam ratusan) = Rp. 120,400.00

88 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu.


0.780 m3 Galian tanah berbatu 39,370.00 = Rp. 30,708.60
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.530 m3 Urugan kembali 8,620.00 = Rp. 4,568.60
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,519.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
No Uraian Pekerjaan Harga Satuan Jumlah
1.000 ls Alat bantu = Rp. 12,484.73
Jumlah ( Dibulatkan dalam ratusan) = Rp. 137,300.00
No Uraian Pekerjaan Harga Satuan Jumlah
89 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III.
0.600 m2 Bongkaran jalan Kelas III 22,640.00 = Rp. 13,584.00
0.455 m3 Galian tanah berbatu 39,370.00 = Rp. 17,913.35
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.465 m3 Urugan kembali 8,620.00 = Rp. 4,008.30
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,719.50
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 12,427.63
Jumlah ( Dibulatkan dalam ratusan) = Rp. 136,700.00

90 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I.


0.600 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 14,904.00
0.618 m3 Galian tanah berbatu 39,370.00 = Rp. 24,310.98
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.465 m3 Urugan kembali 8,620.00 = Rp. 4,008.30
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,719.50
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 13,097.39
Jumlah ( Dibulatkan dalam ratusan) = Rp. 144,000.00

91 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block.


1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 4,310.00
0.630 m3 Galian tanah berbatu 39,370.00 = Rp. 24,803.10
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,781.00
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 12,097.66
Jumlah ( Dibulatkan dalam ratusan) = Rp. 133,000.00

92 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 44,156.25
3.000 kg Kaporit 15,000.00 = Rp. 45,000.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 104,000.00
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 62,400.00
1.000 ls Alat bantu = Rp. 117,945.63
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,297,401.88
Biaya Pengetesan per 1m panjang = Rp. 2,590.00

93 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 63,585.00
4.500 kg Kaporit 15,000.00 = Rp. 67,500.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
No Uraian Pekerjaan Harga Satuan Jumlah
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 124,800.00
10.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 104,000.00
1.000 ls Alat bantu = Rp. 128,378.50
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,412,163.50
Biaya Pengetesan per 1m panjang = Rp. 2,820.00
No Uraian Pekerjaan Harga Satuan Jumlah
G PEKERJAAN PEMASANGAN PIPA PVC

94 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm


200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian.
1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m)
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00
1.000 ls Alat bantu = Rp. 18,745.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 393,645.00
Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp. 330.00

95 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm


110 % Analisa F.48 330.00 = Rp. 363.00
96 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm
120 % Analisa F.48 330.00 = Rp. 396.00
97 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm
140 % Analisa F.48 330.00 = Rp. 462.00
98 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm
170 % Analisa F.48 330.00 = Rp. 561.00
99 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm
210 % Analisa F.48 330.00 = Rp. 693.00
100 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm
260 % Analisa F.48 330.00 = Rp. 858.00
101 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm
310 % Analisa F.48 330.00 = Rp. 1,023.00

102 1 M' Penyambungan pipa PVC Dia. 50 mm didalam galian


360 m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung.
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
1.000 oh Tukang batu semi terampil 38,300.00 = Rp. 38,300.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
1.000 oh Mandor 37,500.00 = Rp. 37,500.00
0.100 An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp. 5,067.00
1.000 ls Alat bantu = Rp. 12,540.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 268,407.00
Biaya Penyambungan per 1 m panjang Pipa. = Rp. 750.00

103 1 M' Penyambungan pipa PVC Dia. 75 mm didalam galian


105 % Analisa F.50 750.00 = Rp. 787.50
104 1 M' Penyambungan pipa PVC Dia. 100 mm didalam galian
125 % Analisa F.50 750.00 = Rp. 937.50
105 1 M' Penyambungan pipa PVC Dia. 150 mm didalam galian
175 % Analisa F.50 750.00 = Rp. 1,312.50
106 1 M' Penyambungan pipa PVC Dia. 200 mm didalam galian
200 % Analisa F.50 750.00 = Rp. 1,500.00
107 1 M' Penyambungan pipa PVC Dia. 250 mm didalam galian
240 % Analisa F.50 750.00 = Rp. 1,800.00
108 1 M' Penyambungan pipa PVC Dia. 300 mm didalam galian
275 % Analisa F.50 750.00 = Rp. 2,062.50
109 1 M' Penyambungan pipa PVC Dia. 400 mm didalam galian
300 % Analisa F.50 750.00 = Rp. 2,250.00

110 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa.
0.385 m3 Galian tanah biasa 19,680.00 = Rp. 7,576.80
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.088 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,924.67
0.295 m3 Urugan kembali 8,620.00 = Rp. 2,542.90
0.295 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,628.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
No Uraian Pekerjaan Harga Satuan Jumlah
1.00 ls Alat bantu = Rp. 2,446.16
Jumlah ( Dibulatkan dalam ratusan) = Rp. 26,900.00

111 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa.
0.399 m3 Galian tanah biasa 19,680.00 = Rp. 7,847.40
0.106 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 831.80
0.100 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,170.73
0.307 m3 Urugan kembali 8,620.00 = Rp. 2,645.26
0.307 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,774.56
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 2,642.02
Jumlah ( Dibulatkan dalam ratusan) = Rp. 29,000.00
No Uraian Pekerjaan Harga Satuan Jumlah

112 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa.
0.509 m3 Galian tanah biasa 19,680.00 = Rp. 10,012.20
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.115 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 11,674.08
0.345 m3 Urugan kembali 8,620.00 = Rp. 2,973.90
0.345 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,243.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 3,120.19
Jumlah ( Dibulatkan dalam ratusan) = Rp. 34,300.00

113 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa.
0.536 m3 Galian tanah biasa 19,680.00 = Rp. 10,553.40
0.141 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,107.42
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,492.71
0.371 m3 Urugan kembali 8,620.00 = Rp. 3,196.94
0.371 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,561.76
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 3,668.67
Jumlah ( Dibulatkan dalam ratusan) = Rp. 40,300.00

114 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa.
0.542 m3 Galian tanah biasa 19,680.00 = Rp. 10,661.64
0.148 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,167.27
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,492.71
0.380 m3 Urugan kembali 8,620.00 = Rp. 3,273.66
0.380 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,671.23
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 3,732.75
Jumlah ( Dibulatkan dalam ratusan) = Rp. 41,000.00

115 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa.
0.550 m3 Galian tanah biasa 19,680.00 = Rp. 10,824.00
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,260.00
0.177 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,028.27
0.390 m3 Urugan kembali 8,620.00 = Rp. 3,361.80
0.390 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,797.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 4,076.41
Jumlah ( Dibulatkan dalam ratusan) = Rp. 44,800.00

1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 17,388.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,074.38
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.524 m3 Urugan kembali 8,620.00 = Rp. 4,513.19
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,439.93
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 5,300.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 69,300.00

1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa.
0.688 m3 Galian tanah biasa 19,680.00 = Rp. 13,530.00
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.219 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 22,272.14
0.424 m3 Urugan kembali 8,620.00 = Rp. 3,652.73
No Uraian Pekerjaan Harga Satuan Jumlah
0.424 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,212.13
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 5,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 55,000.00
No Uraian Pekerjaan Harga Satuan Jumlah

1 M' Pemasangan Pipa STEEL Dia. 300 mm, Galian tanah berbatu.
0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 27,992.07
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,781.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 8,000.00 = Rp. 8,000.00
1.000 ls Alat bantu = Rp. 8,000.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 74,900.00

1 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa.
0.715 m3 Galian tanah biasa 19,680.00 = Rp. 14,071.20
0.270 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,129.40
0.232 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,649.29
0.434 m3 Urugan kembali 8,620.00 = Rp. 3,737.63
0.434 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,333.28
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 5,184.13
Jumlah ( Dibulatkan dalam ratusan) = Rp. 57,000.00

2 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa.
0.840 m3 Galian tanah biasa 19,680.00 = Rp. 16,531.20
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.480 m3 Urugan kembali 8,620.00 = Rp. 4,137.60
0.480 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,904.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 5,653.81
Jumlah ( Dibulatkan dalam ratusan) = Rp. 62,100.00

3 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras


0.399 m3 Galian tanah keras 26,870.00 = Rp. 10,714.41
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.120 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 12,234.15
0.263 m3 Urugan tanah kembali 8,620.00 = Rp. 2,262.75
0.263 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,228.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.00 ls Alat bantu = Rp. 5,300.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 35,700.00

4 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras


0.413 m3 Galian tanah keras 26,870.00 = Rp. 11,083.88
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.127 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 12,957.14
0.290 m3 Urugan tanah kembali 8,620.00 = Rp. 2,499.80
0.290 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,567.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 4,800.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 37,000.00
No Uraian Pekerjaan Harga Satuan Jumlah

5 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras.
0.495 m3 Galian tanah keras 26,870.00 = Rp. 13,300.65
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,260.00
0.158 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 16,052.77
0.308 m3 Urugan tanah kembali 8,620.00 = Rp. 2,650.65
0.308 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,782.25
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 5,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 43,400.00

6 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras.
0.550 m3 Galian tanah keras 26,870.00 = Rp. 14,778.50
0.181 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,422.42
0.200 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 20,380.55
0.314 m3 Urugan tanah kembali 8,620.00 = Rp. 2,709.91
0.314 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,866.81
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1,062.00 = Rp. 1,062.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,812.50 = Rp. 1,812.50
1.00 ls Alat bantu = Rp. 7,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 53,100.00

7 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras.
0.561 m3 Galian tanah keras 26,870.00 = Rp. 15,074.07
0.185 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,456.09
0.201 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 20,472.30
0.327 m3 Urugan tanah kembali 8,620.00 = Rp. 2,815.29
0.327 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,017.18
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 7,400.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 53,000.00

8 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras.
0.605 m3 Galian tanah keras 26,870.00 = Rp. 16,256.35
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.228 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,221.60
0.355 m3 Urugan tanah kembali 8,620.00 = Rp. 3,060.10
0.355 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,366.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 59,400.00

9 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras.
0.660 m3 Galian tanah keras 26,870.00 = Rp. 17,734.20
0.281 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,212.09
0.328 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 33,427.52
0.352 m3 Urugan tanah kembali 8,620.00 = Rp. 3,030.79
0.352 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,324.68
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 9,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 72,700.00

10 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras.
0.688 m3 Galian tanah keras 26,870.00 = Rp. 18,473.13
0.303 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,382.19
0.332 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 33,779.75
0.413 m3 Urugan tanah kembali 8,620.00 = Rp. 3,555.75
0.413 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,073.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
No Uraian Pekerjaan Harga Satuan Jumlah
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 10,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 76,200.00
No Uraian Pekerjaan Harga Satuan Jumlah

11 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras
0.715 m3 Galian tanah keras 26,870.00 = Rp. 19,212.05
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.407 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 41,469.54
0.465 m3 Urugan tanah kembali 8,620.00 = Rp. 4,008.30
0.465 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,719.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.000 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.000 ls Alat bantu = Rp. 11,400.00
Jumlah = Rp. 85,700.00

12 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu


0.373 m3 Galian tanah berbatu 39,370.00 = Rp. 14,665.33
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 492.19
0.061 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 6,164.35
0.295 m3 Urugan tanah kembali 8,620.00 = Rp. 2,542.90
0.295 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,628.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.00 ls Alat bantu = Rp. 5,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 34,000.00

13 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu


0.381 m3 Galian tanah berbatu 39,370.00 = Rp. 15,009.81
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 492.19
0.071 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 7,250.84
0.309 m3 Urugan tanah kembali 8,620.00 = Rp. 2,661.43
0.309 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,797.63
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 5,900.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 36,200.00

14 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu.
0.455 m3 Galian tanah berbatu 39,370.00 = Rp. 17,913.35
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,364.61
0.350 m3 Urugan tanah kembali 8,620.00 = Rp. 3,017.00
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,305.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 6,700.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 42,300.00

15 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu.
0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 7,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 48,300.00

16 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu.
0.550 m3 Galian tanah berbatu 39,370.00 = Rp. 21,653.50
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,740.16
0.389 m3 Urugan tanah kembali 8,620.00 = Rp. 3,348.87
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,778.55
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
No Uraian Pekerjaan Harga Satuan Jumlah
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 7,800.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 51,000.00
No Uraian Pekerjaan Harga Satuan Jumlah
17 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu.
0.558 m3 Galian tanah berbatu 39,370.00 = Rp. 21,968.46
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.403 m3 Urugan tanah kembali 8,620.00 = Rp. 3,469.55
0.403 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,950.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,200.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 58,200.00

18 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu.
0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 27,992.07
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,781.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 8,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 69,400.00

1 M' Pemasangan Pipa STEEL Dia. 300 mm, Galian tanah berbatu.
0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 27,992.07
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,781.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 14,800.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 75,700.00

19 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu.
0.730 m3 Galian tanah berbatu 39,370.00 = Rp. 28,740.10
0.260 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,048.29
0.189 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 19,285.15
0.490 m3 Urugan tanah kembali 8,620.00 = Rp. 4,222.94
0.490 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,025.77
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 16,759.33
Jumlah ( Dibulatkan dalam ratusan) = Rp. 80,000.00

19 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu
0.805 m3 Galian tanah berbatu 39,370.00 = Rp. 31,692.85
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.480 m3 Urugan tanah kembali 8,620.00 = Rp. 4,137.60
0.480 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,904.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 17,207.94
Jumlah ( Dibulatkan dalam ratusan) = Rp. 88,900.00

1 M' Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu.


0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
No Uraian Pekerjaan Harga Satuan Jumlah
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 170.00
1.00 m1 Penyambungan dan pengelasan pipa. 23,000.00 = Rp. 23,000.00
1.00 ls Alat bantu = Rp. 40,000.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 102,200.00

1 M' Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu.


0.550 m3 Galian tanah berbatu 39,370.00 = Rp. 21,653.50
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,740.16
0.389 m3 Urugan tanah kembali 8,620.00 = Rp. 3,348.87
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,778.55
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 170.00
1.00 m1 Penyambungan dan pengelasan pipa. 24,000.00 = Rp. 24,000.00
1.00 ls Alat bantu = Rp. 57,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 122,800.00
No Uraian Pekerjaan Harga Satuan Jumlah
20 1 M' Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar.
0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 2,586.00
0.400 m3 Galian tanah berbatu 39,370.00 = Rp. 15,748.00
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,364.61
0.350 m3 Urugan tanah kembali 8,620.00 = Rp. 3,017.00
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,305.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 3,347.69
Jumlah ( Dibulatkan dalam ratusan) = Rp. 36,800.00

21 1 M' Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar.


0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 2,586.00
0.400 m3 Galian tanah berbatu 39,370.00 = Rp. 15,748.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 3,695.39
Jumlah ( Dibulatkan dalam ratusan) = Rp. 40,600.00

22 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar.


1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 4,310.00
0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.131 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,035.00
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.419 m3 Urugan kembali 8,620.00 = Rp. 3,608.09
0.419 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,148.43
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 4,893.99
Jumlah ( Dibulatkan dalam ratusan) = Rp. 53,800.00

23 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar.


1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 4,310.00
0.600 m3 Galian tanah berbatu 39,370.00 = Rp. 23,622.00
0.149 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,174.22
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.511 m3 Urugan kembali 8,620.00 = Rp. 4,403.90
0.511 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,283.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 5,790.71
Jumlah ( Dibulatkan dalam ratusan) = Rp. 63,600.00

24 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar.


1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 4,310.00
0.660 m3 Galian tanah berbatu 39,370.00 = Rp. 25,984.20
0.171 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,344.38
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.489 m3 Urugan kembali 8,620.00 = Rp. 4,217.64
0.489 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,018.21
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 6,305.16
Jumlah ( Dibulatkan dalam ratusan) = Rp. 69,300.00

25 1 M' Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar.


1.200 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 5,172.00
0.720 m3 Galian tanah berbatu 39,370.00 = Rp. 28,346.40
No Uraian Pekerjaan Harga Satuan Jumlah
0.246 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,935.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.414 m3 Urugan kembali 8,620.00 = Rp. 3,571.14
0.414 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,095.71
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 7,125.06
Jumlah ( Dibulatkan dalam ratusan) = Rp. 78,300.00
No Uraian Pekerjaan Harga Satuan Jumlah
26 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III.
0.700 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. 15,848.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.311 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,452.50
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.349 m3 Urugan kembali 8,620.00 = Rp. 3,004.69
0.349 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,287.43
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 5,728.14
Jumlah ( Dibulatkan dalam ratusan) = Rp. 63,000.00

27 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III.
0.750 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. 16,980.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.349 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,749.22
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.311 m3 Urugan kembali 8,620.00 = Rp. 2,679.90
0.311 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,823.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 6,088.15
Jumlah ( Dibulatkan dalam ratusan) = Rp. 66,900.00

28 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III.
0.800 m2 Bongkaran jalan Kelas III 22,640.00 = Rp. 18,112.00
0.585 m3 Galian tanah berbatu 39,370.00 = Rp. 23,031.45
0.236 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,856.25
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.564 m3 Urugan kembali 8,620.00 = Rp. 4,864.14
0.564 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,940.71
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 7,598.17
Jumlah ( Dibulatkan dalam ratusan) = Rp. 83,500.00

29 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 17,388.00
0.368 m3 Galian tanah berbatu 39,370.00 = Rp. 14,468.48
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,074.38
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.524 m3 Urugan kembali 8,620.00 = Rp. 4,513.19
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,439.93
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 5,903.74
Jumlah ( Dibulatkan dalam ratusan) = Rp. 64,900.00

30 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 17,388.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,074.38
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.524 m3 Urugan kembali 8,620.00 = Rp. 4,513.19
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,439.93
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,328.30
Jumlah ( Dibulatkan dalam ratusan) = Rp. 72,300.00

31 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I.
0.800 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 19,872.00
0.585 m3 Galian tanah berbatu 39,370.00 = Rp. 23,031.45
No Uraian Pekerjaan Harga Satuan Jumlah
0.169 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,331.72
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.491 m3 Urugan kembali 8,620.00 = Rp. 4,231.50
0.491 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,037.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 7,568.18
Jumlah ( Dibulatkan dalam ratusan) = Rp. 83,200.00
No Uraian Pekerjaan Harga Satuan Jumlah
32 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 1,766.25
0.118 kg Kaporit 15,000.00 = Rp. 1,766.25
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
0.100 oh Mandor 37,500.00 = Rp. 3,750.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 62,400.00
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 41,600.00
1.000 ls Alat bantu = Rp. 74,858.25
Jumlah = Rp. 823,440.75
Biaya Pengetesan per 1m panjang = Rp. 1,640.00

33 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.


500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.
6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 3,974.06
0.265 kg Kaporit 15,000.00 = Rp. 3,974.06
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
0.100 oh Mandor 37,500.00 = Rp. 3,750.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 62,400.00
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 41,600.00
1.000 ls Alat bantu = Rp. 75,299.81
Jumlah = Rp. 828,297.94
Biaya Pengetesan per 1m panjang = Rp. 1,650.00

34 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 7,065.00
0.471 kg Kaporit 15,000.00 = Rp. 7,065.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
5.000 jam Pickup Truck 47,900.00 = Rp. 239,500.00
1.500 oh Tukang pipa 37,500.00 = Rp. 56,250.00
0.150 oh Mandor 37,500.00 = Rp. 5,625.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
8.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 83,200.00
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 62,400.00
1.000 ls Alat bantu = Rp. 91,930.50
Jumlah = Rp. 1,011,235.50
Biaya Pengetesan per 1m panjang = Rp. 2,020.00

35 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 15,896.25
1.060 kg Kaporit 15,000.00 = Rp. 15,896.25
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
5.000 jam Pickup Truck 47,900.00 = Rp. 239,500.00
1.500 oh Tukang pipa 37,500.00 = Rp. 56,250.00
0.150 oh Mandor 37,500.00 = Rp. 5,625.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
No Uraian Pekerjaan Harga Satuan Jumlah
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
9.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 93,600.00
7.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 72,800.00
1.000 ls Alat bantu = Rp. 95,776.75
Jumlah = Rp. 1,053,544.25
Biaya Pengetesan per 1m panjang = Rp. 2,100.00
No Uraian Pekerjaan Harga Satuan Jumlah
36 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 28,260.00
1.884 kg Kaporit 15,000.00 = Rp. 28,260.00
7.000 oh Pekerja 25,000.00 = Rp. 175,000.00
6.000 jam Pickup Truck 47,900.00 = Rp. 287,400.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 104,000.00
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 83,200.00
1.000 ls Alat bantu = Rp. 109,682.00
Jumlah = Rp. 1,206,502.00
Biaya Pengetesan per 1m panjang = Rp. 2,410.00

37 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 44,156.25
2.944 kg Kaporit 15,000.00 = Rp. 44,156.25
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
11.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 114,400.00
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 83,200.00
1.000 ls Alat bantu = Rp. 120,981.25
Jumlah = Rp. 1,330,793.75
Biaya Pengetesan per 1m panjang = Rp. 2,660.00

38 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 63,585.00
4.239 kg Kaporit 15,000.00 = Rp. 63,585.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 124,800.00
9.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 93,600.00
1.000 ls Alat bantu = Rp. 126,947.00
Jumlah = Rp. 1,396,417.00
Biaya Pengetesan per 1m panjang = Rp. 2,790.00

39 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 113,040.00
7.536 kg Kaporit 15,000.00 = Rp. 113,040.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
No Uraian Pekerjaan Harga Satuan Jumlah
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
18.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 187,200.00
12.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 124,800.00
1.000 ls Alat bantu = Rp. 146,198.00
Jumlah = Rp. 1,608,178.00
Biaya Pengetesan per 1m panjang = Rp. 3,210.00
ANALISA PEKERJAAN
No Uraian Pekerjaan Harga Satuan Jumlah

F PEKERJAAN PEMASANGAN PIPA BAJA

76 1 kg Pengangkutan pipa baja ke lokasi galian.


3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian.
2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km
4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp.
8.000 oh Pekerja 25,000.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
1.000 oh Pembantu sopir 33,300.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp.

8 btg Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda.


15.000 kg Kawat Las Listrik 11,100.00 = Rp.
6.000 jam Welding Mechine 500A 16,700.00 = Rp.
1.000 unit Bahan cairan spay uji las (2 tube) 149,900.00 = Rp.
1.200 kg Coltar primer anti karat 12,900.00 = Rp.
96.00 bh Baut baja , Mur , Ring 4,000.00 = Rp.
8.00 bh Packing Loose Flange 7,500.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
1.000 oh Tukang pipa 37,500.00 = Rp.
6.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Tukang las 50,000.00 = Rp.
0.020 oh Mandor 37,500.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
1 Meter Penyambungan pipa GI dengan flange = Rp.

77 1 M' Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) = Rp.
78 1 M' Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg ) = Rp.

79 1 M' Pemasangan Pipa GI ND. 250 mm, diatas tumpuan


31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

80 1 M' Pemasangan Pipa GI ND. 300 mm, diatas tumpuan


36.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

81 1 M' Pemasangan GI Dia. 250 mm, Galian tanah biasa.


0.720 m3 Galian tanah biasa 19,680.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.518 m3 Urugan tanah kembali 8,620.00 = Rp.
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

82 1 M' Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu.


0.720 m3 Galian tanah berbatu 39,370.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.518 m3 Urugan tanah kembali 8,620.00 = Rp.
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

83 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III.
0.720 m2 Bongkaran perkerasan jalan kelas III (40 cm) 22,640.00 = Rp.
0.480 m3 Galian tanah berbatu 39,370.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.518 m3 Urugan tanah kembali 8,620.00 = Rp.
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

84 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I.


0.720 m2 Bongkaran perkerasan jalan kelas I (15 cm) 24,840.00 = Rp.
0.480 m3 Galian tanah berbatu 39,370.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.518 m3 Urugan tanah kembali 8,620.00 = Rp.
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

85 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block.


0.720 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp.
0.600 m3 Galian tanah berbatu 39,370.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.458 m3 Urugan kembali 8,620.00 = Rp.
0.458 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

86 1 M' Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu.


0.780 m3 Galian dasar sungai berbatu 71,250.00 = Rp.
0.70 m3 Pasangan batu kosong (bahan setempat) 28,300.00 = Rp.
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

87 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa.


0.780 m3 Galian tanah biasa 19,680.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.530 m3 Urugan kembali 8,620.00 = Rp.
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

88 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu.


0.780 m3 Galian tanah berbatu 39,370.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.530 m3 Urugan kembali 8,620.00 = Rp.
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

89 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III.
0.600 m2 Bongkaran jalan Kelas III 22,640.00 = Rp.
0.455 m3 Galian tanah berbatu 39,370.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.465 m3 Urugan kembali 8,620.00 = Rp.
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

90 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I.


0.600 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp.
0.618 m3 Galian tanah berbatu 39,370.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.465 m3 Urugan kembali 8,620.00 = Rp.
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

91 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block.


1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp.
0.630 m3 Galian tanah berbatu 39,370.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.470 m3 Urugan kembali 8,620.00 = Rp.
0.470 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

92 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
3.000 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
8.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
Biaya Pengetesan per 1m panjang = Rp.

93 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
4.500 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
8.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
10.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
Biaya Pengetesan per 1m panjang = Rp.

G PEKERJAAN PEMASANGAN PIPA PVC

94 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm


200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian.
1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m)
4.000 jam Pickup Truck 47,900.00 = Rp.
4.000 oh Pekerja 25,000.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
1.000 oh Pembantu sopir 33,300.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp.

95 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm


110 % Analisa F.48 330.00 = Rp.
96 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm
120 % Analisa F.48 330.00 = Rp.
97 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm
140 % Analisa F.48 330.00 = Rp.
98 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm
170 % Analisa F.48 330.00 = Rp.
99 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm
210 % Analisa F.48 330.00 = Rp.
100 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm
260 % Analisa F.48 330.00 = Rp.
101 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm
310 % Analisa F.48 330.00 = Rp.

102 1 M' Penyambungan pipa PVC Dia. 50 mm didalam galian


360 m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung.
4.000 oh Pekerja 25,000.00 = Rp.
1.000 oh Tukang batu semi terampil 38,300.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
1.000 oh Mandor 37,500.00 = Rp.
0.100 An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
Biaya Penyambungan per 1 m panjang Pipa. = Rp.

103 1 M' Penyambungan pipa PVC Dia. 75 mm didalam galian


105 % Analisa F.50 750.00 = Rp.
104 1 M' Penyambungan pipa PVC Dia. 100 mm didalam galian
125 % Analisa F.50 750.00 = Rp.
105 1 M' Penyambungan pipa PVC Dia. 150 mm didalam galian
175 % Analisa F.50 750.00 = Rp.
106 1 M' Penyambungan pipa PVC Dia. 200 mm didalam galian
200 % Analisa F.50 750.00 = Rp.
107 1 M' Penyambungan pipa PVC Dia. 250 mm didalam galian
240 % Analisa F.50 750.00 = Rp.
108 1 M' Penyambungan pipa PVC Dia. 300 mm didalam galian
275 % Analisa F.50 750.00 = Rp.
109 1 M' Penyambungan pipa PVC Dia. 400 mm didalam galian
300 % Analisa F.50 750.00 = Rp.

110 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa.
0.385 m3 Galian tanah biasa 19,680.00 = Rp.
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.088 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.295 m3 Urugan kembali 8,620.00 = Rp.
0.295 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

111 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa.
0.399 m3 Galian tanah biasa 19,680.00 = Rp.
0.106 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.100 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.307 m3 Urugan kembali 8,620.00 = Rp.
0.307 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

112 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa.
0.509 m3 Galian tanah biasa 19,680.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.115 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.345 m3 Urugan kembali 8,620.00 = Rp.
0.345 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

113 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa.
0.536 m3 Galian tanah biasa 19,680.00 = Rp.
0.141 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.371 m3 Urugan kembali 8,620.00 = Rp.
0.371 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

114 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa.
0.542 m3 Galian tanah biasa 19,680.00 = Rp.
0.148 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.380 m3 Urugan kembali 8,620.00 = Rp.
0.380 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

115 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa.
0.550 m3 Galian tanah biasa 19,680.00 = Rp.
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.177 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.390 m3 Urugan kembali 8,620.00 = Rp.
0.390 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

116 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa.
0.688 m3 Galian tanah biasa 19,680.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.219 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.424 m3 Urugan kembali 8,620.00 = Rp.
0.424 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

117 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa.
0.715 m3 Galian tanah biasa 19,680.00 = Rp.
0.270 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.232 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.434 m3 Urugan kembali 8,620.00 = Rp.
0.434 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

118 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa.
0.840 m3 Galian tanah biasa 19,680.00 = Rp.
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.480 m3 Urugan kembali 8,620.00 = Rp.
0.480 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

119 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras
0.399 m3 Galian tanah keras 26,870.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.120 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.263 m3 Urugan tanah kembali 8,620.00 = Rp.
0.263 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

120 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras
0.413 m3 Galian tanah keras 26,870.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.127 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.290 m3 Urugan tanah kembali 8,620.00 = Rp.
0.290 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

121 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras.
0.495 m3 Galian tanah keras 26,870.00 = Rp.
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.158 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.308 m3 Urugan tanah kembali 8,620.00 = Rp.
0.308 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

122 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras.
0.550 m3 Galian tanah keras 26,870.00 = Rp.
0.181 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.200 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.314 m3 Urugan tanah kembali 8,620.00 = Rp.
0.314 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.
123 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras.
0.561 m3 Galian tanah keras 26,870.00 = Rp.
0.185 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.201 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.327 m3 Urugan tanah kembali 8,620.00 = Rp.
0.327 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

124 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras.
0.605 m3 Galian tanah keras 26,870.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.228 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.355 m3 Urugan tanah kembali 8,620.00 = Rp.
0.355 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

125 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras.
0.660 m3 Galian tanah keras 26,870.00 = Rp.
0.281 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.328 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.352 m3 Urugan tanah kembali 8,620.00 = Rp.
0.352 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

126 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras.
0.688 m3 Galian tanah keras 26,870.00 = Rp.
0.303 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.332 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.413 m3 Urugan tanah kembali 8,620.00 = Rp.
0.413 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

127 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras
0.715 m3 Galian tanah keras 26,870.00 = Rp.
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.407 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.465 m3 Urugan tanah kembali 8,620.00 = Rp.
0.465 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.

128 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu
0.373 m3 Galian tanah berbatu 39,370.00 = Rp.
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.061 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.295 m3 Urugan tanah kembali 8,620.00 = Rp.
0.295 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

129 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu
0.381 m3 Galian tanah berbatu 39,370.00 = Rp.
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.071 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.309 m3 Urugan tanah kembali 8,620.00 = Rp.
0.309 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

130 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu.
0.455 m3 Galian tanah berbatu 39,370.00 = Rp.
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.350 m3 Urugan tanah kembali 8,620.00 = Rp.
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

131 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu.
0.500 m3 Galian tanah berbatu 39,370.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.373 m3 Urugan tanah kembali 8,620.00 = Rp.
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

132 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu.
0.550 m3 Galian tanah berbatu 39,370.00 = Rp.
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.389 m3 Urugan tanah kembali 8,620.00 = Rp.
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

133 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu.
0.558 m3 Galian tanah berbatu 39,370.00 = Rp.
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.403 m3 Urugan tanah kembali 8,620.00 = Rp.
0.403 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

134 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu.
0.711 m3 Galian tanah berbatu 39,370.00 = Rp.
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.470 m3 Urugan tanah kembali 8,620.00 = Rp.
0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

135 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu.
0.730 m3 Galian tanah berbatu 39,370.00 = Rp.
0.260 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.189 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.490 m3 Urugan tanah kembali 8,620.00 = Rp.
0.490 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

135 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu
0.805 m3 Galian tanah berbatu 39,370.00 = Rp.
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.480 m3 Urugan tanah kembali 8,620.00 = Rp.
0.480 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

Assisten Perencanaan
Proyek Pengembangan Sarana dan
Prasarana Permukiman Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

1 M' Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu.


0.500 m3 Galian tanah berbatu 39,370.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.373 m3 Urugan tanah kembali 8,620.00 = Rp.
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.00 m1 Penyambungan dan pengelasan pipa. 23,000.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

1 M' Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu.


0.550 m3 Galian tanah berbatu 39,370.00 = Rp.
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.389 m3 Urugan tanah kembali 8,620.00 = Rp.
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp.
1.00 m1 Penyambungan dan pengelasan pipa. 24,000.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

Assisten Perencanaan
Proyek Pengembangan Sarana dan Prasarana Permukiman
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568
136 1 M' Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar.
0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp.
0.400 m3 Galian tanah berbatu 39,370.00 = Rp.
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.350 m3 Urugan tanah kembali 8,620.00 = Rp.
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

137 1 M' Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar.
0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp.
0.400 m3 Galian tanah berbatu 39,370.00 = Rp.
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.373 m3 Urugan tanah kembali 8,620.00 = Rp.
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

138 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar.
1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp.
0.500 m3 Galian tanah berbatu 39,370.00 = Rp.
0.131 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.419 m3 Urugan kembali 8,620.00 = Rp.
0.419 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

139 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar.
1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp.
0.600 m3 Galian tanah berbatu 39,370.00 = Rp.
0.149 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.511 m3 Urugan kembali 8,620.00 = Rp.
0.511 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

140 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar.
1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp.
0.660 m3 Galian tanah berbatu 39,370.00 = Rp.
0.171 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.489 m3 Urugan kembali 8,620.00 = Rp.
0.489 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

141 1 M' Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar.
1.200 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp.
0.720 m3 Galian tanah berbatu 39,370.00 = Rp.
0.246 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.414 m3 Urugan kembali 8,620.00 = Rp.
0.414 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

142 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III.
0.700 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp.
0.420 m3 Galian tanah berbatu 39,370.00 = Rp.
0.311 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.349 m3 Urugan kembali 8,620.00 = Rp.
0.349 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

143 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III.
0.750 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp.
0.420 m3 Galian tanah berbatu 39,370.00 = Rp.
0.349 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.311 m3 Urugan kembali 8,620.00 = Rp.
0.311 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

144 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III.
0.800 m2 Bongkaran jalan Kelas III 22,640.00 = Rp.
0.585 m3 Galian tanah berbatu 39,370.00 = Rp.
0.236 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.564 m3 Urugan kembali 8,620.00 = Rp.
0.564 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

145 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp.
0.368 m3 Galian tanah berbatu 39,370.00 = Rp.
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.524 m3 Urugan kembali 8,620.00 = Rp.
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

146 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp.
0.420 m3 Galian tanah berbatu 39,370.00 = Rp.
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.524 m3 Urugan kembali 8,620.00 = Rp.
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp.
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp.
1.00 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

147 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I.
0.800 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp.
0.585 m3 Galian tanah berbatu 39,370.00 = Rp.
0.169 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp.
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp.
0.491 m3 Urugan kembali 8,620.00 = Rp.
0.491 m3 Pemadatan tanah dengan alat 12,300.00 = Rp.
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp.
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah ( Dibulatkan dalam ratusan) = Rp.

148 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
0.118 kg Kaporit 15,000.00 = Rp.
4.000 oh Pekerja 25,000.00 = Rp.
4.000 jam Pickup Truck 47,900.00 = Rp.
1.000 oh Tukang pipa 37,500.00 = Rp.
0.100 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

149 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.
6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
0.265 kg Kaporit 15,000.00 = Rp.
4.000 oh Pekerja 25,000.00 = Rp.
4.000 jam Pickup Truck 47,900.00 = Rp.
1.000 oh Tukang pipa 37,500.00 = Rp.
0.100 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

150 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
0.471 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
5.000 jam Pickup Truck 47,900.00 = Rp.
1.500 oh Tukang pipa 37,500.00 = Rp.
0.150 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
8.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

151 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
1.060 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
5.000 jam Pickup Truck 47,900.00 = Rp.
1.500 oh Tukang pipa 37,500.00 = Rp.
0.150 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
9.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
7.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

152 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
1.884 kg Kaporit 15,000.00 = Rp.
7.000 oh Pekerja 25,000.00 = Rp.
6.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

153 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
2.944 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
8.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
11.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

154 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
4.239 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
8.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
9.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.

155 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp.
7.536 kg Kaporit 15,000.00 = Rp.
6.000 oh Pekerja 25,000.00 = Rp.
8.000 jam Pickup Truck 47,900.00 = Rp.
2.000 oh Tukang pipa 37,500.00 = Rp.
0.200 oh Mandor 37,500.00 = Rp.
1.000 oh Sopir 50,000.00 = Rp.
2.000 oh Operator semi terampil 45,800.00 = Rp.
2.000 oh Pembantu operator 50,000.00 = Rp.
2.000 oh Pembantu sopir 33,300.00 = Rp.
18.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp.
12.000 jam Pressure Pump 20 Bar 10,400.00 = Rp.
1.000 ls Alat bantu = Rp.
Jumlah = Rp.
Biaya Pengetesan per 1m panjang = Rp.
Jumlah

170.00
didekat galian.

200,000.00 s
200,000.00
50,000.00
33,300.00
48,330.00
531,600.00
170.00

166,500.00
100,200.00
149,900.00
15,480.00
384,000.00
60,000.00
150,000.00
37,500.00
274,800.00
100,000.00
750.00
143,913.00 0.79
1,583,000.00 125,920
32,900.00

49,468.75 49,468.75
56,535.71 56,535.71

60,200.00
5,270.00
49,468.75
5,473.88
60,200.00

68,900.00
6,120.00
56,535.71
6,265.57
68,900.00

106,600.00
14,169.60
1,594.69
15,619.99
4,460.85
6,365.25
5,270.00
49,468.75
9,694.91
106,600.00

124,100.00
28,346.40
1,594.69
15,619.99
4,460.85
6,365.25
5,270.00
49,468.75
13,001.73
124,100.00

133,300.00
16,300.80
18,897.60
1,594.69
15,619.99
4,460.85
6,365.25
5,270.00
49,468.75
15,337.13
133,300.00

131,500.00
17,884.80
18,897.60
1,594.69
15,619.99
4,460.85
6,365.25
5,270.00
49,468.75
11,956.19
131,500.00

119,000.00
3,103.20
23,622.00
1,594.69
15,619.99
3,943.65
5,627.25
5,270.00
49,468.75
10,824.95
119,000.00 (11,100.00)

165,800.00
55,575.00
19,810.00
6,290.00
56,535.71
27,642.14
165,800.00

120,400.00
15,350.40
1,968.75
18,256.66
4,568.60
6,519.00
6,290.00
56,535.71
10,948.91
120,400.00

137,300.00
30,708.60
1,968.75
18,256.66
4,568.60
6,519.00
6,290.00
56,535.71
12,484.73
137,300.00

136,700.00
13,584.00
17,913.35
1,968.75
18,256.66
4,008.30
5,719.50
6,290.00
56,535.71
12,427.63
136,700.00

144,000.00
14,904.00
24,310.98
1,968.75
18,256.66
4,008.30
5,719.50
5,270.00
56,535.71
13,097.39
144,000.00

133,000.00
4,310.00
24,803.10
1,968.75
18,256.66
4,051.40
5,781.00
5,270.00
56,535.71
12,097.66
133,000.00

2,590.00

44,156.25
45,000.00
150,000.00
383,200.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
104,000.00
62,400.00
117,945.63
1,297,401.88
2,590.00

2,820.00

63,585.00
67,500.00
150,000.00
383,200.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
124,800.00
104,000.00
128,378.50
1,412,163.50
2,820.00

330.00
aran pipa didekat galian.

191,600.00
100,000.00
50,000.00
33,300.00
18,745.00
393,645.00
330.00

363.00
363.00
396.00
396.00
462.00
462.00
561.00
561.00
693.00
693.00
858.00
858.00
1,023.00
1,023.00

750.00

100,000.00
38,300.00
75,000.00
37,500.00
5,067.00
12,540.00
268,407.00
750.00

787.50
787.50
937.50
937.50
1,312.50
1,312.50
1,500.00
1,500.00
1,800.00
1,800.00
2,062.50
2,062.50
2,250.00
2,250.00

26,900.00
7,576.80
708.75
8,924.67
2,542.90
3,628.50
330.00
750.00
2,446.16
26,900.00 26,800.00

29,000.00
7,847.40
831.80
10,170.73
2,645.26
3,774.56
363.00
787.50
2,642.02
29,000.00

34,300.00
10,012.20
964.69
11,674.08
2,973.90
4,243.50
396.00
937.50
3,120.19
34,300.00

40,300.00
10,553.40
1,107.42
15,492.71
3,196.94
4,561.76
462.00
1,312.50
3,668.67
40,300.00

41,000.00
10,661.64
1,167.27
15,492.71
3,273.66
4,671.23
561.00
1,500.00
3,732.75
41,000.00

44,800.00
10,824.00
1,260.00
18,028.27
3,361.80
4,797.00
693.00
1,800.00
4,076.41
44,800.00

54,500.00
13,530.00
1,968.75
22,272.14
3,652.73
5,212.13
858.00
2,062.50
4,955.62
54,500.00

57,000.00
14,071.20
2,129.40
23,649.29
3,737.63
5,333.28
858.00
2,062.50
5,184.13
57,000.00

62,100.00
16,531.20
2,835.00
23,857.31
4,137.60
5,904.00
1,023.00
2,250.00
5,653.81
62,100.00

35,700.00
10,714.41
964.69
12,234.15
2,262.75
3,228.75
330.00
750.00
5,300.00
35,700.00

37,900.00
11,083.88
964.69
12,957.14
2,499.80
3,567.00
363.00
787.50
5,700.00
37,900.00

44,800.00
13,300.65
1,260.00
16,052.77
2,650.65
3,782.25
396.00
937.50
6,500.00
44,800.00

52,000.00
14,778.50
1,422.42
20,380.55
2,709.91
3,866.81
462.00
1,312.50
7,100.00
52,000.00 (13,800.00)
53,000.00
15,074.07
1,456.09
20,472.30
2,815.29
4,017.18
462.00
1,312.50
7,400.00
53,000.00

59,400.00
16,256.35
1,968.75
23,221.60
3,060.10
4,366.50
693.00
1,800.00
8,100.00
59,400.00

72,700.00
17,734.20
2,212.09
33,427.52
3,030.79
4,324.68
858.00
2,062.50
9,100.00
72,700.00 (20,700.00)

76,200.00
18,473.13
2,382.19
33,779.75
3,555.75
5,073.75
858.00
2,062.50
10,100.00
76,200.00 55,000.00

85,700.00
19,212.05
2,835.00
41,469.54
4,008.30
5,719.50
330.00
750.00
11,400.00
85,700.00 60,900.00

ok 34,000.00
14,665.33
492.19
6,164.35
2,542.90
3,628.50
330.00
750.00
5,500.00
34,000.00

36,300.00
15,009.81
492.19
7,250.84
2,661.43
3,797.63
363.00
787.50
6,000.00
36,300.00

42,300.00
17,913.35
708.75
8,364.61
3,017.00
4,305.00
396.00
937.50
6,700.00
42,300.00

48,300.00
19,685.00
964.69
10,673.97
3,210.95
4,581.75
462.00
1,312.50
7,500.00
48,300.00

51,000.00
21,653.50
708.75
10,740.16
3,348.87
4,778.55
561.00
1,500.00
7,800.00
51,000.00

58,200.00
21,968.46
1,594.69
15,619.99
3,469.55
4,950.75
693.00
1,800.00
8,200.00
58,200.00

69,200.00
27,992.07
1,968.75
18,256.66
4,051.40
5,781.00
858.00
2,062.50
8,250.00
69,200.00

28,740.10
2,048.29
19,285.15
4,222.94
6,025.77
858.00
2,062.50
16,759.33
80,000.00

88,900.00
31,692.85
2,835.00
23,857.31
4,137.60
5,904.00
1,023.00
2,250.00
17,207.94
88,900.00

sisten Perencanaan
engembangan Sarana dan
na Permukiman Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

19,685.00
964.69
10,673.97
3,210.95
4,581.75
170.00
23,000.00
40,000.00
102,200.00

21,653.50
708.75
10,740.16
3,348.87
4,778.55
170.00
24,000.00
57,500.00
122,800.00 ok

an Prasarana Permukiman
36,800.00
2,586.00
15,748.00
708.75
8,364.61
3,017.00
4,305.00
396.00
937.50
3,347.69
36,800.00

40,600.00
2,586.00
15,748.00
964.69
10,673.97
3,210.95
4,581.75
462.00
1,312.50
3,695.39
40,600.00

53,800.00
4,310.00
19,685.00
1,035.00
13,092.43
3,608.09
5,148.43
561.00
1,500.00
4,893.99
53,800.00

63,600.00
4,310.00
23,622.00
1,174.22
15,619.99
4,403.90
6,283.98
693.00
1,800.00
5,790.71
63,600.00

69,300.00
4,310.00
25,984.20
1,344.38
18,256.66
4,217.64
6,018.21
858.00
2,062.50
6,305.16
69,300.00

78,300.00
5,172.00
28,346.40
1,935.00
23,857.31
3,571.14
5,095.71
1,023.00
2,250.00
7,125.06
78,300.00

63,000.00
15,848.00
16,535.40
2,452.50
13,092.43
3,004.69
4,287.43
561.00
1,500.00
5,728.14
63,000.00

66,900.00
16,980.00
16,535.40
2,749.22
15,619.99
2,679.90
3,823.98
693.00
1,800.00
6,088.15
66,900.00

83,500.00
18,112.00
23,031.45
1,856.25
18,256.66
4,864.14
6,940.71
858.00
2,062.50
7,598.17
83,500.00

64,900.00
17,388.00
14,468.48
1,074.38
13,092.43
4,513.19
6,439.93
561.00
1,500.00
5,903.74
64,900.00

72,300.00
17,388.00
16,535.40
1,074.38
15,619.99
4,513.19
6,439.93
693.00
1,800.00
8,328.30
72,300.00

83,200.00
19,872.00
23,031.45
1,331.72
18,256.66
4,231.50
6,037.98
858.00
2,062.50
7,568.18
83,200.00

1,640.00

1,766.25
1,766.25
100,000.00
191,600.00
37,500.00
3,750.00
50,000.00
91,600.00
100,000.00
66,600.00
62,400.00
41,600.00
74,858.25
823,440.75
1,640.00

1,650.00

3,974.06
3,974.06
100,000.00
191,600.00
37,500.00
3,750.00
50,000.00
91,600.00
100,000.00
66,600.00
62,400.00
41,600.00
75,299.81
828,297.94
1,650.00

2,020.00

7,065.00
7,065.00
150,000.00
239,500.00
56,250.00
5,625.00
50,000.00
91,600.00
100,000.00
66,600.00
83,200.00
62,400.00
91,930.50
1,011,235.50
2,020.00

2,100.00

15,896.25
15,896.25
150,000.00
239,500.00
56,250.00
5,625.00
50,000.00
91,600.00
100,000.00
66,600.00
93,600.00
72,800.00
95,776.75
1,053,544.25
2,100.00

2,410.00

28,260.00
28,260.00
175,000.00
287,400.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
104,000.00
83,200.00
109,682.00
1,206,502.00
2,410.00

2,660.00

44,156.25
44,156.25
150,000.00
383,200.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
114,400.00
83,200.00
120,981.25
1,330,793.75
2,660.00

2,790.00
63,585.00
63,585.00
150,000.00
383,200.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
124,800.00
93,600.00
126,947.00
1,396,417.00
2,790.00

3,210.00

113,040.00
113,040.00
150,000.00
383,200.00
75,000.00
7,500.00
50,000.00
91,600.00
100,000.00
66,600.00
187,200.00
124,800.00
146,198.00
1,608,178.00
3,210.00
ANALISA PEKERJAAN
No Uraian Pekerjaan Harga Satuan Jumlah

F PEKERJAAN PEMASANGAN PIPA BAJA

76 1 kg Pengangkutan pipa baja ke lokasi galian.


3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian.
2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km
4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp. 200,000.00
8.000 oh Pekerja 25,000.00 = Rp. 200,000.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00
1.000 ls Alat bantu = Rp. 48,330.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 531,600.00
Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp. 170.00

8 btg Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda.


15.000 kg Kawat Las Listrik 11,100.00 = Rp. 166,500.00
6.000 jam Welding Mechine 500A 16,700.00 = Rp. 100,200.00
1.000 unit Bahan cairan spay uji las (2 tube) 149,900.00 = Rp. 149,900.00
1.200 kg Coltar primer anti karat 12,900.00 = Rp. 15,480.00
96.00 bh Baut baja , Mur , Ring 4,000.00 = Rp. 384,000.00
8.00 bh Packing Loose Flange 7,500.00 = Rp. 60,000.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
6.000 oh Operator semi terampil 45,800.00 = Rp. 274,800.00
2.000 oh Tukang las 50,000.00 = Rp. 100,000.00
0.020 oh Mandor 37,500.00 = Rp. 750.00
1.000 ls Alat bantu = Rp. 143,913.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,583,000.00
1 Meter Penyambungan pipa GI dengan flange = Rp. 32,900.00

77 1 M' Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) = Rp. 49,468.75
78 1 M' Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg ) = Rp. 56,535.71

79 1 M' Pemasangan Pipa GI ND. 250 mm, diatas tumpuan


31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 5,473.88
Jumlah ( Dibulatkan dalam ratusan) = Rp. 60,200.00

80 1 M' Pemasangan Pipa GI ND. 300 mm, diatas tumpuan


36.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,120.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 6,265.57
Jumlah ( Dibulatkan dalam ratusan) = Rp. 68,900.00

81 1 M' Pemasangan GI Dia. 250 mm, Galian tanah biasa.


0.720 m3 Galian tanah biasa 19,680.00 = Rp. 14,169.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 9,694.91
Jumlah ( Dibulatkan dalam ratusan) = Rp. 106,600.00

82 1 M' Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu.


0.720 m3 Galian tanah berbatu 39,370.00 = Rp. 28,346.40
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 13,001.73
Jumlah ( Dibulatkan dalam ratusan) = Rp. 124,100.00
No Uraian Pekerjaan Harga Satuan Jumlah
83 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III.
0.720 m2 Bongkaran perkerasan jalan kelas III (40 cm) 22,640.00 = Rp. 16,300.80
0.480 m3 Galian tanah berbatu 39,370.00 = Rp. 18,897.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 15,337.13
Jumlah ( Dibulatkan dalam ratusan) = Rp. 133,300.00

84 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I.


0.720 m2 Bongkaran perkerasan jalan kelas I (15 cm) 24,840.00 = Rp. 17,884.80
0.480 m3 Galian tanah berbatu 39,370.00 = Rp. 18,897.60
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.518 m3 Urugan tanah kembali 8,620.00 = Rp. 4,460.85
0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,365.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 11,956.19
Jumlah ( Dibulatkan dalam ratusan) = Rp. 131,500.00

85 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block.


0.720 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 3,103.20
0.600 m3 Galian tanah berbatu 39,370.00 = Rp. 23,622.00
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.458 m3 Urugan kembali 8,620.00 = Rp. 3,943.65
0.458 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,627.25
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 = Rp. 49,468.75
1.000 ls Alat bantu = Rp. 10,824.95
Jumlah ( Dibulatkan dalam ratusan) = Rp. 119,000.00

86 1 M' Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu.


0.780 m3 Galian dasar sungai berbatu 71,250.00 = Rp. 55,575.00
0.70 m3 Pasangan batu kosong (bahan setempat) 28,300.00 = Rp. 19,810.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 27,642.14
Jumlah ( Dibulatkan dalam ratusan) = Rp. 165,800.00

87 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa.


0.780 m3 Galian tanah biasa 19,680.00 = Rp. 15,350.40
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.530 m3 Urugan kembali 8,620.00 = Rp. 4,568.60
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,519.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 10,948.91
Jumlah ( Dibulatkan dalam ratusan) = Rp. 120,400.00

88 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu.


0.780 m3 Galian tanah berbatu 39,370.00 = Rp. 30,708.60
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.530 m3 Urugan kembali 8,620.00 = Rp. 4,568.60
0.530 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,519.00
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 12,484.73
Jumlah ( Dibulatkan dalam ratusan) = Rp. 137,300.00
No Uraian Pekerjaan Harga Satuan Jumlah
89 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III.
0.600 m2 Bongkaran jalan Kelas III 22,640.00 = Rp. 13,584.00
0.455 m3 Galian tanah berbatu 39,370.00 = Rp. 17,913.35
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.465 m3 Urugan kembali 8,620.00 = Rp. 4,008.30
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,719.50
37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 6,290.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 12,427.63
Jumlah ( Dibulatkan dalam ratusan) = Rp. 136,700.00

90 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I.


0.600 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 14,904.00
0.618 m3 Galian tanah berbatu 39,370.00 = Rp. 24,310.98
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.465 m3 Urugan kembali 8,620.00 = Rp. 4,008.30
0.465 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,719.50
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 13,097.39
Jumlah ( Dibulatkan dalam ratusan) = Rp. 144,000.00

91 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block.


1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 4,310.00
0.630 m3 Galian tanah berbatu 39,370.00 = Rp. 24,803.10
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,781.00
31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 5,270.00
1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 = Rp. 56,535.71
1.000 ls Alat bantu = Rp. 12,097.66
Jumlah ( Dibulatkan dalam ratusan) = Rp. 133,000.00

92 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 44,156.25
3.000 kg Kaporit 15,000.00 = Rp. 45,000.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 104,000.00
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 62,400.00
1.000 ls Alat bantu = Rp. 117,945.63
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,297,401.88
Biaya Pengetesan per 1m panjang = Rp. 2,590.00

93 1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm.
500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 63,585.00
4.500 kg Kaporit 15,000.00 = Rp. 67,500.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 124,800.00
10.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 104,000.00
1.000 ls Alat bantu = Rp. 128,378.50
Jumlah ( Dibulatkan dalam ratusan) = Rp. 1,412,163.50
Biaya Pengetesan per 1m panjang = Rp. 2,820.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah
G PEKERJAAN PEMASANGAN PIPA PVC

94 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm


200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian.
1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m)
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00
1.000 ls Alat bantu = Rp. 18,745.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 393,645.00
Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp. 330.00

95 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm


110 % Analisa F.48 330.00 = Rp. 363.00
96 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm
120 % Analisa F.48 330.00 = Rp. 396.00
97 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm
140 % Analisa F.48 330.00 = Rp. 462.00
98 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm
170 % Analisa F.48 330.00 = Rp. 561.00
99 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm
210 % Analisa F.48 330.00 = Rp. 693.00
100 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm
260 % Analisa F.48 330.00 = Rp. 858.00
101 1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm
310 % Analisa F.48 330.00 = Rp. 1,023.00

102 1 M' Penyambungan pipa PVC Dia. 50 mm didalam galian


360 m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung.
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
1.000 oh Tukang batu semi terampil 38,300.00 = Rp. 38,300.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
1.000 oh Mandor 37,500.00 = Rp. 37,500.00
0.100 An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp. 5,067.00
1.000 ls Alat bantu = Rp. 12,540.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 268,407.00
Biaya Penyambungan per 1 m panjang Pipa. = Rp. 750.00

103 1 M' Penyambungan pipa PVC Dia. 75 mm didalam galian


105 % Analisa F.50 750.00 = Rp. 787.50
104 1 M' Penyambungan pipa PVC Dia. 100 mm didalam galian
125 % Analisa F.50 750.00 = Rp. 937.50
105 1 M' Penyambungan pipa PVC Dia. 150 mm didalam galian
175 % Analisa F.50 750.00 = Rp. 1,312.50
106 1 M' Penyambungan pipa PVC Dia. 200 mm didalam galian
200 % Analisa F.50 750.00 = Rp. 1,500.00
107 1 M' Penyambungan pipa PVC Dia. 250 mm didalam galian
240 % Analisa F.50 750.00 = Rp. 1,800.00
108 1 M' Penyambungan pipa PVC Dia. 300 mm didalam galian
275 % Analisa F.50 750.00 = Rp. 2,062.50
109 1 M' Penyambungan pipa PVC Dia. 400 mm didalam galian
300 % Analisa F.50 750.00 = Rp. 2,250.00
No Uraian Pekerjaan Harga Satuan Jumlah
110 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa.
0.385 m3 Galian tanah biasa 19,680.00 = Rp. 7,576.80
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.088 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,924.67
0.295 m3 Urugan kembali 8,620.00 = Rp. 2,542.90
0.295 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,628.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.00 ls Alat bantu = Rp. 2,446.16
Jumlah ( Dibulatkan dalam ratusan) = Rp. 26,900.00

111 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa.
0.399 m3 Galian tanah biasa 19,680.00 = Rp. 7,847.40
0.106 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 831.80
0.100 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,170.73
0.307 m3 Urugan kembali 8,620.00 = Rp. 2,645.26
0.307 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,774.56
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 2,642.02
Jumlah ( Dibulatkan dalam ratusan) = Rp. 29,000.00

112 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa.
0.509 m3 Galian tanah biasa 19,680.00 = Rp. 10,012.20
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.115 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 11,674.08
0.345 m3 Urugan kembali 8,620.00 = Rp. 2,973.90
0.345 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,243.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 3,120.19
Jumlah ( Dibulatkan dalam ratusan) = Rp. 34,300.00

113 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa.
0.536 m3 Galian tanah biasa 19,680.00 = Rp. 10,553.40
0.141 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,107.42
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,492.71
0.371 m3 Urugan kembali 8,620.00 = Rp. 3,196.94
0.371 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,561.76
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 3,668.67
Jumlah ( Dibulatkan dalam ratusan) = Rp. 40,300.00
No Uraian Pekerjaan Harga Satuan Jumlah
114 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa.
0.542 m3 Galian tanah biasa 19,680.00 = Rp. 10,661.64
0.148 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,167.27
0.152 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,492.71
0.380 m3 Urugan kembali 8,620.00 = Rp. 3,273.66
0.380 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,671.23
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 3,732.75
Jumlah ( Dibulatkan dalam ratusan) = Rp. 41,000.00

115 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa.
0.550 m3 Galian tanah biasa 19,680.00 = Rp. 10,824.00
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,260.00
0.177 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,028.27
0.390 m3 Urugan kembali 8,620.00 = Rp. 3,361.80
0.390 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,797.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 4,076.41
Jumlah ( Dibulatkan dalam ratusan) = Rp. 44,800.00

116 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa.
0.688 m3 Galian tanah biasa 19,680.00 = Rp. 13,530.00
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.219 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 22,272.14
0.424 m3 Urugan kembali 8,620.00 = Rp. 3,652.73
0.424 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,212.13
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 4,955.62
Jumlah ( Dibulatkan dalam ratusan) = Rp. 54,500.00

117 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa.
0.715 m3 Galian tanah biasa 19,680.00 = Rp. 14,071.20
0.270 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,129.40
0.232 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,649.29
0.434 m3 Urugan kembali 8,620.00 = Rp. 3,737.63
0.434 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,333.28
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 5,184.13
Jumlah ( Dibulatkan dalam ratusan) = Rp. 57,000.00

118 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa.
0.840 m3 Galian tanah biasa 19,680.00 = Rp. 16,531.20
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.480 m3 Urugan kembali 8,620.00 = Rp. 4,137.60
0.480 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,904.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 5,653.81
Jumlah ( Dibulatkan dalam ratusan) = Rp. 62,100.00
No Uraian Pekerjaan Harga Satuan Jumlah
119 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras
0.399 m3 Galian tanah keras 26,870.00 = Rp. 10,714.41
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.120 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 12,234.15
0.263 m3 Urugan tanah kembali 8,620.00 = Rp. 2,262.75
0.263 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,228.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.00 ls Alat bantu = Rp. 5,300.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 35,700.00

120 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras
0.413 m3 Galian tanah keras 26,870.00 = Rp. 11,083.88
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.127 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 12,957.14
0.290 m3 Urugan tanah kembali 8,620.00 = Rp. 2,499.80
0.290 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,567.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 5,700.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 37,900.00
No Uraian Pekerjaan Harga Satuan Jumlah
121 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras.
0.495 m3 Galian tanah keras 26,870.00 = Rp. 13,300.65
0.160 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,260.00
0.158 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 16,052.77
0.308 m3 Urugan tanah kembali 8,620.00 = Rp. 2,650.65
0.308 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,782.25
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 6,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 44,800.00

122 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras.
0.550 m3 Galian tanah keras 26,870.00 = Rp. 14,778.50
0.181 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,422.42
0.200 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 20,380.55
0.314 m3 Urugan tanah kembali 8,620.00 = Rp. 2,709.91
0.314 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,866.81
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 7,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 52,000.00

123 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras.
0.561 m3 Galian tanah keras 26,870.00 = Rp. 15,074.07
0.185 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,456.09
0.201 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 20,472.30
0.327 m3 Urugan tanah kembali 8,620.00 = Rp. 2,815.29
0.327 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,017.18
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 7,400.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 53,000.00

124 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras.
0.605 m3 Galian tanah keras 26,870.00 = Rp. 16,256.35
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.228 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,221.60
0.355 m3 Urugan tanah kembali 8,620.00 = Rp. 3,060.10
0.355 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,366.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 59,400.00

125 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras.
0.660 m3 Galian tanah keras 26,870.00 = Rp. 17,734.20
0.281 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,212.09
0.328 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 33,427.52
0.352 m3 Urugan tanah kembali 8,620.00 = Rp. 3,030.79
0.352 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,324.68
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 9,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 72,700.00

126 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras.
0.688 m3 Galian tanah keras 26,870.00 = Rp. 18,473.13
0.303 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,382.19
0.332 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 33,779.75
0.413 m3 Urugan tanah kembali 8,620.00 = Rp. 3,555.75
0.413 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,073.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 10,100.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 76,200.00

127 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras
0.715 m3 Galian tanah keras 26,870.00 = Rp. 19,212.05
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.407 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 41,469.54
0.465 m3 Urugan tanah kembali 8,620.00 = Rp. 4,008.30
No Uraian Pekerjaan Harga Satuan Jumlah
0.465 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,719.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.000 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.000 ls Alat bantu = Rp. 11,400.00
Jumlah = Rp. 85,700.00
No Uraian Pekerjaan Harga Satuan Jumlah
128 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu ok
0.373 m3 Galian tanah berbatu 39,370.00 = Rp. 14,665.33
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 492.19
0.061 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 6,164.35
0.295 m3 Urugan tanah kembali 8,620.00 = Rp. 2,542.90
0.295 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,628.50
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 = Rp. 330.00
1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 = Rp. 750.00
1.00 ls Alat bantu = Rp. 5,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 34,000.00

129 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu
0.381 m3 Galian tanah berbatu 39,370.00 = Rp. 15,009.81
0.063 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 492.19
0.071 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 7,250.84
0.309 m3 Urugan tanah kembali 8,620.00 = Rp. 2,661.43
0.309 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 3,797.63
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 363.00 = Rp. 363.00
1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 787.50 = Rp. 787.50
1.00 ls Alat bantu = Rp. 6,000.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 36,300.00

130 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu.
0.455 m3 Galian tanah berbatu 39,370.00 = Rp. 17,913.35
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,364.61
0.350 m3 Urugan tanah kembali 8,620.00 = Rp. 3,017.00
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,305.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 6,700.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 42,300.00

131 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu.
0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 7,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 48,300.00

132 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu.
0.550 m3 Galian tanah berbatu 39,370.00 = Rp. 21,653.50
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,740.16
0.389 m3 Urugan tanah kembali 8,620.00 = Rp. 3,348.87
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,778.55
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 7,800.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 51,000.00
No Uraian Pekerjaan Harga Satuan Jumlah
133 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu.
0.558 m3 Galian tanah berbatu 39,370.00 = Rp. 21,968.46
0.203 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,594.69
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.403 m3 Urugan tanah kembali 8,620.00 = Rp. 3,469.55
0.403 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,950.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,200.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 58,200.00

134 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu.
0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 27,992.07
0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,968.75
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 4,051.40
0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,781.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 8,250.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 69,200.00

135 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu.
0.730 m3 Galian tanah berbatu 39,370.00 = Rp. 28,740.10
0.260 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,048.29
0.189 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 19,285.15
0.490 m3 Urugan tanah kembali 8,620.00 = Rp. 4,222.94
0.490 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 6,025.77
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 16,759.33
Jumlah ( Dibulatkan dalam ratusan) = Rp. 80,000.00

135 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu
0.805 m3 Galian tanah berbatu 39,370.00 = Rp. 31,692.85
0.360 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,835.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.480 m3 Urugan tanah kembali 8,620.00 = Rp. 4,137.60
0.480 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 5,904.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 17,207.94
Jumlah ( Dibulatkan dalam ratusan) = Rp. 88,900.00

Assisten Perencanaan
Proyek Pengembangan Sarana dan
Prasarana Permukiman Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

1 M' Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu.


0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 170.00
1.00 m1 Penyambungan dan pengelasan pipa. 23,000.00 = Rp. 23,000.00
1.00 ls Alat bantu = Rp. 40,000.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 102,200.00

1 M' Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu.


No Uraian Pekerjaan Harga Satuan Jumlah
0.550 m3 Galian tanah berbatu 39,370.00 = Rp. 21,653.50
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,740.16
0.389 m3 Urugan tanah kembali 8,620.00 = Rp. 3,348.87
0.389 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,778.55
1.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 = Rp. 170.00
1.00 m1 Penyambungan dan pengelasan pipa. 24,000.00 = Rp. 24,000.00
1.00 ls Alat bantu = Rp. 57,500.00
Jumlah ( Dibulatkan dalam ratusan) = Rp. 122,800.00

Assisten Perencanaan
Proyek Pengembangan Sarana dan Prasarana Permukiman
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568
No Uraian Pekerjaan Harga Satuan Jumlah
136 1 M' Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar.
0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 2,586.00
0.400 m3 Galian tanah berbatu 39,370.00 = Rp. 15,748.00
0.090 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 708.75
0.082 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 8,364.61
0.350 m3 Urugan tanah kembali 8,620.00 = Rp. 3,017.00
0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,305.00
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 = Rp. 396.00
1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 = Rp. 937.50
1.00 ls Alat bantu = Rp. 3,347.69
Jumlah ( Dibulatkan dalam ratusan) = Rp. 36,800.00

137 1 M' Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar.
0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 2,586.00
0.400 m3 Galian tanah berbatu 39,370.00 = Rp. 15,748.00
0.123 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 964.69
0.105 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 10,673.97
0.373 m3 Urugan tanah kembali 8,620.00 = Rp. 3,210.95
0.373 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 4,581.75
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 462.00 = Rp. 462.00
1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1,312.50 = Rp. 1,312.50
1.00 ls Alat bantu = Rp. 3,695.39
Jumlah ( Dibulatkan dalam ratusan) = Rp. 40,600.00

138 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar.
1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 4,310.00
0.500 m3 Galian tanah berbatu 39,370.00 = Rp. 19,685.00
0.131 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,035.00
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.419 m3 Urugan kembali 8,620.00 = Rp. 3,608.09
0.419 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,148.43
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 4,893.99
Jumlah ( Dibulatkan dalam ratusan) = Rp. 53,800.00

139 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar.
1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 = Rp. 4,310.00
0.600 m3 Galian tanah berbatu 39,370.00 = Rp. 23,622.00
0.149 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,174.22
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.511 m3 Urugan kembali 8,620.00 = Rp. 4,403.90
0.511 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,283.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 5,790.71
Jumlah ( Dibulatkan dalam ratusan) = Rp. 63,600.00

140 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar.
1.000 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 4,310.00
0.660 m3 Galian tanah berbatu 39,370.00 = Rp. 25,984.20
0.171 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,344.38
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.489 m3 Urugan kembali 8,620.00 = Rp. 4,217.64
0.489 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,018.21
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 6,305.16
Jumlah ( Dibulatkan dalam ratusan) = Rp. 69,300.00

141 1 M' Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar.
1.200 m2 Bongkaran Paving Block tebal 8 cm 4,310.00 = Rp. 5,172.00
0.720 m3 Galian tanah berbatu 39,370.00 = Rp. 28,346.40
0.246 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,935.00
0.234 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 23,857.31
0.414 m3 Urugan kembali 8,620.00 = Rp. 3,571.14
0.414 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 5,095.71
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 = Rp. 1,023.00
1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 = Rp. 2,250.00
1.000 ls Alat bantu = Rp. 7,125.06
Jumlah ( Dibulatkan dalam ratusan) = Rp. 78,300.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah
142 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III.
0.700 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. 15,848.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.311 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,452.50
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.349 m3 Urugan kembali 8,620.00 = Rp. 3,004.69
0.349 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 4,287.43
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 5,728.14
Jumlah ( Dibulatkan dalam ratusan) = Rp. 63,000.00

143 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III.
0.750 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. 16,980.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.349 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 2,749.22
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.311 m3 Urugan kembali 8,620.00 = Rp. 2,679.90
0.311 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 3,823.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 6,088.15
Jumlah ( Dibulatkan dalam ratusan) = Rp. 66,900.00

144 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III.
0.800 m2 Bongkaran jalan Kelas III 22,640.00 = Rp. 18,112.00
0.585 m3 Galian tanah berbatu 39,370.00 = Rp. 23,031.45
0.236 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,856.25
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.564 m3 Urugan kembali 8,620.00 = Rp. 4,864.14
0.564 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,940.71
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 7,598.17
Jumlah ( Dibulatkan dalam ratusan) = Rp. 83,500.00

145 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 17,388.00
0.368 m3 Galian tanah berbatu 39,370.00 = Rp. 14,468.48
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,074.38
0.129 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 13,092.43
0.524 m3 Urugan kembali 8,620.00 = Rp. 4,513.19
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,439.93
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. 561.00
1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. 1,500.00
1.00 ls Alat bantu = Rp. 5,903.74
Jumlah ( Dibulatkan dalam ratusan) = Rp. 64,900.00

146 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I.
0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 17,388.00
0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 16,535.40
0.136 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,074.38
0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 15,619.99
0.524 m3 Urugan kembali 8,620.00 = Rp. 4,513.19
0.524 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,439.93
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 693.00
1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1,800.00
1.00 ls Alat bantu = Rp. 8,328.30
Jumlah ( Dibulatkan dalam ratusan) = Rp. 72,300.00

147 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I.
0.800 m2 Bongkaran jalan Kelas I tebal 15 cm 24,840.00 = Rp. 19,872.00
0.585 m3 Galian tanah berbatu 39,370.00 = Rp. 23,031.45
0.169 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 1,331.72
0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 18,256.66
0.491 m3 Urugan kembali 8,620.00 = Rp. 4,231.50
0.491 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 6,037.98
1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 858.00
1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 2,062.50
1.000 ls Alat bantu = Rp. 7,568.18
Jumlah ( Dibulatkan dalam ratusan) = Rp. 83,200.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah
148 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm.
2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 1,766.25
0.118 kg Kaporit 15,000.00 = Rp. 1,766.25
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
0.100 oh Mandor 37,500.00 = Rp. 3,750.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 62,400.00
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 41,600.00
1.000 ls Alat bantu = Rp. 74,858.25
Jumlah = Rp. 823,440.75
Biaya Pengetesan per 1m panjang = Rp. 1,640.00

149 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm.
6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 3,974.06
0.265 kg Kaporit 15,000.00 = Rp. 3,974.06
4.000 oh Pekerja 25,000.00 = Rp. 100,000.00
4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00
1.000 oh Tukang pipa 37,500.00 = Rp. 37,500.00
0.100 oh Mandor 37,500.00 = Rp. 3,750.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
6.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 62,400.00
4.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 41,600.00
1.000 ls Alat bantu = Rp. 75,299.81
Jumlah = Rp. 828,297.94
Biaya Pengetesan per 1m panjang = Rp. 1,650.00

150 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm.
11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 7,065.00
0.471 kg Kaporit 15,000.00 = Rp. 7,065.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
5.000 jam Pickup Truck 47,900.00 = Rp. 239,500.00
1.500 oh Tukang pipa 37,500.00 = Rp. 56,250.00
0.150 oh Mandor 37,500.00 = Rp. 5,625.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
8.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 83,200.00
6.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 62,400.00
1.000 ls Alat bantu = Rp. 91,930.50
Jumlah = Rp. 1,011,235.50
Biaya Pengetesan per 1m panjang = Rp. 2,020.00

151 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm.
26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 15,896.25
1.060 kg Kaporit 15,000.00 = Rp. 15,896.25
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
5.000 jam Pickup Truck 47,900.00 = Rp. 239,500.00
1.500 oh Tukang pipa 37,500.00 = Rp. 56,250.00
0.150 oh Mandor 37,500.00 = Rp. 5,625.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
9.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 93,600.00
7.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 72,800.00
1.000 ls Alat bantu = Rp. 95,776.75
Jumlah = Rp. 1,053,544.25
Biaya Pengetesan per 1m panjang = Rp. 2,100.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan Jumlah
152 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 28,260.00
1.884 kg Kaporit 15,000.00 = Rp. 28,260.00
7.000 oh Pekerja 25,000.00 = Rp. 175,000.00
6.000 jam Pickup Truck 47,900.00 = Rp. 287,400.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
10.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 104,000.00
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 83,200.00
1.000 ls Alat bantu = Rp. 109,682.00
Jumlah = Rp. 1,206,502.00
Biaya Pengetesan per 1m panjang = Rp. 2,410.00

153 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm.
73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 44,156.25
2.944 kg Kaporit 15,000.00 = Rp. 44,156.25
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
11.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 114,400.00
8.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 83,200.00
1.000 ls Alat bantu = Rp. 120,981.25
Jumlah = Rp. 1,330,793.75
Biaya Pengetesan per 1m panjang = Rp. 2,660.00

154 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 63,585.00
4.239 kg Kaporit 15,000.00 = Rp. 63,585.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
12.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 124,800.00
9.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 93,600.00
1.000 ls Alat bantu = Rp. 126,947.00
Jumlah = Rp. 1,396,417.00
Biaya Pengetesan per 1m panjang = Rp. 2,790.00

155 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm.
188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 = Rp. 113,040.00
7.536 kg Kaporit 15,000.00 = Rp. 113,040.00
6.000 oh Pekerja 25,000.00 = Rp. 150,000.00
8.000 jam Pickup Truck 47,900.00 = Rp. 383,200.00
2.000 oh Tukang pipa 37,500.00 = Rp. 75,000.00
0.200 oh Mandor 37,500.00 = Rp. 7,500.00
1.000 oh Sopir 50,000.00 = Rp. 50,000.00
2.000 oh Operator semi terampil 45,800.00 = Rp. 91,600.00
2.000 oh Pembantu operator 50,000.00 = Rp. 100,000.00
2.000 oh Pembantu sopir 33,300.00 = Rp. 66,600.00
18.000 jam Water Pump (Dia. 5 cm) 10,400.00 = Rp. 187,200.00
12.000 jam Pressure Pump 20 Bar 10,400.00 = Rp. 124,800.00
1.000 ls Alat bantu = Rp. 146,198.00
Jumlah = Rp. 1,608,178.00
Biaya Pengetesan per 1m panjang = Rp. 3,210.00
No Uraian Pekerjaan Harga Satuan Jumlah
No Uraian Pekerjaan Harga Satuan

H PEKERJAAN PERKERASAN JALAN


Pemadatan
156 1M2 Pemadatan tanah dasar menggunakan Stamper
0.100 jam Plate Vibrator Tamper 4,200.00
0.100 oh Operator semi terampil 45,800.00
0.010 oh Mandor 37,500.00
1.000 m2 Penyiraman
Jumlah

157 1M2 Pemadatan standart Bina Marga menggunakan alat berat


0.012 jam Tree Wheel Roller 51 HP 21,900.00
0.012 oh Operator terampil 50,000.00
0.001 oh Mandor 37,500.00
1.000 m2 Penyiraman
Jumlah

158 1 M2 Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2.


200.00 m2 Prime Coat dihampar manual :
129 kg Aspal 5,800.00
37 ltr Minyak tanah 1,700.00
6.00 oh Pekerja 25,000.00
0.20 oh Mandor 37,500.00
0.50 m3 Kayu bakar 82,500.00
5.00 ltr Minyak bakar 2,400.00
ah Alat bantu
Jumlah

Konstruksi Jalan
159 1 M2 Lapis Pondasi bawah Onderlaght, tebal 15 cm.
150.00 m2 Lapisan LPB dengan tebal 15 cm, dihampar manual.
29.70 m3 Kerikil sungai tidak disaring 75,000.00
1.00 oh Mandor 37,500.00
22.00 oh Pekerja 25,000.00
2.00 oh Operator semi terampil 45,800.00
2.00 oh Pembantu operator 50,000.00
6.00 jam Vibro Roller 600 Kg 15,600.00
1.000 ls Alat bantu
Jumlah
1 M2 Lapis Pondasi bawah steinslaght Kelas C, tebal 15 cm.

160 1 M2 Lapis Pondasi bawah onderlaght, tebal 30 cm.


150.00 m2 Lapisan LPB dengan tebal 15 cm, dihampar manual.
59.40 m3 Kerikil sungai tidak disaring 75,000.00
1.00 oh Mandor 37,500.00
22.00 oh Pekerja 25,000.00
2.00 oh Operator semi terampil 45,800.00
2.00 oh Pembantu operator 50,000.00
6.00 jam Tree Wheel Roller 51 HP 21,900.00
1.000 ls Alat bantu
Jumlah
1 M2 Lapis Pondasi bawah steinslaght Kelas C, tebal 30 cm.

161 1 M2 Lapis Pondasi Atas Steinslaght , tebal 7 cm.


150.00 m2 Lapisan LPA dengan tebal 10 cm, dihampar manual.
15.84 m3 Batu pecah 2 - 3 136,600.00
3.96 m3 Batu pecah 1 - 2 136,600.00
1.00 oh Mandor 37,500.00
20.00 oh Pekerja 25,000.00
2.00 oh Operator semi terampil 45,800.00
2.00 oh Pembantu operator 50,000.00
7.00 jam Vibro Roller 600 Kg 15,600.00
1.000 ls Alat bantu
Jumlah
1 M2 Lapis Pondasi Atas steinslaght Kelas A, tebal 7 cm.

162 1 M2 Lapis Perkerasan Macadam, tebal 5 cm.


180.00 m2 Lapisan Perkerasan Macadam tebal 5 cm, dihampar manual.
7.58 m3 Batu pecah 2 - 3 136,600.00
2.39 m3 Batu pecah 1 - 2 136,600.00
1.36 m3 Batu pecah 0,5 - 1 108,300.00
0.38 m3 Pasir beton 133,300.00
600 m2 Prime Coat (3 x tabur) 5,193.02
2.00 m3 Kayu bakar 82,500.00
5.00 ltr Minyak bakar 2,400.00
24.00 oh Pekerja 25,000.00
1.00 oh Mandor 37,500.00
1.00 oh Sopir 50,000.00
1.00 oh Operator terampil 50,000.00
1.00 oh Pembantu operator 50,000.00
6.00 jam Tree Wheel Roller 51 HP 21,900.00
5.00 jam Pickup Truck 47,900.00
1.00 ls Alat bantu
Jumlah
1 M2 Lapis Perkerasan Macadam, tebal 5 cm.

163 1 M2 Lapis PENETRASI , tebal 3 cm.


250.00 m2 Lapisan latasir tebal 3 cm padat, dihampar manual.
6.38 m3 Pasir beton 133,300.00
1.69 m3 Abu batu/Filler 139,900.00
563 kg Aspal 5,800.00
5.00 m3 Kayu bakar 82,500.00
10.00 ltr Minyak bakar 2,400.00
28.00 oh Pekerja 25,000.00
1.00 oh Mandor 37,500.00
1.00 oh Sopir 50,000.00
1.00 oh Operator terampil 50,000.00
1.00 oh Pembantu operator 50,000.00
6.00 jam Tree Wheel Roller 51 HP 21,900.00
4.00 jam Pickup Truck 47,900.00
1.00 ls Alat bantu
Jumlah
1 M2 Lapis LATASIR, tebal 3 cm.

Assisten Perencanaa
Proyek Pengembangan Sarana dan Pra
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

164 1 M2 Perbaikan Perkerasan jalan kelas III


1.00 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00
1.00 m2 Lapis Penetrasi Macadam tebal 5 cm 33,558.13

165 1 M2 Perbaikan Perkerasan jalan kelas I


1.00 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00
1.00 m2 Lapir LPA, steinslaght kelas A, Analisa 76 23,985.49
1.00 m2 LATASIR tebal 3 cm 24,101.38

166 1 M2 Pemasangan kembali Paving Block (30% rusak diganti baru)


0.30 m2 Paving Block natural 8 cm 65,800.00
0.05 m3 Pasir pasang 116,600.00
0.10 oh Pekerja 25,000.00
0.05 oh Tukang batu 38,300.00
0.00 oh Mandor 37,500.00
0.01 oh Operator terampil 50,000.00
1.00 ls Alat bantu
Jumlah

167 1 M2 Perbaikan paving blok, pemasangan pipa dia. 400 mm (1,0 m/m1)
168 1 M2 Perbaikan paving blok, pemasangan pipa dia. 300 mm (0.90 m/m1)
169 1 M2 Perbaikan paving blok, pemasangan pipa dia. 250 mm (0.80 m/m1)
170 1 M2 Perbaikan paving blok, pemasangan pipa dia. 200 mm (0.70 m/m1)

171 1 M2 Jalan inspeksi, beton rabat tebal 10 cm


1.20 m2 Pemadatan tanah dasar 5,643.75
0.12 m3 Pasir urug dipadatkan 101,830.00
0.11 m3 Beton K125 594,330.00
0.20 m3 Pekerja 25,000.00
0.05 oh Tukang batu 38,300.00
0.01 oh Mandor 37,500.00
0.01 oh Operator terampil 50,000.00
1.00 ls Alat bantu
Jumlah

172 1 M2 Perbaikan Perkerasan jalan kelas III, pemasangan pipa dia. 200 mm
0.60 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00
0.60 m2 Lapis Penetrasi Macadam tebal 5 cm 33,558.13

173 1 M2 Perbaikan Perkerasan jalan kelas I, pemasangan pipa dia. 200 mm


0.60 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00
0.60 m2 Lapir LPA, Sub Base kelas A, Analisa 76 23,985.49
0.60 m2 LATASIR tebal 3 cm 24,101.38

174 1 M2 Perbaikan Perkerasan jalan kelas I, pemasangan pipa dia. 250 mm


0.65 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00
0.65 m2 Lapir LPA, Sub Base kelas A, Analisa 76 23,985.49
0.65 m2 LATASIR tebal 3 cm 24,101.38

Assisten Perencanaa
Proyek Pengembangan Sarana dan Pra
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

1 M' Pekerjaan Saluran

0.210 m3 Galian tanah 19,680.00


0.210 m3 Buang tanah galian 7,875.00
0.190 m3 Pasangan batu kali 1:4 480,990.00
0.551 m2 Siaran 1:4 27,380.00
0.600 m2 Plesteran 1:4 27,200.00
1 ls Perapihan 500.00

Jumlah
Dibulatkan

No Uraian Pekerjaan Harga Satuan

1 M' Pekerjaan Jalan Penetrasi


Lebar Perkerasan 3.00 meter
3.00 meter Lapisan pondasi atas Stenslagh t =7 cm = Rp. 23,985.49
3.00 meter Lapisan resap pengikat ( Prime Coate ) = Rp. 5,193.02
3.00 meter Lapisan Penetrasi t=3 cm = Rp. 24,101.38
1.00 ls Perapihan = Rp. 1,000.00

Jumlah
Dibulatkan

No Uraian Pekerjaan Harga Satuan

1 M' Pekerjaan Jalan Penetrasi


Lebar Perkerasan 3.50 meter
3.50 meter Pecing Onderlagh 80 % = Rp. 30,549.96
3.50 meter Lapisan pondasi atas Stenslagh t =7 cm = Rp. 23,985.49
3.50 meter Lapisan resap pengikat ( Prime Coate ) = Rp. 5,193.02
3.50 meter Lapisan Penetrasi t=3 cm = Rp. 24,101.38
1.00 ls Perapihan = Rp. 3,300.00

Jumlah
Dibulatkan

No Uraian Pekerjaan Harga Satuan

1 M' Pekerjaan Jalan Penetrasi


Lebar Perkerasan 4.00 meter
4.00 meter Lapisan Pondasi Bawah Onderlagh 15 Cm = Rp. 20,970.00
4.00 meter Lapisan pondasi atas Stenslagh t =7 cm = Rp. 23,985.49
4.00 meter Lapisan resap pengikat ( Prime Coate ) = Rp. 5,193.02
4.00 meter Lapisan Penetrasi t=3 cm = Rp. 24,101.38
1.00 ls Perapihan = Rp. 6,800.00
Jumlah
Dibulatkan

1 M' Pekerjaan Saluran

0.210 m3 Galian tanah 19,680.00


0.210 m3 Buang tanah galian 7,875.00
0.190 m3 Pasangan batu kali 1:4 480,990.00
0.551 m2 Siaran 1:4 27,380.00
0.600 m2 Plesteran 1:4 27,200.00
1 ls Perapihan 5,225.00

Jumlah
Dibulatkan

Assisten Perencanaan
Proyek Pengembangan Sarana dan Prasarana Pe
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568
Jumlah

5,643.75
= Rp. 420.00
= Rp. 4,580.00
= Rp. 375.00
= Rp. 268.75
= Rp. 5,643.75

1,050.30
= Rp. 262.80
= Rp. 600.00
= Rp. 37.50
= Rp. 150.00
= Rp. 1,050.30

5,193.02

= Rp. 750,288.00
= Rp. 62,560.00
= Rp. 150,000.00
= Rp. 7,500.00
= Rp. 41,250.00
= Rp. 12,000.00
= Rp. 15,005.76
= Rp. 1,038,603.76
= Rp. 5,193.02

20,970.00

= Rp. 2,227,500.00
= Rp. 37,500.00
= Rp. 550,000.00
= Rp. 91,600.00
= Rp. 100,000.00
= Rp. 93,600.00
= Rp. 45,300.00
= Rp. 3,145,500.00
= Rp. 20,970.00

36,369.00

= Rp. 4,455,000.00
= Rp. 37,500.00
= Rp. 550,000.00
= Rp. 91,600.00
= Rp. 100,000.00
= Rp. 131,400.00
= Rp. 89,850.00
= Rp. 5,455,350.00
= Rp. 36,369.00

23,985.49

= Rp. 2,163,744.00
= Rp. 540,936.00
= Rp. 37,500.00
= Rp. 500,000.00
= Rp. 91,600.00
= Rp. 100,000.00
= Rp. 109,200.00
= Rp. 54,843.60
= Rp. 3,597,823.60
= Rp. 23,985.49

33,558.13

= Rp. 1,035,646.56
= Rp. 326,036.88
= Rp. 146,984.76
= Rp. 50,531.36
= Rp. 3,115,811.28
= Rp. 165,000.00
= Rp. 12,000.00
= Rp. 600,000.00
= Rp. 37,500.00
= Rp. 50,000.00
= Rp. 50,000.00
= Rp. 50,000.00
= Rp. 131,400.00
= Rp. 239,500.00
= Rp. 30,052.05
= Rp. 6,040,462.90
= Rp. 33,558.13

24,101.38

= Rp. 849,787.50
= Rp. 236,081.25
= Rp. 3,262,500.00
= Rp. 412,500.00
= Rp. 24,000.00
= Rp. 700,000.00
= Rp. 37,500.00
= Rp. 50,000.00
= Rp. 50,000.00
= Rp. 50,000.00
= Rp. 131,400.00
= Rp. 191,600.00
= Rp. 29,976.84
= Rp. 6,025,345.59
= Rp. 24,101.38

Assisten Perencanaan
mbangan Sarana dan Prasarana Permukiman
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

54,528.13
= Rp. 20,970.00
= Rp. 33,558.13
= Rp. 54,528.13

69,056.87
= Rp. 20,970.00
= Rp. 23,985.49
= Rp. 24,101.38
= Rp. 69,056.87

30,675.11
= Rp. 19,740.00
= Rp. 5,830.00
= Rp. 2,500.00
= Rp. 1,915.00
= Rp. 37.50
= Rp. 500.00
= Rp. 152.61
= Rp. 30,675.11

= Rp. 30,675.11 30,675.11


= Rp. 27,607.60 27,607.60
= Rp. 24,540.09 24,540.09
= Rp. 21,472.58 21,472.58

101,374.24
= Rp. 6,772.50
= Rp. 12,219.60
= Rp. 65,376.30
= Rp. 5,000.00
= Rp. 1,915.00
= Rp. 375.00
= Rp. 500.00
= Rp. 9,215.84
= Rp. 101,374.24

32,716.88
= Rp. 12,582.00
= Rp. 20,134.88
= Rp. 32,716.88

41,434.12
= Rp. 12,582.00
= Rp. 14,391.29
= Rp. 14,460.83
= Rp. 41,434.12

44,886.97
= Rp. 13,630.50
= Rp. 15,590.57
= Rp. 15,665.90
= Rp. 44,886.97

Assisten Perencanaan
mbangan Sarana dan Prasarana Permukiman
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568

= Rp. 4,132.80
= Rp. 1,653.75
= Rp. 91,388.10
= Rp. 15,086.38
= Rp. 16,320.00
= Rp. 500.00

129,081.03
129,080.00

Jumlah

= Rp. 71,956.47
= Rp. 15,579.06
= Rp. 72,304.15
= Rp. 1,001.00

160,840.68
160,840.00

Jumlah

= Rp. 106,924.86
= Rp. 83,949.22
= Rp. 18,175.57
= Rp. 84,354.84
= Rp. 3,300.00

296,704.48
296,700.00

Jumlah

= Rp. 83,880.00
= Rp. 95,941.96
= Rp. 20,772.08
= Rp. 96,405.53
= Rp. 6,800.00
303,799.57
303,790.00

= Rp. 4,132.80
= Rp. 1,653.75
= Rp. 91,388.10
= Rp. 15,086.38
= Rp. 16,320.00
= Rp. 5,225.00

133,806.03
133,800.00

Perencanaan
rana dan Prasarana Permukiman
No Uraian Pekerjaan Harga Satuan Jumlah

No Uraian Pekerjaan Harga Satuan Jumlah

1 M' Pekerjaan Jalan Penetrasi


Lebar Perkerasan 4.00 meter
4.00 meter Lapisan Pondasi Bawah Onderlagh 15 Cm = Rp. 20,970.00 = Rp. 83,880.00
4.00 meter Lapisan pondasi atas Stenslagh t =7 cm = Rp. 23,985.49 = Rp. 95,941.96
4.00 meter Lapisan resap pengikat ( Prime Coate ) = Rp. 5,193.02 = Rp. 20,772.08
4.00 meter Lapisan Penetrasi t=3 cm = Rp. 24,101.38 = Rp. 96,405.53
1.00 ls Perapihan = Rp. 6,800.00 = Rp. 6,800.00

Jumlah 303,799.57
Dibulatkan 303,790.00

1 M' Pekerjaan Saluran

0.210 m3 Galian tanah 19,680.00 = Rp. 4,132.80


0.210 m3 Buang tanah galian 7,875.00 = Rp. 1,653.75
0.190 m3 Pasangan batu kali 1:4 480,990.00 = Rp. 91,388.10
0.551 m2 Siaran 1:4 27,380.00 = Rp. 15,086.38
0.600 m2 Plesteran 1:4 27,200.00 = Rp. 16,320.00
1 ls Perapihan 5,225.00 = Rp. 5,225.00

Jumlah 133,806.03
Dibulatkan 133,800.00

Assisten Perencanaan
Proyek Pengembangan Sarana dan Prasarana Permukiman
Jawa Barat

Ir. Ady Rachmat


Nip 110 054 568