Levels of a programme / schedule, number 1

By John Keeton
23rd May 2005

When producing programmes for a project, I use the following levels of programmes:

LEVEL 1 : Project Management overview schedule/programme, by Project Phase.

LEVEL 2 : Area or Process/Utility Unit schedule/programme, by Project Phase by Area


or Unit.

LEVEL 3 : Discipline schedule/programme, by Project Phase by Area/Unit by Single or


Multi-disciplines.

LEVEL 4 : Main Activities schedule/programme, by Project Phase by Area/Unit by Single


or Multi-disciplines by Main Activities.

LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit by


Single or Multi-disciplines by Detail Activities.

LEVEL 6 : Micro-detail Activities schedule/programme, by Project Phase by Area/Unit by


Single or Multi-disciplines by Micro-detail Activities.

Levels of a programme_schedule.doc