Chilled water pipe flushing schedule
Description start date End date
Welding works completion - 1/2/2018
Initial Static flushing 1/3/2018 1/5/2018
Dynamic flushing 1/6/2018 1/9/2018
Chemical flushing 1/10/2018 1/13/2018
Final Inhibition 1/14/2018 1/16/2018
Chiller start-up 1/17/2018 1/18/2018
Total working days
No. of working days

2
3
3
2
1
11