Professional Documents
Culture Documents
Method of Statement For Construction of Plunge Column in Station
Method of Statement For Construction of Plunge Column in Station
PROJECT: Design and Construction of Tunnel between Chand Pole and Badi Chouper and
reversal line by Shield TBM, Underground Metro Stations at Choti Chouper &
Badi Chouper by Cut & Cover Method on East-West Corridor of Jaipur Metro
(Phase 1B) at Jaipur, Rajasthan, India.
LOCATION: JAIPUR
Project Manager
RV AKASH
GANGA Senior Manager Chief Manager
INFRASTRUCTURE DGM-Planning QA/QC HSE
Construction Pvt. Department, DPM STATION, Department, Department, Project Leader
Ltd. CEC CEC CEC CEC CEC
Page 1
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
Table of Contents
Sr. No. Description Page No.
1.0 Purpose 03
2.0 Scope of Work 03
3.0 Site Establishment & Setting Out 03
4.0 Major Resources to be Deployed 04
4.1 Equipment to be Deployed 04
4.2 Manpower to be deployed 04
5.0 Materials 04
6.0 Responsibility and Authority 05
7.0 Construction Procedure 06
7.1 Traffic Management and Barricading 06
7.2 SHE Measures 06
7.3 Design & Drawings 07
7.4 Site Establishment 07
7.5 Surveying 07
7.6 Pre Trench 08
7.7 Plunge column boring 08
7.8 Muck Disposal 09
7.9 Preparation of Rebar Cage 10
7.10 Concreting 12
8.0 Quality Control / Control Assurance 12
9.0 Environmental Management 12
10.0 Safety and Emergency Procedure 13
11.0 Attachments 13
Page 2
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
1.0 PURPOSE
This Method Statement describes the construction process of 1500 mm diameter Plunge columns
in station areas.
Page 3
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
1 Construction Manager 1
2 Site Engineer 2
3 QC Engineer (Field and Lab) 1
4 Mechanical Engineer 1
5 Surveyor 1
6 Foreman 1
7 Supervisor 4
8 Electrician 2
9 Safety Officer 2
10 Mechanic 2
5.0 MATERIALS
Concrete as per Approved mix design M35 Grade.
Reinforcement – Steel conforming to specification
Polymer (from approved supplier)
Page 4
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
Page 5
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
6.7 Surveyor
Carry out setting up works and locate as per submission drawings.
Carry out inspection for location and level of structure.
Keep monitoring the movement of ground and structure.
6.8 QC Engineer
Ensure works are carried out in accordance with specification.
Carry out inspection for all activities in accordance with the Inspection and Test plan.
He shall be responsible to prepare the method statement in co-ordination with Design, Safety &
Quality and enclose Inspection and Test Plan and risk assessment. He shall review the method
statement as per site requirement.
7. CONSTRUCTION PROCEDURE
Page 6
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
7.5 Surveying
Upon clearing the site area, the setting outpoints shall be marked for the subjected Plunge Column
panel and with reference to that guide wall, points shall be marked through requisite survey.
Reference pillars shall be always preserved for checking of constructed guide wall at later stage. All
Page 7
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
Page 9
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
(Details of Polymer Batching Plant mix is shown in Annexure - B)The polymer characteristics shall
be checked with respect to the following prescribed values:
Permissible Value
Sr.
Test Prior to concrete
No. Fresh mix Reused Slurry
pour
2 pH Value 11 to 12 11 to 12 9-12
Marsh Cone
3 55-140 55-140 50-140
Viscosity API (s)
Page 10
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
1. Cutting / Shearing of Rebar’s : The bars with improper ends like bent, too much heated, improper
manufactured ends etc., are cut with Bandsaw machine or sheared with shearing machine. This is
done in order to achieve a flat surface for further forging of the rebar. Also the face of the rebar
becomes perpendicular to the axis of the bar. This flat face also helps in abutment of two rebar when
in contact with each other.
Page 12
CEC - UG1B CONTRACT: ICB No. :-JP/EW/1B/C1 JAIPUR METRO RAIL
CORPORATION LIMITED
METHOD STATEMENT FOR CONSTRUCTION CONTRACT UG1B
OF PLUNGE COLUMN IN STATION
DOC NO: PR/JMRC/MS/UG1B/PHOF/14-R0
Date: 14-03-2015
The construction shall also involve the removal of earth from site to dumping areas by dumpers
that shall use the public roads. During transportation the dumpers shall be covered by tarpaulins.
The muck shall be disposed during the night hours only and one supervisory level staff shall be
engaged permanently at dumping yard with JCB for leveling the upcoming soil leveling, while
dumping the soil.
Simultaneously the area leveling and shall create a proper way for soil dumping. The used polymer
slurry shall be transported in dumpers.
The washing bay shall be installed near each exit gate. These washing bays are of improved design
using a heavy-duty pump having high head and large discharge. The tires and the undercarriage of
the vehicles shall be washed before the vehicle leaves the working area for dumping site. In case
water is not available due to water scarcity, tire shall be cleaned manually with wire brush.
Required persons shall be engaged to clean the sides of the vehicles manually. The working area
shall be kept clean and tidy.
11. Attachments
I) INSPECTION AND TEST PLAN
Inspection and Test Plans attached as annexure D
II) FORMAT/ CHECKLIST
1. Inspection Checklist for Plunge Column - Annexure El
2. Reinforcement Inspection Checklist - Annexure E2
3. Plunge Column concrete pour card - Annexure E3
4. Concrete Pre Pour Card - Annexure E4
5. Plunge Column Boring Excavation Record - Annexure E6
6. Plunge Column Boring Construction Record - Annexure E7
7. Inspection Checklist for Poly Mud Slurry - Annexure E8
8. Concrete Pouring Records – Annexure E10
9. Properties of Polymer slurry - Annexure E11
10. Welding Inspection check list-Annexure E12
11. Risk Assessment – Annexure K
Page 13