ZED Towers PROJECT‐PHASE 01B

SHEIKH ZAYED CITY‐EGYPT


METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 1 of 10
 

 
PROJECT
  ZED Towers PROJECT‐PHASE 01B
                      SHEIKH ZAYED CITY‐EGYPT 

 
Employer

Engineer

CONSTRUCTION SUPERVISION

  

 1
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 2 of 10
 
 
Method Statement

  R.C Slabs &Beams Works
  SCOPE:

The aim of this method statement is to provide and maintain an effective quality control to execute the 
work in compliance to standard and good practices at all This General method statement describes the 
methodology to be employed in the safe (Pouring R.C Slabs &Beams Works). 

 This method statement covers all sequence of the work to be carried out for (Pouring of R.C Slabs 
&Beams Works). 

  SPECIFICATION REFERENCES:
‐ Egyp an code of prac ce for design and construc on reinforced concrete ECP 203‐
2017.  
‐ ACI 304, 318. 
‐ Project specifica on volume III, division 3, sec on 033000 
‐ Contract /IFC drawings. 
‐ Manufacture’s recommendation according to approved Material Submittals. 
‐ Project HSE Plan and Procedures. 
 

  RESPONSIBILITIES
The direct personnel responsible for the works are Section Engineers; the section engineer is responsible 
for compliance by his subordinates with the contents of this method statement, for ensuring that all 
  parties involved in supervision of the works are in receipt of all relevant information. 

The section engineer will ensure the required degree of safety to personnel and protection to property 
  is maintained at all times.

The Project Manager / Construction Manager shall be responsible to: 

o Communicate this method statement to all Engineers, Senior Surveyor, Surveyors, 
supervisors and employees. 
o Provide them with the information they need to carry out their responsibilities. 
o Enforce  the  application  of  this  document  once  it  has  been  effectively 
communicated to employees. 
o Responsible for the safe execution of the works. 
 2
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 3 of 10
 
o Project Engineer shall be responsible to: 
o Implement and maintain a successful completion of the work. 
o Ensure that this method statement is being implemented correctly. 
o Ensure that sufficient resources are allocated to enable full compliance with this 
document. 
o Ensure  that  all  construction  works  are  being  carried  out  as  per  project 
specifications and IFC drawing. 
o Keep all his personnel fully aware of the quality control principles and he shall 
provide all support to the project Quality Control Department. 
o Responsible for the safety and the quality of work carried out by all site personnel 
under his control including sub‐contractors and suppliers. 
o Interpreting  contract  drawing  and  specifications  and  being  familiar  with  all 
provisions of the contract and any revisions or amendments. 
o Records and control of production documentation. 
o Ensure  that  staff  under  his  control  areas  are  experienced  and  trained  in  their 
relevant disciplines. 
o Designate the competent person to carry out or himself carry out jointly with the 
HSE Officer of the area the daily excavation inspection and complete the checklist 
and co‐sign it with the HSE officer of the area. 
                     Supervisor / Foremen shall be responsible to: 
o Directly be in charge in the execution of activities.  
o Takes  instruction  from  the  Superintendent  and  communicates  directly  to 
Foreman, Workforce and drivers. 
o Ensure also that the working area is safe for the workers and equipment. 
o Daily and for each task conduct a STARRT briefing to his work crew to ensure that 
the task is properly explained, the hazards associated with each step are identified 
and the control measures for these hazards are identified and implemented. 
o Conduct daily Toolbox talks to his workers. 
HSE officer shall be responsible to: 
o Ensure that toolbox talks are conducted as per HSE plan by the activity supervisor. 
o Monitor  against  the  implementation  of  the  requirements  of  this  Method 
Statement. 
o Provide the required training for the site personnel involved. 
o Advise the construction personnel regarding compliance with the project HSE Plan 
and Procedures. 

 3
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 4 of 10
 
o Monitor to ensure compliance with procedures with respect to equipment’s and 
related certifications and permits. Stop work activities in case non compliances 
are observed and notify the engineer in charge to rectify. 
 

                        QA / QC Engineer shall be responsible to: 
o Discuss inspection schedule and the result with those responsible for works and 
recommended necessary corrective actions if applicable. 
o Discard or reject products, material and equipment not meeting specifications. 
o Inspect test and sample materials or assembled parts or products for defects and 
deviations for specifications. 
o Observe  and  monitor  production  operations  and  equipment’s  to  ensure 
conformance  to  specifications  and  make  order  necessary  process  or  assembly 
adjustment. 
o To check and ensure that the work is done as per project specification, method 
statement and as per approved shop drawing. 
o To ensure that all approved and inspected materials are used. 
o To raise NCR and initiate corrective actions if the work done is not as per approved 
specification, method statement or as per approved shop drawing. 
o Witnessing of all site inspections within their discipline. 
o Coordinate all site inspection with the sub‐contractors designated site engineer 
or section engineer. 
o Ensure all work is correctly prepared prior to inspection being undertaken. 
o Review all inspection reports for compliance. 
Senior Site Engineer: -

o Assigning site engineers to specific task and ensuring that tasks are performed
according to the projects plans and specifications.

Laboratory Technician: -

o Sampling of fresh concrete samples as applicable.


o Maintenance of materials prior to testing.
o Testing of hard concrete specimens and reporting of results.

 4
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 5 of 10
 
Site Engineers: -

o Notifying Quality Control Engineer when work is ready for inspection Liaison with
Mechanical, Electrical and Plumbing trades foremen for marking out and
installation of embedded items.

Surveyor: -

o Make exact measurements and determine property boundaries. Provide data


relevant to the shape, contour, gravitation, location, elevation, or dimension of
land or land features on or near the earth's surface for engineering, mapmaking,
mining, land evaluation, construction, and other purposes.

MATERIALS STORAGE:
In the event that any materials for use in this chapter deteriorate and become unusable due to 
  inadequate and poor storage they shall be removed from site as instructed by the Engineer.

  Products:

1- Reinforcement steel according to approved material submittal.


2- Reinforced concrete (400 kg/cm2) according to approved submittal for mix
design.
3- Curing material according to approved material submittal.
4- Formwork according to approved submittal.
5- Bonding agent material according to approved material submittal.
6- Approved Release agent according to approved material submittal.
7- Nails.
8- Wire ties.
9- Concrete repair material according to approved material submittal.

EQUIPMENT
Depending on the size of the area, site conditions and accessibility, some / all of
the following equipment shall be used as applicable for:

 Surveying Equipment’s
 Hand Tools
 Air Compressor
 Electrical Table saw
 Form work cutting power machine
 Concrete Batching plant, Wheel Loader

 5
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 6 of 10
 
 Transit Mixers, Concrete Vibrator
 Concrete Pump, Concrete bucket
 Concrete Testing Equipment
 Water Jet Machine

MANPOWER
Manpower allocated to this job will be as follows:
 Site Engineers
 Superintendent, General Foreman, Supervisor and Charge
Hands.
 HSE Officer
 Surveyor and chainman
 Carpenter, steel fixer, Mason and Labors
 Operators, drivers and Riggers
 Lab Technician
 Labors
 Flagman
 QC Inspectors

Procedure for casting reinforced concrete for R.C Slabs &Beams works
(400 kg/cm2): -

1‐ Survey work:  

 Mark the lines and levels of the slabs to be casting.


 Ensure levels for final casting as per IFC drawings &approved concrete
dimension SD.
 Check level, coordinates and alignment of formworks.

  
 6
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 7 of 10
 
2‐ Form Work: 

 Form works will be constructed according to the R.C Slabs &Beams structural levels 
indicated in the approved shop drawings& approved formwork design. 
 Scaffolding will be constructed according to the reinforced slab structural levels
indicated in the approved shop drawings and IFC drawings and approved formwork
design. 
  Decking of slabs started after finalizing of supporting system over the shore system.
 Plywood shall be spread over span using plywood sheet 18 mm thickness creating
the flat slabs with its drop panel at intersection &outer wall strips.
 Adequate supports will be used to support the formworks to support and achieve the
required levels.
 Form works will be accurately levelled with sharp.
 Joints and gaps in formworks will be tightly closed to avoid any losses.
 Form works internal faces will be cleaned and painted with suitable releasing agent
to avoid any adhesion between the formworks and the concrete during the removing
of formworks. 

3‐ Reinforcement Steel:

 Steel bars lengths; bends and lap lengths will be fabricated according to the
approved shop drawings and approved bending schedules (BBS).
 Clean the starter bar from cement paste or grout.

 Bottom mesh and additional bottom bars will be fixed using annealed wire ties
according to locations and spaces shown in the approved shop drawings. 

 After completing the bottom layer of slab reinforcement allow MEP works to lay the 
concealed services. 

 Tie the reinforcement bars at both ends to maintain the spacing. 

 Install bar chairs acting as spacers between top and bottom reinforcements. 

 Top mesh and dowels bars will be fixed using annealed wire ties according to
locations and spaces shown in the approved shop drawings.
 Install additional slab reinforcement if there is any.

 Spacers will be used to maintain and achieve the required concrete covers
(according to location).
 After completing the slab top reinforcements, clean and blow away the dust by using
compressed air.

 7
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 8 of 10
 

4‐ Cas ng Reinforced Concrete (400 Kg/cm2) 

 Before placing concrete, the form works will be cleaned thoroughly, steel bars will be
checked, free from rust, stains or any other materials that may affect the bond
between the bars and concrete.
 Before casting concrete cleaning will be done using Compressor air.
 Surveyor shall make the lines and levels of the area to be pouring with reference to
approved control points and benchmarks.
 Timber battens shall be installed around the perimeter of the areas to be casting.
The timber battens shall be kept in required profiles and elevations.
 Water spraying of formworks prior to concrete placing.
 Reference levels for top of the concrete shall be provided at the edges of the
reinforced concrete areas. Concrete guide point shall be provided at intermediate
areas as guide for levels for the required elevation. The surveyor shall cross check
the reference while pouring.
 Reinforced concrete shall be grade C40 (400 kg/cm2) as stated in Drawings & Specs.
 All the Shovels and hand tools shall be cleaned with water before and after
concreting.
 Where accessible, concrete shall be poured directly from the Transit mixer to pump.
Pump hose shall be kept as close as possible to the point of delivery to avoid
segregation.
 Concrete shall be laid uniformly to cover the required area, starting along the
transverse direction of the pouring areas, and then moving towards the longitudinal
direction.
 Concrete shall be pumped vertically from the pump hose to prevent segregation.
 Concrete shall be properly distributed and compacting with vibrators uniformly to
obtain homogeneous dense surface. Excess concrete shall spread by tools.
 Concrete fall from high distance will be prevented by using flexible hose connection
inside concrete element.
 Each layer shall be compacted so as to avoid the formation of construction joint with
the previous layer which has not taken initial settlement.
 Casting will be done from lower level to upper level.
 Concrete cover to be maintained as per drawing during casting operation.
 The final working up to the surface shall be done by 2"x4” aluminum sections to
obtain surface free irregularities.
 Surface finishes shall be done as per Spec.

 8
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 9 of 10
 

    5‐ Concrete Repairs 

 Areas requiring repair shall be highlighted during the post‐concreting inspection and recorded 
on the relevant Concreting Record check‐sheet. 
 Senior Site Engineers shall determine the appropriate standard repair method and materials. 
 Foreman shall ensure that required repairs are undertaken by competent persons only, using 
the methods and materials determined by Senior Site Engineers. 
 Manufacturers’ literature shall be made available for reference of site personnel. 
 As the acceptability of repairs generally relates to their aesthetics no testing of repairs shall 
generally, be required however all shall be subject to approval by the Consultant. 
 Repair materials used shall be covered by compliance certification, third party registration 
schemes or periodic test results. 
 
 
 

    6‐ Removal of Formwork sides& structural elements that support weight of concrete: 

 Carry out the de‐shu ering works for the side only a er 24hr from the  me of the concrete is 


placed. 
 The minimum period of time that shall elapse between pouring concrete and removal of forms 
shall be in no case less than the age shown in ECP 203‐2018. 
 In no circumstances shall forms of structural elements that support weight of concrete be 
removed and struck un l concrete reaches a cube strength of at least seventy five percent (75%) 
of the concrete characteristic strength. 

    7‐ Upon Work Completion: 

 The Site Engineer and QC Engineer shall ensure that the Concreting Record check‐sheet is 
completed immediately, concrete samples are taken and the concrete surface is properly 
finished, and curing operation is running as specified. 

    8‐ Curing: 

 Curing shall be started immediately after initial set of concrete by approved curing compound 
material. 

 9
 
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
METHOD STATEMENT Ref MS-08 Rev 00
FOR R.C Slabs &Beams Works Date 15/11/ 2020 Page 10 of 10
 
  Safety:

All safety and health regulations shall be strictly followed and any case disregarding the safety 
procedures to be immediately reported to safety office and construction manager. 

Risk assessment will be submitted separately.

  INSPECTION And Test PLAN:  Attached
 