PROJECT
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
Employer
Engineer
CONSTRUCTION SUPERVISION
1
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
2 of 9 Page 25/10/ 2020 Date
Works
Method Statement
To ensure the management for the erection work on customer job site safety, correctly and comply
Applied to all job site with products supplied by E3M FOR METAL INDUSTRIAL.
:SPECIFICATION REFERENCES
- Egyptian code of practice for design and construction reinforced concrete ECP 203-
2017.
- ACI 304, 318.
- Code of Standard Practices for Steel Building and Bridges section 7 ((AISC)
- Project specification volume III, division 3, section 033000
- Contract /IFC drawings.
- Manufacture’s recommendation according to approved Material Submittals.
RESPONSIBILITIES
The direct personnel responsible for the works are Section Engineers; the section engineer is responsible
for compliance by his subordinates with the contents of this method statement, for ensuring that all
.parties involved in supervision of the works are in receipt of all relevant information
The section engineer will ensure the required degree of safety to personnel and protection to property
.is maintained at all times
3
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
4 of 9 Page 25/10/ 2020 Date
Works
o Advise the construction personnel regarding compliance with the project HSE
Plan and Procedures.
o Monitor to ensure compliance with procedures with respect to equipment’s and
related certifications and permits. Stop work activities in case non compliances
are observed and notify the engineer in charge to rectify.
o Assigning site engineers to specific task and ensuring that tasks are performed
according to the projects plans and specifications.
Laboratory Technician: -
4
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
5 of 9 Page 25/10/ 2020 Date
Works
Site Engineers: -
Surveyor: -
Erection Superintendent
o Reporting
o The Erection Superintendent is to report to the Site Manager and
Project Manager
o Main Responsibilities
o Monitoring the Erection team to make sure the Erection work was
processed in line with project
o schedule, designed quality and approved safety procedures.
o Follow the ITP, checklist to carry out site inspection with the
Erection Team to make sure all
o inspection steps were done adequately.
o Liaise closely with the Civil contractor to raise timely any of
disagreement was found.
o Sign off acceptances with Client inspector for the E3M’s works
done on site
o Prepare Site daily report for his scope of works.
Erection Team
o Reporting
o To report to the Erection Superintendents.
5
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
6 of 9 Page 25/10/ 2020 Date
Works
o Main Responsibilities
o Process the Erection work in line with project schedule, designed
quality and approved safety
o procedures.
o Follow strictly all instructions of Erection Superintendents.
o Prepare adequately, qualified labors, machines, equipments to
process the Erection effectively.
o Organize and monitor all team members about every aspect.
o Prepare toolbox meeting, safety training course to train team
members about safety.
o Every day morning, enter the Safety Tool Box Meeting with the Safety
Officer before starting the Work.
o Organize the work for groups in day to day operation.
o Performs 100% pre-checks and pre-inspections before the Site
Supervisor do the official checks and inspections.
o Make sure there is space and firmed pathway for truck delivery,
crane truck erection operation. The suitable truck & crane capacity
must be clarified.
o Survey the wind direction to have plan for roof material storage
and installation direction.
o Decide the plan for unloading and material storage. Choose a firm
and dry location. Materials shall be stored in designated areas for
each building and clearly identified for their location in that area.
o Make sure that materials supply and storage schedule is
appropriate and not conflict with the installation schedule and
other sub- contractors' schedules.
6
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
7 of 9 Page 25/10/ 2020 Date
Works
7
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
8 of 9 Page 25/10/ 2020 Date
Works
Sequence of Erection -3
The structural frames and other parts of the item such as (Banners, hunger,.etc.)
can be erected in various ways which will
o The type of structures such as: small clear span, large clear
span, low rise building, high building, taper I structure,
open-web structure, etc.…
o The availability of equipment such as cranes, winch,
manually lift, etc.…
o The site conditions.
o The experience level of the erectors.
o The individual job conditions.
o The sequence/method of erection shall be studied and
planned so that execution can be carried out in a safe,
economical and efficient manner.
o There are certain erection practices which are in general use
and have proven sound over the years.
8
ZED Towers PROJECT‐PHASE 01B
SHEIKH ZAYED CITY‐EGYPT
00 Rev MS-03 Ref METHOD STATEMENT
FOR steel structure activity at mobilization
9 of 9 Page 25/10/ 2020 Date
Works