WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
General
Larsen & Toubro Ltd.
CONTRACTOR
Signature
Name :
Date :
REVISION RECORDS
2
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
CONTENTS
3
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
S. CONTENT PAGE
REMARKS
No. NUMBER
01 Objective 5
02 Scope 5
03 Reference Documents 5
05 Responsibility 6-7
07 ABBREVIATIONS 11
1.0 OBJECTIVE
The objective of generating this Method Statement is to define the procedure step by
step to implement the correct practices for Cable Tray, through guidelines so as to
ensure that the job execution complies with the requirements of contract specifications
and serves the intended function to satisfactory level.
2.0 SCOPE
This Method Statement refers to the work procedures contained within Netelec Project
Quality Plan & Contract Specifications, which explains and covers the Internal
Electrification works.
4
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
5
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
t. Vernier Caliper
u. Electrical Tool Kit
5.0 RESPONSIBILITY
Project Managers:
Engineer-In charge:
a. Ensure all required submittals are made and required plant / tools / material
and manpower are available in a timely manner.
b. Ensure execution of all works are carried out according to approvals, contract
specifications, Mock up approvals, approved shop drawings, Project Quality
Plan, Method Statement and that safety measures are implemented.
c. Ensure necessary coordination with GC Management / OE & PMC
Representatives and other Agencies for timely completion of works.
Site Engineer:
a. Timely provision of complete relevant information, Consultant approved
documents and instructions to site execution / installation team.
b. Proper execution of works as per approved material submittals, approved
Method Statements, Approved Construction drawings and adopt all safety
measures as required.
c. The implementation of the procedures mentioned in method statement shall
be ensured by concerned Site Engineer / Site Supervisor.
d. To carryout site work activities with regard to Quality and Safety
requirements, Conducting Tool Box Talks to the site workers and
coordinating with concerned Quality & Safety Engineer.
6
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
Safety Engineer:
Quality Engineer:
7
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
Preparation Work :
8
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
Installation Procedure:
The total cable route shall be inspected to ensure that the routing is complete,
ether on ground or on cable trays, as per approved layout and free from any
sharp edges & sharp objects.
As per cable cutting schedule, site electrical supervisor will ensure that the
cable drums are shifted to the correct location, where cabling has to started for
any particular feeder.
The trays shall be curved enough at the right angles to allow to lay the cable
with correct bending radius, with out any sharp bends, knits.
Where more power cables are run together, Adequate cable tray should be
provided considering the spacing as per specification. Spaced apart by at
least one cable diameter (of larger cable) throughout the length of the cable
run.)
Cable rollers shall be placed inside trench / on cable tray inline and angle
rollers will be used at all the turnings of trench / on cable tray.
Cable laying shall be started by rotating the drum in a direction
recommended by manufacturer and as indicated on drums. The site
supervision team will ensure that the undue stress on pull is not applied to
cable, while laying the cables.
Cables shall be identified at the both ends and in between convenience
interval on riser, identification bands as per approved material and approved
cable schedule.
Cables shall be dressed properly, Secure cables to cable tray using straps /
heavy duty ties where the cables are fixed to a vertical cable tray or ties where
the cable tray surface is horizontal, without any overlapping. Ensure that the
cable distance is maintained as per approved shop drawing, as per
manufacturer’s recommendations and as per general engineering practices.
Earth conductor shall be laid parallel along with cables and tied along with the
cable at suitable intervals.
Where cables passes through a floor or wall, sealing material should be
provided and that area should be sealed properly (from both sides).
On completion of cable laying and dressing, continuity and insulation
resistance tests with (1000 V Insulation tester ) shall be carried out and shall
be recorded. Cable ends shall be sealed properly, till the glanding and
termination.
All conductors requiring bolted connection shall be terminated with
compression lugs using an automatic compression crimping type tool.
Cable lugs shall be tinned copper compression type.
9
WIPRO IT SEZ DOC NO:ME/ELECT/MS/05
Rev 0
7.0 ABBREVIATIONS:
MS – Method Statement
FQP – Field Quality Plan
ICL – Installation Check List
CCL – Commissioning Check list
MHS – Material Handling System Checklist
MQAP – Manufacturer Quality Assurance Plan
10