Professional Documents
Culture Documents
CLIENT:THALES
METHOD OF STATEMENT
FOR CABLE TRAY & TRUNKING
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 2 of 8
INDEX
I. PURPOSE
II. SCOPE
III. REFERENCES
IV. SAFETY
V. RESPONSIBILITIES
VI. TOOLS & EQUIPMENT
VII. EXECUTION OF WORKS
VIII. QUALITY CONTROL PROCEDURE
IX. ENVIRONMENTAL
X. EMERGENCY PROCEDURE
XI. ATTACHMENTS
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 3 of 8
I. PURPOSE
The purpose of generating this Method Statement is to define the procedure step by step to
implement the correct practices for Installation of PVC & GI conduits & Accessories through the
guidelines contained herein so as to ensure that the job execution complies with the requirements
and serves the intended function to satisfactory level.
II. SCOPE
This work will be carried out by JAZAL Engineering & Contracting LLC.
III. REFERENCES
Project Specification
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 18/08/2023
Trunking
Page: 4 of 8
IV. SAFETY
All individual operation will be set up and expedited to ensure the compliance with project
approved HSE Management Plan.
Workers should use proper Personal Protection Equipment.
Workers will be advised of hazards (Tool Box Talks) prior to start the activities.
Suitable and sufficient sign boards shall be provided (traffic sign, mandatory sign,
prohibition sign warning sign; emergency contact numbers sign boards etc.)
Only qualified and experienced personnel will conduct the operation.
The safety of the works will be closely monitored by Competent Safety Officer.
Approved method statement and task specific risk assessment shall be followed.
Daily inspection of the equipment involved must be implemented, resourced and recorded.
Temporary rest shelter and drinking water must be arranged at site, but with safe from any
construction activities.
Manual handling training to be conducted for all workers prior to the works.
V. RESPONSIBILITIES
a) Project Manager shall be responsible for the implementation of this method statement.
b) Project Manager is responsible to co-ordinate with the main contractor for obtaining necessary and
essential work permits - if any, for proceeding with the works.
c) Project Manager / Project Engineer will ensure that the Resources are available to carry out the
works as scheduled.
d) The Project Engineer / Site Engineer are responsible to carry out the works as per approved Shop
Drawings, Method statements.
e) The Site Engineer / Supervisor are responsible to ensure that the work has been carried out as per
drawings and inspections are done as per contract.
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 5 of 8
VII. MATERIALS
The Cable Tray & Trunking materials shall be in line with the approved Material submittal.
Any cable trays/ladders & trunking material delivered at site shall be carefully off-loaded by
crane and deploying necessary / adequate manpower in such a way that no damage is
caused.
Cable trays/ladders and trunking material shall be handled and stored properly at allocated
location of site.
It shall be ensured that the delivered cable trays/ladders and trunking are in compliance
with approved material submittals.
Cables trays/ladders and trunking materials shall be stored carefully to avoid any damages
due to constructional activities in a place free of water and dust.
Any discrepancies, damages etc found shall be notified and reported for further action.
Material found not suitable for site use shall be removed from site immediately.
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 6 of 8
To carry out installation activities for Cable trays, Ladders & trunking, below mentioned
procedure shall be followed step by step in sequential manner.
Preparation of work
Prior to start installation, refer the approved shop drawing related to the installation area
and ensure that required material is available at store as per approved material submittals.
While issuing from site store, ensure that the materials are free of any damage or deformity
of any kind.
Any minor damages observed (for trays/ladders / trunkings) will be repaired suitably and in
case the repairs could not be done properly, the material has to be rejected for
replacement.
Ensure tray/ladders/ trunking routes are clear to start and co-ordinated with other services,
if any in the concerned areas.
Ensure Cable tray/ladders and trunking schedule is made available with the supervisors at
site.
All drilling or cut ends of site fabricated items should be cleaned-up and treated with zinc
rich paint before installation.
Ensure cable trays/ladders & trunking which are planned for installation are available at the
location of installation.
Prior to start of the installation works, make sure that shop drawing of the area is approved
& issued for construction and ensure that only approved shop drawings with correct
revisions are followed, while taking-up any installation activity at site
Ensure that correct sizes and right type of accessories are drawn from site stores for the
programmed portion of job.
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 7 of 8
Ensure that all civil works including finishes are completed for the area of installation and
released / cleared by civil section to proceed with cable tray / trunking installations. Also
ensure that the work area is clean and safe to take-up the activities.
Mark & line-out the route of Cable Tray/ladders/ Trunking as per approved shop drawing &
make final field measurement for assembly or fabricating the tray/ladders to suit the actual
site dimensions.
The route and levels should also be co-ordinated as necessary to interface installation of
Cable Tray/Ladders or Trunking with other works.
Install adequate supports / brackets to prevent sagging throughout the length of run, not
exceeding 1.8 meter so that any stresses on cable is prevented. Check all hardware
mountings are anchored firmly to walls, ceiling or floors and ensure all supports are
mechanically secured firmly.
The installation of Cable trays/ladders or trunking system shall be neat, straight & parallel to
building features so as to achieve overall good aesthetic look and finish of all installations.
Proper branching, permissible bending, cutting or drilling to facilitate branch joints, up and
down trunking, tee joints shall be done in proper professional manner. All cut, drilled and
filed surfaces will be treated with zinc rich paint.
Positive earth continuity shall be provided at each joint of Cable trays/ ladders and trunking
and they will be bonded to the main building earthing system.
The covering of trunking shall be done after the wiring is done including proper dressing and
tieing of wires.
All fixing will be so arranged that there are no projecting screw threads or similar points
within the tray / trunking, which may cause damage to the cables / conductors.
Cable tray / trunking passing through fire rated structural elements will be sealed with an
approved fire proof sealant.
Cable tray / trunking expansion joints will be provided, where they are crossing the building
expansion joints.
Client Consultant MEP Contractor
Document No.
Revision No.: 00
Method Statement for Installation of Cable Tray &
Date: 19/08/2023
Trunking
Page: 8 of 8
All works shall be ensured by the Project Manager and Site Engineer to conform with the
MS, specification and manufacturer recommendation.
Upon completion of the work, Inspection Request (WIR) shall be raised for consultant
approval.
QA/QC shall double check the work procedure along with the site team to ensure whether it
is compiled as per approved MS, project specification and manufacture recommendation.
QA/QC will invite the Engineer for work inspection at site.
Once WIR is approved, further activity will proceed.
If WIR is rejected, QA/QC immediately inform the site team to rectify the Engineer’s
comments. Once rectification completed, Work Inspection Request (WIR) shall be raised
again for consultant approval.
X. ENVIRONMENTAL
All waste shall be segregated and disposed as per waste management plan.
Dust shall be suppressed by water spraying as and when required.
Necessary dust bin or waste collection box will be provided to collect the wastages.
Appropriate drinking water shall be provided according to the man power.
Contractor will ensure emergency procedure as per the site HSE Plan.
All the chemicals shall be stored, handled and disposed as per MSDS only
XII. ATTACHMENTS
Risk Assessment
PROJECT: THALES HANGER FIT OUT WORKS IN ZONE 2
Ref.
No. ITEMS
Check By
JAZAL CAPITAL THALES
Ensure the installed cable tray/trunkings are as per
1 approved material submittals.
Ensure that the sizes of installed cable tray/trunkings are
2 correct as per approved shop drawing.
Ensure the installed cable tray/trunkings are free of
3 damage.
Ensure the route of the installed cable tray/trunkings are as
4 per approved shop drawings
5 Ensure proper supports are provided.
Ensure repair, cuts, splicing or fabrication have been made
6 good and there are no sharp edges.
Ensure proper touch up is done on location of cuts,
7 splicing or site fabrications.
Ensure the electrical continuity of the system is
8 maintained by providing earth link at joints
Ensure proper clearance is maintained from heat sources
9 and water services.
Ensure agreed and adjusted route being followed in case
10 of any clashes with other services.
Ensure over all good aesthetic installation and fine finish
11 is maintained in all installations.
Ensure expansion couplers are provided where cable
12 tray/trunkings crosses expansion joints.
Ensure proper sleeves and fire sealant are provided where
13 cable tray/trunkings crosses fire rated walls/floors.
Ensure that cable tray/trunkings/joints are electrically
14 bonded using flexible earth links.
Ensure that the access to the cable tray/trunkings is
15 sufficient for cable.
NAME
SIGNATURE
DATE
Jazal Engineering and Contracting LLC Doc Ref No JEC/Elec/RA‐2
Revision/ Issue
Doc. Ref No: JEC/Elec/RA‐2 Company Name Jazal Engineering and Contracting LLC
Date of Assessment 19/08/2023 Description of Installation of Cable Tray and Trunking (THALES)
Activity
Sl No HAZARD IDENTIFICATION RISK RISK CONTROL Residual Risk
EVALUATION
Work activity Hazard Consequences / Risk Control Measures Risk
Impact P S Level P S level
R=PXS R=PXS
1. Provision of proper light arrangement
2. Strict compliance to cable management
to avoid exposure to workers and
general public
Access/Egress Slip trip and fall 3. All materials shall properly store in
Poor lighting resulting to approved area away from walkway and
Preparation of
1 Poor injuries 3 2 6 access 1 2 2
work
housekeeping 4. Relevant signage’s and exclusion zone to
Trailing cables be provided to avoid entry of
unauthorized personnel
5. Proper housekeeping shall be done after
completion of each shift
1. Before commencing the work check all
power hand tools
2. Check the guard and wheels of the power
Electrocution hand tools
Electrical shock
Conduit pipe Eye injury 3. Double insulated machine shall be used
2 Flying objects 4 3 12 2 2 4
cutting Cut injury 4. Use adequate and appropriate PPEs for the
Sharp edges
Job
5. Work area shall be barricaded and warning
signage’s shall be displayed
Doc. Ref No: JEC/Elec/RA‐011
6. Only authorized personnel shall be use the
Jazal Engineering and Contracting LLC Doc Ref No JEC/Elec/RA‐2
Revision/ Issue
Consequence
Likelihood
Insignificant=1 Minor=2 Moderate=3 Major=4 Critical=5
Almost Certain=5 5 10 15 20 25
Likely=4 4 8 12 16 20
Unlikely=2 2 5 6 8 10
Rare=1 1 2 3 4 5
Minor injury requiring First Aid treatment Not likely to occur within the foreseeable future, or within the project
2. Minor 2. Unlikely
(e.g. minor cuts, bruises, bumps) lifecycle
3. Moderate Injury requiring medical treatment or lost time 3. Possible May occur within the foreseeable future, or within the project lifecycle
Serious injury (injuries) requiring specialist Likely to occur within the foreseeable future, or within the project
4. Major 4. Likely
medical treatment or hospitalisation lifecycle
Loss of life, permanent disability or multiple 5. Almost Almost certain to occur within the foreseeable future or within the
5. Critical
serious injuries Certain project lifecycle
How to control hazards.
By determining the consequences and likelihood of risks occurring, you can now, aim to eliminate, minimise and control the
hazards.
Use the hierarchy of control system to minimise or eliminate exposure to hazards. It is a widely accepted system promoted by
numerous safety organisations. Referring to the hierarchy will help you decide what controls to put in place to manage the hazards
once you have assessed their risk level.
Doc. Ref No: JEC/Elec/RA‐011
Jazal Engineering and Contracting LLC Doc Ref No JEC/Elec/RA‐2
Revision/ Issue
ELIMINATION Remove or stop the hazard if possible, remove the cause or source of the hazard, by
eliminating the machine, task or work process. If this is not practical, then
Eliminate the hazard substitute.
SUBSTITUTION Use a less hazardous process‐ use a less‐noisy machine for the task, or introduce a
Substitute the process less‐noisy work process. If this is not practical, then engineer.
ENGINEERING Introduce enclosures and barriers around or between the hazards. Improve
Change the equipment maintenance procedures. If this is not practical, then: